Artech Sreya - Progress

Work status as on 5-7-2017, we have completed.

  • RCC for Structure – completed
  • Block/Brick masonry – completed
  • Door frame fixing work – completed
  • Electrical chasing work – completed
  • Wall Plastering work – upto Terrace floor – completed
  • Outside plastering work – completed
  • Flooring and skirting – progressing
  • Inside Putty & primer work – progressing
  • Plumbing work – progressing

Work status as on 9-6-2017, we have completed.

  • RCC for Structure – completed
  • Block/Brick masonry – completed
  • Door frame fixing work – completed
  • Electrical chasing work – completed
  • Wall plastering work – completed
  • Outside plastering work – completed
  • Inside Putty & primer work – on progress
  • Outside Putty & primer work – all floors – on progress
  • Plumbing work – on progress

Work status as on 9-5-2017, we have completed.

  • RCC for Structure – completed
  • Block/Brick masonry – completed
  • Electrical chasing work – completed
  • Outside plastering work – completed
  • Flooring and skirting – progressing
  • Outside Putty & primer work -progressing

Work status as on 8-3-2017, we have completed.

  • RCC for Structure – 100% completed
  • Block/Brick masonry – 100% completed
  • Door frame fixing work – 100% completed
  • Electrical chasing work – 100% completed
  • Wall Plastering work – 100% completed
  • Outside plastering work – 100% completed

Work status as on 8-2-2017, we have completed.

  • RCC for Structure – completed
  • Block/Brick masonry – completed
  • Door frame fixing work – completed
  • Electrical chasing work – completed
  • Wall Plastering work – upto Terrace floor – completed
  • Plumbing work – progressing
  • As per the current work progress from our site we are progressing with the same and will complete it by the end of February , 2017.
  • Slab shuttering and steel work – 6th floor – progressing
  • Ceiling plastering – 3rd floor – progressing
  • Block work – 1st floor – 90% completed and 2nd floor progressing

We are expected to complete the following works by the end of June 2015.

  • Slab RCC – 6th floor roof – 100% completion
  • Ceiling plastering – 3 rd floor – 100% completion
  • Block work – 1st& 2nd floor – 100% completion
  • Pile cap work – 23nos completed (out of 56)
  • Tie beam work – progressing
  • Plinth beam work – progressing
  • We are expected to complete the following works by the end of January 2015.
  • Pile cap work – 90% completion
  • Tie beam work – 100% completion
  • Plinth beam work – 60% completion
  • 1st floor column work – 50% completion
  • 1st floor Slab shuttering work – 50% completion