Artech Sreya - Progress
![3G3A9887 3G3A9887](https://i0.wp.com/workprogress.artechrealtors.com/wp-content/uploads/2017/06/3G3A9887.jpg?w=596&h=397&ssl=1)
![3G3A9900 3G3A9900](https://i0.wp.com/workprogress.artechrealtors.com/wp-content/uploads/2017/06/3G3A9900.jpg?w=596&h=397&ssl=1)
Work status as on 5-7-2017, we have completed.
- RCC for Structure – completed
- Block/Brick masonry – completed
- Door frame fixing work – completed
- Electrical chasing work – completed
- Wall Plastering work – upto Terrace floor – completed
- Outside plastering work – completed
- Flooring and skirting – progressing
- Inside Putty & primer work – progressing
- Plumbing work – progressing
![DSC_3445 DSC_3445](https://i0.wp.com/workprogress.artechrealtors.com/wp-content/uploads/2017/06/DSC_3445.jpg?w=216&h=324&ssl=1)
![DSC_3447 DSC_3447](https://i0.wp.com/workprogress.artechrealtors.com/wp-content/uploads/2017/06/DSC_3447.jpg?w=216&h=323&ssl=1)
![DSC_3450 DSC_3450](https://i0.wp.com/workprogress.artechrealtors.com/wp-content/uploads/2017/06/DSC_3450.jpg?w=976&h=651&ssl=1)
Work status as on 9-6-2017, we have completed.
- RCC for Structure – completed
- Block/Brick masonry – completed
- Door frame fixing work – completed
- Electrical chasing work – completed
- Wall plastering work – completed
- Outside plastering work – completed
- Inside Putty & primer work – on progress
- Outside Putty & primer work – all floors – on progress
- Plumbing work – on progress
![DSC_3337-1 DSC_3337-1](https://i0.wp.com/workprogress.artechrealtors.com/wp-content/uploads/2017/06/DSC_3337-1.jpg?w=216&h=324&ssl=1)
![DSC_3338-1 DSC_3338-1](https://i0.wp.com/workprogress.artechrealtors.com/wp-content/uploads/2017/06/DSC_3338-1.jpg?w=216&h=323&ssl=1)
![DSC_3340-1 DSC_3340-1](https://i0.wp.com/workprogress.artechrealtors.com/wp-content/uploads/2017/06/DSC_3340-1.jpg?w=976&h=651&ssl=1)
Work status as on 9-5-2017, we have completed.
- RCC for Structure – completed
- Block/Brick masonry – completed
- Electrical chasing work – completed
- Outside plastering work – completed
- Flooring and skirting – progressing
- Outside Putty & primer work -progressing
![DSC_3235 DSC_3235](https://i0.wp.com/workprogress.artechrealtors.com/wp-content/uploads/2017/06/DSC_3235.jpg?w=279&h=419&ssl=1)
![DSC_3239 DSC_3239](https://i0.wp.com/workprogress.artechrealtors.com/wp-content/uploads/2017/06/DSC_3239.jpg?w=279&h=186&ssl=1)
![DSC_3241 DSC_3241](https://i0.wp.com/workprogress.artechrealtors.com/wp-content/uploads/2017/06/DSC_3241.jpg?w=913&h=609&ssl=1)
Work status as on 8-3-2017, we have completed.
- RCC for Structure – 100% completed
- Block/Brick masonry – 100% completed
- Door frame fixing work – 100% completed
- Electrical chasing work – 100% completed
- Wall Plastering work – 100% completed
- Outside plastering work – 100% completed
![DSC_2797 DSC_2797](https://i0.wp.com/workprogress.artechrealtors.com/wp-content/uploads/2017/06/DSC_2797.jpg?w=486&h=324&ssl=1)
![DSC_2802 DSC_2802](https://i0.wp.com/workprogress.artechrealtors.com/wp-content/uploads/2017/06/DSC_2802.jpg?w=486&h=324&ssl=1)
![DSC_2803 DSC_2803](https://i0.wp.com/workprogress.artechrealtors.com/wp-content/uploads/2017/06/DSC_2803.jpg?w=216&h=324&ssl=1)
Work status as on 8-2-2017, we have completed.
- RCC for Structure – completed
- Block/Brick masonry – completed
- Door frame fixing work – completed
- Electrical chasing work – completed
- Wall Plastering work – upto Terrace floor – completed
- Plumbing work – progressing
- As per the current work progress from our site we are progressing with the same and will complete it by the end of February , 2017.
![DSC_2496 DSC_2496](https://i0.wp.com/workprogress.artechrealtors.com/wp-content/uploads/2017/06/DSC_2496-1.jpg?w=279&h=419&ssl=1)
![DSC_2501 DSC_2501](https://i0.wp.com/workprogress.artechrealtors.com/wp-content/uploads/2017/06/DSC_2501-1.jpg?w=279&h=186&ssl=1)
![DSC_2506 DSC_2506](https://i0.wp.com/workprogress.artechrealtors.com/wp-content/uploads/2017/06/DSC_2506-1.jpg?w=913&h=609&ssl=1)
- Slab shuttering and steel work – 6th floor – progressing
- Ceiling plastering – 3rd floor – progressing
- Block work – 1st floor – 90% completed and 2nd floor progressing
We are expected to complete the following works by the end of June 2015.
- Slab RCC – 6th floor roof – 100% completion
- Ceiling plastering – 3 rd floor – 100% completion
- Block work – 1st& 2nd floor – 100% completion
![progress1 progress1](https://i0.wp.com/workprogress.artechrealtors.com/wp-content/uploads/2017/06/progress1.jpg?w=630&h=419&ssl=1)
![progress2 progress2](https://i0.wp.com/workprogress.artechrealtors.com/wp-content/uploads/2017/06/progress2.jpg?w=279&h=419&ssl=1)
![progress3 progress3](https://i0.wp.com/workprogress.artechrealtors.com/wp-content/uploads/2017/06/progress3.jpg?w=279&h=419&ssl=1)
- Pile cap work – 23nos completed (out of 56)
- Tie beam work – progressing
- Plinth beam work – progressing
- We are expected to complete the following works by the end of January 2015.
- Pile cap work – 90% completion
- Tie beam work – 100% completion
- Plinth beam work – 60% completion
- 1st floor column work – 50% completion
- 1st floor Slab shuttering work – 50% completion
![DSC_3123 DSC_3123](https://i0.wp.com/workprogress.artechrealtors.com/wp-content/uploads/2017/06/DSC_3123.jpg?w=486&h=324&ssl=1)
![DSC_3121 DSC_3121](https://i0.wp.com/workprogress.artechrealtors.com/wp-content/uploads/2017/06/DSC_3121.jpg?w=486&h=324&ssl=1)
![DSC_3126 DSC_3126](https://i0.wp.com/workprogress.artechrealtors.com/wp-content/uploads/2017/06/DSC_3126.jpg?w=216&h=324&ssl=1)