Artech Sreya - Progress
Work status as on 5-7-2017, we have completed.
- RCC for Structure – completed
- Block/Brick masonry – completed
- Door frame fixing work – completed
- Electrical chasing work – completed
- Wall Plastering work – upto Terrace floor – completed
- Outside plastering work – completed
- Flooring and skirting – progressing
- Inside Putty & primer work – progressing
- Plumbing work – progressing
Work status as on 9-6-2017, we have completed.
- RCC for Structure – completed
- Block/Brick masonry – completed
- Door frame fixing work – completed
- Electrical chasing work – completed
- Wall plastering work – completed
- Outside plastering work – completed
- Inside Putty & primer work – on progress
- Outside Putty & primer work – all floors – on progress
- Plumbing work – on progress
Work status as on 9-5-2017, we have completed.
- RCC for Structure – completed
- Block/Brick masonry – completed
- Electrical chasing work – completed
- Outside plastering work – completed
- Flooring and skirting – progressing
- Outside Putty & primer work -progressing
Work status as on 8-3-2017, we have completed.
- RCC for Structure – 100% completed
- Block/Brick masonry – 100% completed
- Door frame fixing work – 100% completed
- Electrical chasing work – 100% completed
- Wall Plastering work – 100% completed
- Outside plastering work – 100% completed
Work status as on 8-2-2017, we have completed.
- RCC for Structure – completed
- Block/Brick masonry – completed
- Door frame fixing work – completed
- Electrical chasing work – completed
- Wall Plastering work – upto Terrace floor – completed
- Plumbing work – progressing
- As per the current work progress from our site we are progressing with the same and will complete it by the end of February , 2017.
- Slab shuttering and steel work – 6th floor – progressing
- Ceiling plastering – 3rd floor – progressing
- Block work – 1st floor – 90% completed and 2nd floor progressing
We are expected to complete the following works by the end of June 2015.
- Slab RCC – 6th floor roof – 100% completion
- Ceiling plastering – 3 rd floor – 100% completion
- Block work – 1st& 2nd floor – 100% completion
- Pile cap work – 23nos completed (out of 56)
- Tie beam work – progressing
- Plinth beam work – progressing
- We are expected to complete the following works by the end of January 2015.
- Pile cap work – 90% completion
- Tie beam work – 100% completion
- Plinth beam work – 60% completion
- 1st floor column work – 50% completion
- 1st floor Slab shuttering work – 50% completion