Artech Empire - Progress

Work status as on 08-01-2019, we have completed the following

  • RCC for Structure – 100% completed
  • Ceiling Plastering work – 100% completed
  • Block/Brick masonry work – 100% completed
  • Wall plastering work – 100% completed
  • Aluminium Windows and Ventilators – 100% completed
  • Grill making & fixing – 100% completed
  • Electrical HT work – 100% completed
  • Wire pulling – 100% completed
  • 1st coat painting work – 100% completed
  • 2nd coat painting work – 100% completed
  • External plastering work – 100% completed
  • CP sanitary fixing work – 100% completed
  • Yard work – 100% completed

As per the current work status from our site we are targeted to complete the following works by end of December 2019

  • Yard work – 100% to be completed

Work status as on 06-12-2018, we have completed the following

  • RCC for Structure – 100% completed
  • Ceiling Plastering work – 100% completed
  • Block/Brick masonry work – 100% completed
  • Wall plastering work – 100% completed
  • Aluminium Windows and Ventilators – 100% completed
  • Grill making & fixing – 100% completed
  • Electrical HT work – 100% completed
  • Wire pulling – 100% completed
  • 1st coat painting work – 100% completed
  • 2nd coat painting work – 100% completed
  • External plastering work – 100% completed
  • CP sanitary fixing work – 100% completed
  • Yard work – 95% completed