Artech Avantika - Progress
As per the current work status from our site we are targeted to complete the following works by end of April 2018
- Internal wall plastering work – 100% to be completed
- Inside painting work (1st coat) -100% to be completed
- Inside painting work (2nd coat) -100% to be completed
- External wall plastering work – 100% to be completed
- External painting work- 100% to be completed
- Electrical work – 100% to be completed
- Electrical HT work – 100% to be completed
- Inside putty work – GF -100% to be completed
- Plumbing work – 100% to be completed
- CP sanitary fixing work – 100% to be completed
- Door shutter fixing- 100% to be completed
Work status as on 16-04-2018, we have completed the following.
- Internal wall plastering work – GF (95% completed);1st to Terrace floor (100% completed)
- Inside painting work (1st coat) -1st to 16th floor(100% completed)
- Inside painting work (2nd coat) -1st floor(50% completed);2nd floor(25% completed);5th floor(50% completed);6th,7th,8th,10th & 12th floor(25% completed)
- External wall plastering work – GF (100% completed);1st to Terrace floor (100% completed); Carparking area (90% completed)
- External painting work- 1st floor(85% completed); 2nd floor(95% completed); 3rd floor to Terrace floor(90% completed)
- Electrical LT work – GF (80% completed);1st to Terrace floor (100% completed)
- Electrical HT work – 95% completed
- Inside putty work – GF (95% completed); 1st to Terrace floor (100% completed)
- Tiling work- 1st to 16th floor-100% completed
- Plumbing work – GF (90% completed); 1st to Terrace floor (100% completed)
- CP sanitary fixing work – 1st floor (50% completed); 2nd floor (25% completed);5th floor(50% completed); 7th,8th,10th & 12th floor(25% completed)
- Aluminium Windows and Ventilators – 1st floor to 16th floor (100% completed)
- Door shutter fixing- 1st floor to 15th floor(100% completed); 16th floor(90% completed);
- Water Proofing work – 1st to terrace floor -100% completed
- Yard work- 95% completed
As per the current work status from our site we are targeted to complete the following works by end of March 2018
- Internal wall plastering work – 100% to be completed
- Inside painting work(1st coat) -100% to be completed
- External wall plastering work – 100% to be completed
- Putty work – GF -100% to be completed
- Electrical work – GF -100% to be completed
- Electrical HT work – 100% to be completed
- Aluminium Windows and Ventilators – 100% to be completed
- Door shutter fixing- 100% to be completed
- Plumbing work – 100% to be completed
- CP sanitary fixing work – 1st & 2nd floor 100% to be completed
- Yard work- 100% to be completed
Work status as on 10-03-2018, we have completed the following.
- Internal wall plastering work – GF (90% completed);1st to Terrace floor (100% completed)
- Inside painting work(1st coat) -1st to 16th floor(100% completed)
- External wall plastering work – GF (80% completed);1st to Terrace floor (100% completed); Carparking area (75% completed)
- Putty work – GF (90% completed); 1st to Terrace floor (100% completed)
- Electrical LT work – GF (60% completed);1st to Terrace floor (100% completed)
- Electrical HT work – 85% completed
- Aluminium Windows and Ventilators – 1st floor(100% completed);2nd floor(95% completed);3rd & 4th(90% completed);5th floor(80% completed);6th floor(95% completed);7th,8th & 9th floor(100% completed);10th to 16th floor(95% completed)
- Door shutter fixing- 1st floor(90% completed);2nd to 13th floor(100% completed);14th & 16th floor(90% completed);15th floor(100% completed)
- Tiling work- 1st to 16th floor-100% completed
- Water Proofing work – 1st to terrace floor -100% completed
- Plumbing work – GF (85% completed); 1st to Terrace floor (100% completed)
- CP sanitary fixing work – 1st(50% completed); 2nd floor (25% completed);5th,7th,8th &12th floor(25% completed)
- Yard work- 90% completed
As per the current work status from our site we are targeted to complete the following works by end of February-2018
- Internal wall plastering work – 100% to be completed
- Inside painting work(1st coat) -100% to be completed
- Electrical work – GF -100% to be completed
- Electrical HT work – 100% to be completed
- Putty work – GF -100% to be completed
- External wall plastering work – 100% to be completed
- Plumbing work – 100% to be completed
- CP sanitary fixing work – 1st & 2nd floor 100% to be completed
- Aluminium Windows and Ventilators – 100% to be completed
- Door shutter fixing- 100% to be completed
- Yard work- 100% to be completed
Work status as on 10-02-2018, we have completed.
- Internal wall plastering work – GF (90% completed);1st to Terrace floor (100% completed)
- Inside painting work(1st coat) -1st to 16th floor(100% completed)
- Electrical LT work – GF (60% completed);1st to Terrace floor (100% completed)
- Electrical HT work – 85% completed
- Putty work – GF (90% completed); 1st to Terrace floor (100% completed)
- External wall plastering work – GF (80% completed);1st to Terrace floor (100% completed); Carparking area (75% completed)
- Tiling work- 1st to 16th floor-100% completed
- Plumbing work – GF (85% completed); 1st to Terrace floor (100% completed)
- CP sanitary fixing work – 1st(50% completed); 2nd floor (25% completed)
- Aluminium Windows and Ventilators – 1st,9th floor(100% completed);2nd,6th to 8th & 10th to 13th floor(95% completed);3rd,4th(90% completed); 5th floor(80% completed)14th floor(75% completed);15th floor(50% completed);16th floor(25% completed)
- Door shutter fixing- 1st floor(90% completed);2nd to 12th floor(100% completed);13th,14th & 16th floor(90% completed);15th floor(100% completed)
- Water Proofing work – 1st to terrace floor -100% completed
- Yard work- 90% completed
As per the current work status from our site we are targeted to complete the following works by end of December, 2017
- Internal wall plastering work – 100% to be completed
- Inside panting work(1st coat) -100% to be completed
- Electrical work – GF -100% to be completed
- Putty work – GF -100% to be completed
- External wall plastering work – 100% to be completed
- Tiling work-15th & 16th floor-100% to be completed
- Plumbing work – 100% to be completed
- CP sanitary fixing work – 1st & 2nd floor 100% to be completed
- Alumnium Windows and Ventilators – 100% to be completed
- Yard work- 100% to be completed
Work status as on 10-12-2017, we have completed
- Internal wall plastering work – GF (90% completed);1st to Terrace floor (100% completed)
- Inside panting work(1st coat) -1st to 16th floor(100% completed)
- Electrical work – GF (50% completed);1st to 16th floor (100% completed)
- Putty work – GF (90% completed); 1st to Terrace floor (100% completed)
- External wall plastering work – GF (80% completed);1st to Terrace floor (100% completed); Carparking area (75% completed)
- Tiling work- 1st to 14th floor(100% completed);15th & 16th floor(95% completed)
- Plumbing work – GF (85% completed); 1st to Terrace floor (100% completed)
- CP sanitary fixing work – 1st & 2nd floor (25% completed)
- Alumnium Windows and Ventilators – 1st &5th floor(80% completed);2nd & 7th floor(95% completed);3rd,4th &6th floor(90% completed);8th floor(85% completed);9th floor(100% completed);10th,11th & 12th floor(75% completed)
- Yard work- 75% completed
Work status as on 9-8-2017, we have completed
- RCC for Structure – completed
- Car parking roof concreting work – completed
- Ceiling plastering work – completed
- Block/Brick masonry – completed
- Internal wall plastering work – completed
- Putty work – progressing
- External wall plastering work -progressing
Work status as on 10-7-2017, we have completed
- RCC for Structure – completed
- Car parking roof concreting work – completed
- Ceiling plastering work – completed
- Block/Brick masonry – completed
- Block/Brick masonry – completed
- Putty work – GF balnce; progressing
- External wall plastering work – progressing
Work status as on 10-6-2017, we have completed
- RCC for Structure – completed
- Car parking roof concreting work – completed
- Ceiling plastering work – completed
- Block/Brick masonry – completed
- External wall plastering work – progressing
Work status as on 9-5-2017, we have completed
- RCC for Structure – completed
- Car parking roof concreting work – completed
- Ceiling plastering work – completed
- Block/Brick masonry – completed
- Putty work – GF balnce; 13th floor – progressing
Work status as on 7-3-2017, we have completed
- RCC for Structure – completed
- Car parking roof concreting work – completed
- Ceiling plastering work – completed
- Block/Brick masonry – completed
- External wall plastering work – progressing
Construction status as on June 2015
- 5th floor roof slab (half portion) RCC work – 100% completed
- 5th to 6th floor roof column – 8nos completed (out of 37)
- Lift wall steel work – completed.
- Ceiling plastering work – 4th floor – progressing
- Block work – 1st, 2nd and 3rd floor – progressing
- Wire pulling work – 3rd floor – progressing
Following works are expected to be completed by end of June 2015.
- 5th & 6th floor roof slab RCC work – 100% completion
- 5th to 6th floor roof column – 100% to be completed
- Ceiling plastering work – 4th & 5th floor – 100% completion
- Block work – 3rd and 4th floor – 100% completion
- Wire pulling work – 3rd & 4th floor – 100% to be completed
As on 6-3-2015, we are progressing 3rd floor -Slab shuttering & Steel works.
The 3rd & 4th floor slab RCC works are expected to be completed by next month.