Artech -The Address - Progress
As per the current work status from our site we are targeted to complete the following works by end of February-2018
- Inside Putty work -100% to be completed
- 1st coat painting work – 100% to be complete
- 2nd coat painting work – 100% to be complete
- Aluminium Windows and Ventilators – 100% to be completed
- CP Sanitary fixing work -100% to be completed
- Tiling – 100 % to be completed
- Door frame fixing work – 100% completed
- Yard work- 100% to be completed
Work status as on 10-02-2018, we have completed the following.
- 2nd coat painting work – 1st & 3rd floor (A-flat-100% completed) & 5th,11th & 13th floor (B-flat-100% completed); 7th floor(A & D flat-100% completed) & 8th floor(C & B flat- 100% completed)
- Aluminium Windows and Ventilators – 60% completed
- CP Sanitary fixing work- 1st & 3rd (A flat 100% completed);4th floor(A flat & Bflat-100% complete);7th (A,D flat-100% completed);8th floor( C & Bflat-100% completed);13th floor (B flat- 100% completed); 21st floor (Common area- 100% completed)
- Electrical HT work – 100 % completed
- Electrical LT work -Wire pulling-100% completed
- Tiling – 1st floor & 3rd to 20th floor(100% completed);2nd floor(80% completed)
- Water proofing work -100% completed
- Door frame fixing work – 3rd to 9th, 11th to 16th & 18th to 20th floor(100% completed);1st floor( 50% completed);2nd ,10th & 17th floor(75% completed)
- Yard work- 85% completed
Work status as on 10-7-2017, we have completed
- RCC for Structure – completed
- Ceiling Plastering – completed
- Block/Brick Masonry – progressing
- InsideWall Plastering work – progressing
Work status as on 7-5-2017, we have completed
- RCC for Structure – completed
- Ceiling Plastering – completed
- Block/Brick Masonry – progressing
- External Wall Plastering work – progressing
Work status as on 7-3-2017, we have completed
- Ceiling Plastering – 100% completed
- Block/Brick Masonry – progressing
- External Wall Plastering work – progressing
- InsideWall Plastering work – progressing
Construction status as on June 2015
- Slab shuttering work – 14th roof – progressing
- Block work – 12th floor – completed
- Ceiling plastering work – 13th roof – progressing
- Water proofing work – 7th floor – progressing
- Electrical wall chasing work- 11th floor- progressing
- Plumbing work – 6th & 7th floor – progressing
Following works are expected to be completed by June 2015:
- Slab RCC – 14th floor roof – 100% completion
- Block work – 13th floor – 100% completion
- Ceiling plastering work – 13th roof – 100% completion
- Water proofing work – 7th & 8th floor – 100% completion
- Electrical wall chasing work – 12th floor – 100% completion
- Plumbing work – 7th & 8th floor – 100% completion
- Slab concrete work – 2nd floor roof slab completed
- Column work – 3rd floor – 50% completed
- Ceiling plastering work- 1st floor – 60% completed
- Block work – 1st floor progressing