Artech Flora - PROGRESS

Work status as on 08-03-2023, we have completed the following.

  • Structural Works – All sub-structural and structural works-Completed.
  • Civil Works – Ceiling plastering and wall plastering- Completed, Masonry – Block/ brick-Completed, Screeding- up to 15th floor 100% Completed, GF – 95% Completed, Internal plaster Completed.
  • Internal Finishes – Main door – up to 15th floor – completed, Waterproofing- till 15th floor completed, GF – 100% Completed, BF – 90% Completed,terrace completed, Wall tiling- up to 15th floor 98% completed, Flooring- up to 15th floor 95% completed, GF & BF – 90% Completed, putty works & Painting- 50% completed (100% 1st coat putty, primer completed (inside), 2nd coat putty (up to 15th floor completed)), lift lobby up to 13th floor (2 coat putty, 1 coat primer, 1 coat emulsion completed), Door frame fixtures – fully completed, Hand rail – Mainstair completed, firestair – till 7th floor completed, balcony handrail – 93% completed.
  • Electrical, Plumbing & Firefighting works – Concealed plumbing works- up to 15th Floor Completed, Fire fighting Works – 92% completed, Suspended line work – completed, Gas line work – 70% completed.
  • External Finishes – Windows and sliding doors – up to 15th floor – 93% completed, External Painting- outside primer fully completed, 1st coat putty – 100% completed, 2nd coat emulsion – front elevation, rear and 2 sides 2nd coat emulsion 90% completed, External Plastering- fully completed, Elevation grill completed, Wire pulling completed in 32 flats, GF Lobby, and switch fixing completed in 5 flats.
  • Mockup – Completed.

As per the current work status from our site, we are targeted to complete the following works by the end of MARCH 2023.

  • Electrical, Plumbing & Firefighting works – Gas line work – ring line work to be completed
  • External Finishes – Windows and sliding doors – 100% to be completed, painting – back side elevation emulsion to be completed

Work status as on 11-02-2023, we have completed the following.

  • Structural Works – All sub-structural and structural works-Completed.
  • Civil Works – Ceiling plastering and wall plastering- Completed, Masonry – Block/ brick-Completed, Screeding- up to 15th floor 100% Completed, GF – 90% Completed, Internal plaster Completed.
  • Internal Finishes – Main door – up to 15th floor – completed, Waterproofing- till 15th floor completed, GF – 100% Completed, BF – 90% Completed,terrace completed, Wall tiling- up to 15th floor 98% completed, Flooring- up to 15th floor 95% completed, GF & BF – 90% Completed, putty works & Painting- 45% completed (100% 1st coat putty, primer completed (inside), 2nd coat putty (up to 15th floor completed)), Door frame fixtures – fully completed, Hand rail – Mainstair completed, firestair – till 7th floor completed, balcony handrail – 90% completed.
  • Electrical, Plumbing & Firefighting works – Concealed plumbing works- up to 15th Floor Completed, Fire fighting Works – 92% completed, Suspended line work – completed, Gas line work – 70% completed.
  • External Finishes – Windows and sliding doors – up to 15th floor – 93% completed, External Painting- outside primer fully completed, 1st coat putty – 100% completed, 2nd coat emulsion – front elevation, rear and 2 sides 2nd coat emulsion 90% completed, External Plastering- fully completed, Elevation grill completed, Wire pulling completed in 32 flats, GF Lobby, and switch fixing completed in 5 flats.
  • Mockup – Completed.

As per the current work status from our site, we are targeted to complete the following works by the end of FEBRUARY 2023.

  • Electrical, Plumbing & Firefighting works -Gas line work – ring line work to be completed
  • External Finishes – Windows and sliding doors – 100% to be completed, painting – back side elevation emulsion to be completed

Work status as on 14-01-2023, we have completed the following.

  • Structural Works – All sub-structural and structural works-Completed.
  • Civil Works – Ceiling plastering and wall plastering- Completed, Masonry – Block/ brick-Completed, Screeding- up to 15th floor 100% Completed, GF – 70% Completed, Internal plaster Completed.
  • Internal Finishes – Main door – up to 14th floor – 95% completed, Waterproofing- till 15th floor 100 % completed, GF – 70% Completed, terrace completed, Wall tiling- up to 15th floor 98% completed, Flooring- up to 15th floor 95% completed, GF & BF – 70% Completed, putty works & Painting- 45% completed (100% 1st coat putty, primer completed (inside), 2nd coat putty (up to 12th floor completed)), Door frame fixtures – fully completed, Hand rail – Mainstair completed, firestair – till 7th floor completed, balcony handrail – 85% completed (base frame till 14th floor completed)
  • Electrical, Plumbing & Firefighting works – Concealed plumbing works- up to 15th Floor Completed, Fire fighting Works – 92% completed, Suspended line work – completed, Gas line work – (40 flats) 70% completed (external lines completed, inside copper laying completed)
  • External Finishes – Windows and sliding doors – up to 15th floor – 90% completed, External Painting- outside primer fully completed, 1st coat putty – 100% completed, 1st coat emulsion – front elevation and 2 sides completed, External Plastering- fully completed, Elevation grill completed
  • Mockup – Blockwork, Internal plaster – 100% completed, Firefighting – 100% completed, Concealed plumbing – 100% completed, Waterproofing – 100% completed, Electrical wall services – 100% completed, Reticulated gas piping – 100% completed, Painting – Primer application completed.

As per the current work status from our site, we are targeted to complete the following works by the end of JANUARY 2023.

  • Electrical, Plumbing & Firefighting works – Gas line work – (15 more flats to be completed) 60% completed
  • Internal Finishes – Main door -2 more apartments to be fixed, Water proofing – terrace, ground floor, ramp, servant’s toilets 100% to be completed, Wall tiling- 15th floor 100% to be completed, Flooring – 15th floor, BF,GF 100% to be completed, Putty works and painting – 50% (lobby and corridor of all floors) to be completed
  • External Finishes – Windows and sliding doors – 15th floor to be completed including stair windows

As per the current work status from our site, we are targeted to complete the following works by the end of DECEMBER 2022.

  • Civil Works – screeding – terrace to be completed
  • Internal Finishes – Main door -100% to be completed, Water proofing – terrace, ground floor, ramp, servant’s toilets 100% to be completed, Wall tiling- 14th floor 100% to be completed, Flooring – 14th floor 100% to be completed, Putty works and painting – 50% (lobby and corridor of all floors) to be completed, Hand rail – balcony handrail – (10th to 14th floor) 90% to be completed
  • External Finishes – Windows and sliding doors – 15 more flats to be completed, External Painting – 1st coat emulsion – remaining 4 elevations to be completed
  • Electrical, Plumbing & Firefighting works – Gas line work – (15 more flats to be completed) 60% completed

Work status as on 13-12-2022, we have completed the following.

  • Structural Works – All sub-structural and structural works-Completed.
  • Civil Works – Ceiling plastering and wall plastering- Completed, Masonry – Block/ brick-Completed, Screeding- up to 15th floor 100% Completed, GF – 70% Completed, Internal plaster Completed.
  • Internal Finishes – Main door – up to 14th floor – 90% completed, Waterproofing- till 15th floor 100 % completed, GF – 70% Completed, Wall tiling- up to 14th floor 98% completed, Flooring- up to 14th floor 90% completed, putty works & Painting- 45% completed (100% 1st coat putty, primer completed (inside), 2nd coat putty (up to 12th floor completed)), Door frame fixtures – fully completed, Hand rail – Mainstair completed, balcony handrail – (up to 9th floor – 85% completed)
  • External Finishes – Windows and sliding doors – 20 flats completed, External Painting- outside primer fully completed, 1st coat putty – 100% completed, 1st coat emulsion – front elevation completed, External Plastering- fully completed.
  • Electrical, Plumbing & Firefighting works – Concealed plumbing works- up to 15th Floor Completed, Fire fighting Works – 92% completed, Suspended line work – completed, Gas line work – (20 flats) 50% completed
  • Mockup – Blockwork, Internal plaster – 100% completed, Firefighting – 100% completed, Concealed plumbing – 100% completed, Waterproofing – 100% completed, Electrical wall services – 100% completed, Reticulated gas piping – 100% completed, Painting – Primer application completed

As per the current work status from our site, we are targeted to complete the following works by the end of NOVEMBER 2022.

  • Civil Works – screeding – terrace to be completed
  • Internal Finishes – Main door – 11th to 13th floor 100% to be completed, Water proofing – terrace, ground floor, ramp 100% to be completed, Wall tiling- 14th floor 100% to be completed, Flooring – 14th floor 100% to be completed, Putty works and painting – 50% to be completed, Hand rail – balcony handrail – 90% to be completed
  • External Finishes – Windows and sliding doors – 95% to be completed
  • Electrical, Plumbing & Firefighting works – Gas line work – 60% completed

Work status as on 15-11-2022, we have completed the following.

  • Structural Works – All sub-structural and structural works-Completed.
  • Civil Works – Ceiling plastering and wall plastering- Completed, Masonry – Block/ brick-Completed, Screeding- up to 15th floor 100% Completed, Internal plaster Completed.
  • Internal Finishes – Main door – up to 10th floor completed, Waterproofing- till 15th floor 100 % completed, Wall tiling- up to 14th floor 98% completed, Flooring- up to 14th floor 90% completed, putty works & Painting- 45% completed (100% 1st coat putty, primer completed (inside), 2nd coat putty (8 flats completed)), Door frame fixtures – fully completed, Hand rail – Mainstair completed, balcony handrail – 85% completed
  • External Finishes – Windows and sliding doors – till 12 th floor 90% completed, External Painting- outside primer fully completed, 1st coat putty – 100% completed, External Plastering- fully completed.
  • Electrical, Plumbing & Firefighting works – Concealed plumbing works- up to 15th Floor Completed, Fire fighting Works – 92% completed, Suspended line work – completed, Gas line work – 50% completed
  • Mockup – Blockwork, Internal plaster – 100% completed, Firefighting – 100% completed, Concealed plumbing – 100% completed, Waterproofing – 100% completed, Electrical wall services – 100% completed, Reticulated gas piping – 100% completed, Painting – Primer application completed

Work status as on 11-10-2022, we have completed the following.

  • Structural Works – All sub-structural and structural works-Completed.
  • Civil Works – Ceiling plastering and wall plastering- Completed, Masonry – Block/ brick-Completed, Screeding- up to 13th floor 100% completed & 14th floor 100% Completed, Internal plaster Completed.
  • Internal Finishes – Main door – up to 10th floor completed, Waterproofing- till 15th floor 100 % completed, Wall tiling- up to 14th floor 90% completed, Flooring- up to 14th floor 90% completed, putty works & Painting- 45% completed (100% 1st coat putty, primer completed (inside), 2nd coat putty (8 flats completed)), Door frame fixtures – fully completed, Hand rail – Mainstair completed, balcony handrail – 70% completed.
  • External Finishes – Windows and sliding doors – till 12 th floor 90% completed, External Painting- outside primer fully completed, 1st coat putty – 100% completed, External Plastering- fully completed.
  • Electrical, Plumbing & Firefighting works – Concealed plumbing works- up to 15th Floor Completed, Fire fighting Works – 90% completed, Suspended line work – completed, Gas line work – 50% completed.
  • Mockup – Blockwork, Internal plaster – 100% completed, Firefighting – 100% completed, Concealed plumbing – 100% completed, Waterproofing – 100% completed, Electrical wall services – 100% completed, Reticulated gas piping – 100% completed, Painting – Primer application completed.

As per the current work status from our site, we are targeted to complete the following works by the end of OCTOBER 2022.

  • Internal Finishes – Main door – 11th to 13th floor 100% to be completed, Water proofing – terrace (water tank)100% to be completed, Wall tiling- 14th floor 100% to be completed, Flooring – 14th floor 100% to be completed, Putty works and painting – 50% to be completed, Hand rail – balcony handrail – 75% to be completed.
  • External Finishes – Windows and sliding doors – 95% to be completed.
  • Electrical, Plumbing & Firefighting works – Gas line work – 60% completed.

Work status as on 17-09-2022, we have completed the following.

  • Structural Works – All sub-structural and structural works-Completed.
  • Civil Works – Ceiling plastering and wall plastering- Completed, Masonry – Block/ brick-Completed, Screeding- up to 13th floor 100% completed & 14th floor (95% completed) (except balcony) Completed, Internal plaster Completed.
  • Internal Finishes – Main door – up to 10th floor completed, Waterproofing- till 15th floor 100 % completed, Wall tiling- up to 13th floor 95% completed, Flooring- up to 13th floor 95% completed, putty works & Painting- 45% completed (100% 1st coat putty, primer completed (inside), 2nd coat putty (8 flats completed)), Door frame fixtures – fully completed, Hand rail – Mainstair completed, balcony handrail – 70% completed.
  • External Finishes – Windows and sliding doors – till 12 th floor 90% completed, External Painting- outside primer fully completed, 1st coat putty – 100% completed, External Plastering- fully completed.
  • Electrical, Plumbing & Firefighting works – Concealed plumbing works- up to 15th Floor Completed, Fire fighting Works – 90% completed, Suspended line work – completed, Gas line work – 45% completed.
  • Mockup – Blockwork, Internal plaster – 100% completed, Firefighting – 100% completed, Concealed plumbing – 100% completed, Waterproofing – 100% completed, Electrical wall services – 100% completed, Reticulated gas piping – 100% completed, Painting – Primer application completed.

As per the current work status from our site, we are targeted to complete the following works by the end of SEPTEMBER 2022.

  • Internal Finishes – Main door – 11th to 13th floor 100% to be completed, Water proofing – terrace 100% to be completed, Wall tiling- 13th floor 100% to be completed, Flooring – 13th floor 100% to be completed, Putty works and painting – 50% to be completed, Hand rail – balcony handrail – 75% to be completed.
  • External Finishes – Windows and sliding doors – 95% to be completed.

Work status as on 09-07-2022, we have completed the following.

  • Structural Works – All sub-structural and structural works-Completed.
  • Civil Works – Ceiling plastering and wall plastering- Completed, Masonry – Block/ brick-Completed, Screeding- up to 13th floor (except balcony) Completed, Internal plaster Completed.
  • Internal Finishes – Main door – up to 9th floor completed, Waterproofing- till 15th floor 100 % completed, Wall tiling- up to 12th floor 80% completed, Flooring- up to 13th floor 70% completed, putty works & Painting- 45% completed (100% 1st coat putty, primer completed (inside), 2nd coat putty (1 to 6th floor completed)), Door frame fixtures – fully completed, Hand rail – Mainstair completed, balcony handrail – base frame fixed till 8th floor 70% completed.
  • External Finishes – Windows and sliding doors – 1st, 2nd, 3rd and 6th floor completed, External Painting- outside primer fully completed, 1st coat putty – 60% completed, External Plastering- fully completed.
  • Electrical, Plumbing & Firefighting works – Concealed plumbing works- up to 15th Floor Completed, Fire fighting Works – Piping up to 14th floor completed, Suspended line work – till 11th floor completed, Gas line work – 25% completed.
  • Mockup – Blockwork, Internal plaster – 100% completed, Firefighting – 100% completed, Concealed plumbing – 100% completed, Waterproofing – 100% completed, Electrical wall services – 100% completed, Reticulated gas piping – 100% completed, Painting – Primer application completed.

As per the current work status from our site, we are targeted to complete the following works by the end of JULY 2022.

  • Internal Finishes – Main door – 10th to 13th floor 100% to be completed, Water proofing – terrace 100% to be completed, Wall tiling- 12th, 13th floor 100% to be completed. Flooring – 13th floor 100% to be completed, passage and staircase till 8th floor to be completed, Putty works and painting – 50% to be completed, Hand rail – Firestair till 5th floor 100% to be completed, balcony handrail – 14 flats top frame fixing 100% to be completed.
  • External Finishes – Windows and sliding doors – 4th, 5th floor 100% to be completed.
  • Electrical, Plumbing & Firefighting works – Suspended line work – up to 15th floor to be completed, duct line work – 30% to be completed.


Work status as on 09-06-2022, we have completed the following.

  • Structural Works – All sub-structural and structural works-Completed.
  • Civil Works – Ceiling plastering and wall plastering- Completed, Masonry – Block/ brick-Completed, Screeding- up to 10th floor Completed, Internal plaster Completed.
  • Internal Finishes – Main door – up to 9th floor completed, Waterproofing- till 12th floor 100 % completed, Wall tiling- up to 10th floor 90% completed, Flooring- up to 10th floor 95% completed, putty works & Painting- 45% completed (100% 1st coat putty completed (inside), 2nd coat putty (1 to 6th floor completed)), Door frame fixtures – fully completed, Hand rail – Mainstair completed
  • External Finishes – Windows and sliding doors – 1st, 2nd, 3rd and 6th floor completed, External Painting- outside primer fully completed, External Plastering- fully completed.
  • Electrical, Plumbing & Firefighting works – Concealed plumbing works- up to 13th Floor Completed, Fire fighting Works – Piping up to 14th floor completed, Suspended line work – till 10th floor completed
  • Mockup – Blockwork, Internal plaster – 100% completed, Firefighting – 100% completed, Concealed plumbing – 100% completed, Waterproofing – 100% completed, Electrical wall services – 100% completed, Reticulated gas piping – 100% completed, Painting – Primer application completed

As per the current work status from our site, we are targeted to complete the following works by the end of JUNE 2022.

  • Civil Works – Screeding – 11th floor 100% to be Completed
  • Internal Finishes – Main door – 10th floor 100% to be completed, Water proofing – 13th, 14th floor 100% to be completed, Wall tiling- 11th, 12th floor 100% to be completed. Flooring – 11th, 12th floor 100% to be completed, Putty works and painting – 50% to be completed, Hand rail – Firestair till 5th floor 100% to be completed
  • External Finishes – Windows and sliding doors – 4th, 5th floor 100% to be completed
  • Electrical, Plumbing & Firefighting works – Firefighting works Concealed plumbing works – 14th floor 100% to be completed, Fire fighting Work – Piping 14th floor to be completed, Suspended line work – 11th, 12th, 13th, 14th floor to be completed

Work status as on 12-04-2022, we have completed the following.

  • Structural Works – All sub-structural and structural works-Completed.
  • Civil Works – Ceiling plastering and wall plastering- Completed, Masonry – Block/ brick-Completed, Screeding- up to 10th floor Completed, Internal plaster Completed.
  • Internal Finishes – Main door – up to 6th floor completed, Waterproofing-11th floor completed (terrace half portion , basement floor completed), Wall tiling- up to 9th floor completed, Flooring- up to 9th floor completed (passage till 4th floor 100% completed), putty works & Painting- 100% 1st coat putty completed (inside), 2nd coat putty (1 to 5th floor completed), Door frame fixtures – fully completed.
  • External Finishes – External Painting- outside primer fully completed , 20% putty work completed, External Plastering- fully completed.
  • Electrical, Plumbing & Firefighting works – Concealed plumbing works- up to 12th Floor Completed.
  • Mockup – Blockwork, Internal plaster – 100% completed, Firefighting – 100% completed, Concealed plumbing – 100% completed, Waterproofing – 100% completed, Electrical wall services – 100% completed, Reticulated gas piping – 100% completed, Painting – Primer application completed

As per the current work status from our site, we are targeted to complete the following works by the end of APRIL 2022.

  • Civil Works – Screeding – 11th floor 100% to be Completed
  • Internal Finishes – Main door – 7th to 9th floor 100% to be completed, Water proofing – 12th floor 100% to be completed, Wall tiling- 10th floor 100% to be completed. Flooring – 10th floor 100% to be completed, Putty works and painting – 2nd coat putty 6th, 7th, 8th floor 100% to be completed (inside).
  • External Finishes – 40% putty work to be completed
  • Electrical, Plumbing & Firefighting works – Concealed plumbing works – 13th Floor 100% to be completed.

Work status as on 10-03-2022, we have completed the following.

  • Structural Works – All sub-structural and structural works-Completed.
  • Civil Works – Ceiling plastering and wall plastering- Completed, Masonry – Block/ brick-Completed, Screeding-10th floor Completed, Internal plaster Completed.
  • Internal Finishes – Main door – 4th floor completed, Waterproofing-10th floor completed, Wall tiling-7th floor completed, Flooring-9th floor completed, putty works & Painting- 100% 1st coat putty completed (inside), Door frame fixtures-fully completed, Handrails-not yet started
  • External Finishes – External Painting- outside primer fully completed, 20% putty work completed, External Plastering- fully completed.
  • Electrical, Plumbing & Firefighting works – Concealed plumbing works-11th Floor Completed.
  • Mockup – Blockwork, Internal plaster – 100% completed, Firefighting – 100% completed, Concealed plumbing – 100% completed, Waterproofing – 100% completed, Electrical wall services – 95% completed, Reticulated gas piping – 100% completed, Painting – Primer application completed

As per the current work status from our site, we are targeted to complete the following works by the end of MARCH 2022.

  • Civil Works – Screeding – 11th floor to be Completed
  • Internal Finishes – Main door – 6th floor to be completed, Water proofing – 11th floor to be completed, Wall tiling- 9th floor to be completed. Flooring – 10th floor to be completed, Putty works and painting – 30% second coat putty to be completed(inside).
  • External Finishes – 40% putty work to be completed
  • Electrical, Plumbing & Firefighting works – Concealed plumbing works – 12th Floor to be completed.
  • Mockup – Electrical works 100% to be Completed.

Work status as on 09-04-2021, we have completed the following.

  • Floor Slab Work :
  1. Retaining wall side ground floor slab -100% completed (west side portion )
  2. GF slab – 13th floor: 100 % completed,14th floor-100% completed.
  3. Upto 15th floor column : 100% completed.
  4. Front side retaining wall slab& front side GF slab: 80% completed.
  5. Backside retaining wall area: 100% completed
  • ELECTRICAL WALL CHASING
  1. upto 10th floor -100% completed
  • WALL PLASTERING
  1. upto 8th floor -100% completed.
  • CEILING PLASTERING :
  1. Ground floor -12th floor : 100% completed
  • BLOCK WORK
  1. First floor-8th floor: 100% completed, 9th floor -100%completed.
  • PLUMBING WALL CHASING
  1. 1st-4th floor: 100% completed
  • FIRST COAT PUTTY
  1. Upto 5th floor -100% completed.
  • TILE WORK
  1. Sample falt (4C)-50% completed.
  • WATERPROOFING
  1. Upto 4th floor -100% completed.

As per the current work status from our site, we are targeted to complete the following works by the end of APRIL 2021.

  • Floor Slab Work :
  1. 15th-Floor Slab: 100% to be completed
  • ELECTRICAL WALL CHASING
  1. 11th floor -100% to be completed
  • WALL PLASTERING
  1. 9th floor -100% to be completed.
  • CEILING :
  1. 13th floor: 100% to be completed.
  • BLOCK WORK
  1. 10th floor- 100% to be completed.
  • PLUMBING WALL CHASING
  1. 5th floor-: 100% to be completed.
  • FIRST COAT PUTTY
  1. 6th column -100% to be completed
  • TILE WORK
  1. Sample falt (4C)-100% to be completed.
  2. 1st floor:-100% to be completed.
  • WATERPROOFING
  1. 5th floor -100% to be completed.

Work status as on 11-03-2021, we have completed the following.

  • Floor Slab Work :
  1. Retaining wall side ground floor slab -85%  completed (west side portion )
  2. GF slab – 13th floor: 100 % completed,14th floor-50% completed.
  3. Up to 14th floor column : 100% completed.
  4. Front side retaining wall slab& front side GF slab: 80% completed.
  5. Backside retaining wall area: 100% completed
  • ELECTRICAL WALL CHASING: 2nd floor-8th floor -100%  completed
  • WALL PLASTERING: 1st floor-6th floor -100%  completed.
  • CEILING: Ground floor -11th floor : 100% completed
  • BLOCK WORK: First floor-8th floor: 100% completed.,9th floor -50%completed.
  • Plumbing Wall Chasing: 1st-4th floor: 100%  completed
  • FIRST COAT PUTTY: Up to 4th floor, -100% completed.
  • WATERPROOFING: Up to 3rd floor, -100% completed.

As per the current work status from our site, we are targeted to complete the following works by the end of February 2021.

  • Floor Slab Work :
  1. Retaining wall work – 95%  to be completed
  2. 14th-Floor Slab: 100% to be completed
  3. 15th column: 100% to be completed
  • ELECTRICAL WALL CHASING: 9th-10th floor -100% to be completed
  • WALL PLASTERING: 7th-8th floor -100% to be completed.
  • CEILING : 12th floor: 100% to be completed.
  • BLOCK WORK: 9th floor- 100% to be completed.
  • Plumbing Wall Chasing: 5th floor-: 100% to be completed.
  • FIRST COAT PUTTY: 5th,6th column -100% to be completed
  • WATERPROOFING: 4th floor  -100% to be completed

As per the current work status from our site, we are targeted to complete the following works by the end of February 2021.

  • Floor Slab Work:
  1. Retaining wall work – 95% to be completed
  2. 14th-Floor Slab: 100% to be completed
  3. 14th column: 100% to be completed
  • ELECTRICAL WALL CHASING: 7th-8th floor -100% to be completed
  • WALL PLASTERING: 6th floor -100% to be completed.
  • CEILING : 11th floor: 100% to be completed.
  • BLOCK WORK: 9th floor- 100% to be completed.
  • Plumbing Wall Chasing: 4th floor-: 100% to be completed.

Work status as on 09-02-2021, we have completed the following.

  • Floor Slab Work:
  1. Retaining wall side ground floor slab -85% completed (west side portion )
  2. GF slab – 13th floor : 100 % completed
  3. Upto 13th floor column : 100% completed,14th floor -50% completed.
  4. Front side retaining wall slab& front side GF slab: 80% completed.
  5. Backside retaining wall area: 100% completed
  • ELECTRICAL WALL CHASING: 2nd floor-6th floor -100% completed
  • WALL PLASTERING: 1st floor-5th floor -100% completed.
  • CEILING: Ground floor -10th floor: 100% completed
  • BLOCK WORK: first floor-8th floor: 100% completed.
  • Plumbing Wall Chasing: 1st-3rd floor: 100% completed,4th floor -50% completed.

As per the current work status from our site, we are targeted to complete the following works by the end of JANUARY 2021

  • Floor Slab Work:
  1. Retaining wall work – 95% to be completed
  2. 13th-Floor Slab: 100% to be completed
  3. 14th column: 100% to be completed
  • ELECTRICAL WALL CHASING: 5th-6th floor -100% to be completed
  • WALL PLASTERING: 4th floor(CD): 100% to be completed, 5th floor -100% to be completed.
  • CEILING : 10th floor: 100% to be completed.
  • BLOCK WORK: 8th floor- 100% to be completed.
  • Plumbing Wall Chasing: 4th floor-: 100% to be completed.

Work status as on 07-01-2021, we have completed the following.

  • Floor Slab Work:
  1. Retaining wall side ground floor slab -85% completed (west side portion )
  2. GF slab – 12th floor : 100 % completed
  3. Upto 13th floor column : 100% completed
  4. Front side retaining wall slab& front side GF slab : 80% completed.
  5. Backside retaining wall area: 100% completed
  • ELECTRICAL WALL CHASING: 2nd floor- 4th floor 100% completed, 5th-6th floor -50% completed
  • WALL PLASTERING: 1st floor-3rd floor -100% completed, 4th floor(AB): 100% completed.
  • CEILING: Ground floor -9th floor : 100% completed
  • BLOCK WORK: first floor-7th floor: 100% completed.
  • Plumbing Wall Chasing: 1st-3rd floor: 100% completed.

As per the current work status from our site, we are targeted to complete the following works by the end of July 2020

  • Retaining wall work -80% to be completed
  • Sixth floor Slab : 100% to be completed
  • Seventh floor Slab : 60% to be completed
  • Front portion GF slab : 100% to be completed
  • Fifth floor: 100% to be completed.
  • First floor- 50% to be completed.

Work status as on 11-06-2020, we have completed the following.

  • Floor Slab Work:
  1. Retaining wall side ground floor slab -85% completed (west side portion )
  2. GF slab – 4th floor : 100 % completed
  3. Fifth floor Slab : 100% completed
  4. Sixth floor Slab : 60% completed
  5. Back side retaining wall area : 100%
  6. Fround side retaining wall area slab& front side GF slab : 50% completed.
  • CEILING:
  1. Ground floor ceiling plastering : 100% completed
  2. first floor : 100 % completed
  3. second floor : 100 %completed
  4. Third floor: 100% completed.
  5. Forth floor: 100% completed.

As per the current work status from our site, we are targeted to complete the following works by the end of March 2020

  • Retaining wall work: 100% to be (west side) completed
  • Third floor Slab: 100% to be completed
  • Fourth floor Slab: 100% to be completed
  • Front side retaining wall area slab: 100% to be completed
  • CEILING: ground floor & first floor- 100 will be completed

Work status as on 11-03-2020, we have completed the following.

  • Floor Slab Work:
  1. Retaining wall side ground floor slab -85% completed(west side portion)
  2. Ground floor slab : 100 % completed
  3. First floor Slab :100% completed
  4. Second floor Slab :100% completed
  5. Third floor Slab : 100% completed
  6. Fourth floor Slab : 100% completed
  7. Back side retaining wall area : 100%
  8. Fround side retaining wall area slab& front side GF slab : 50% to be completed.
  • CEILING:
  1. Ground floor ceiling plastering : 100% completed
  2. first floor : 100 %completed
  3. second floor : 50 %completed

As per the current work status from our site, we are targeted to complete the following works by the end of February 2020

  • Retaining wall work: 100% to be (west side)completed
  • Third floor Slab: 100% to be completed
  • Fourth floor Slab: 100% to be completed
  • Front side retaining wall area slab: 100% to be completed
  • CEILING: ground floor & first floor- 100 will be completed

Work status as on 08-02-2020, we have completed the following.

  • Retaining wall side ground floor slab -85% completed(west side portion)
  • Ground floor slab: 100% completed
  • First floor Slab: 100% completed
  • Second floor Slab: 100% completed
  • Third floor Slab: 60% completed
  • Ground floor ceiling plastering : 20% completed
  • Back side retaining wall area: 100%
  • Front side retaining wall area: 50%

As per the current work status from our site, we are targeted to complete the following works by the end of JANUARY 2020

  • Retaining wall work -100% to be (west side )completed
  • Second floor Slab :100% to be completed
  • Third floor Slab :100% to be completed

Work status as on 10-01-2020, we have completed the following.

  • Retaining wall side ground floor slab -85% completed(west side portion )
  • Ground floor slab : 100 % completed
  • First floor Slab :100% completed
  • Second floor Slab :60% completed

As per the current work status from our site we are targeted to complete the following works by end of September 2019

  • Retaining wall work -25% to be completed
  • Basement floor slab :75 % to be completed

Work status as on 05.09.2019, we have completed the following

  • Retaining wall work -5% completed
  • Basement floor slab :30 % completed

Work status as on 05.08.2019, we have completed the following

  • Retaining wall work -on progressing
  • Earth work excavation- on Progressing
  • Raft slab work -On progressing