Artech Life Spaces - Progress

Work status as on 08-03-2023, we have completed the following.

ARTECH LIFE SPACES (TOWER-D)

  • Structural Works – All sub-structural and structural works-100% completed
  • Civil Works – Ceiling plastering and wall plastering – 100 % completed, Masonry – Block/ brick- 100 % completed, Internal plaster – 100 % completed
  • Internal Finishes – Main door – 100% completed, Waterproofing- 100% completed, Wall Tiling Work – 99% completed, Flooring – 99% completed, Putty works & Painting – 91% completed, Door frame fixtures – 100% completed, Handrails – 100% completed
  • Electrical, Plumbing & Firefighting works – Concealed plumbing works – 100% completed, Corridor handrail works – 100% completed, Wall and floor services, Risers – 100% completed, Centralised Gas piping system – 95% completed
  • Final Finishes – Door shutters – 100% completed, Final Painting – 90% completed, CP & Sanitaryware – (82 flats) 60% completed, Electrical final fixtures – 88% completed, Fire fighting final fixtures – 100% completed
  • External Finishes – Windows & Sliding doors – 98% completed, External Plastering – 100% completed, External Painting – 92% completed, Louvers/façade/wall cladding – 94% completed
  • Yard Work – External Infrastructure & MEP services & connections – 96% completed
  • Landscape – Hardscape – 95% completed, Landscape area – 95% completed
  • Mockup – Completed.

ARTECH LIFE SPACES (TOWER A)

  • Structural Works – Footings – 100 % completed, all slab completed – (98% of overall completed), RCC of treated water tank cover slab, Fire and drinking water tank wall and cover slab, Main stair cover slab and beams, terrace parapet 100% completed , rear side RCC retaining wall (35m) completed.
  • Civil Works – Ceiling plastering – stilt 1 level 100% ceiling plastering completed, Masonry – Block/ brick- up to 16th level completed, P1, P2 Passage brick work completed, Brick work – 17th floor Completed, Internal plastering – ceiling and wall – up to 17th level completed except client change apartments.
  • Internal Finishes – Waterproofing- up to 12th level completed,13th level (A &D) Completed, Painting and putty work – putty and primer – up to 14th level A,B,C,D flats completed,15 th level B,C,D Flats completed
  • Electrical, Plumbing & Firefighting works – Plumbing works – level 8th flats sunken floor work completed, concealed work of toilets – up to 6th floor completed, Electrical work – box fixing & piping upto 17th level completed, fire fighting piping work 6th level completed.
  • External Finishes – A & D front area external plastering completed, Service lift rear side external plastering completed, A flat rear side external plastering completed

ARTECH LIFE SPACES (TOWER B)

  • Structural Works – Footings – 89 nos completed out of 95 including lift (98%), Raft slab completed – 90% completed, Roof slab – Stilt 2 level roof slab 75 % completed, Stilt 1 – roof slab 70% completed, Roof slab podium – 70% completed, Level 1 to 11 – Type A, B, C & D flats completed, level 12th – Type A,B completed
  • Civil Works – Ceiling Plastering – level 1,2,3,4,5,6,7 (A,B,C,D) Completed, Masonry – Block/brick – level 2 (A ,B,C,D) Completed

ARTECH LIFE SPACES (TOWER C)

  • Structural Works – Footings – 121 nos: completed out of 136 nos:, Basement slab @ 101.35 – 65% completed & Basement slab @ 104.35 – 75% completed, sub structural works – 75% completed, slab completed – up to 17th level 100% Completed, 18th level (roof slab – terrace) – completed, Stair case roof slab, LMR base slab, Water Tank base slab – completed
  • Civil Works – Ceiling Plastering – basement ceiling – 80% completed, level 1 25% completed, 2nd-15th level, level 16 – 55% completed, Masonary/Block work-level 1 35% completed, 2nd – 13th level-100% completed, level 14th – 75% completed, level 15 – 70% completed, level 16 – 35% completed, level 17 – 20% completed, Inside Plastering- level 1 – 25% completed, 2nd – 12th level 100%, level 13 – 25% completed
  • Internal Finishes – Door frame fixtures – (84 flats) 50% completed, putty and painting works – level 2 (75% completed), level 3 (100% completed), level 4 (100% completed), level 5 (100% completed), level 6 (100% completed), level 7- 90%, level 8 – 100% completed, level 9 – 100%, level 10 – 30% completed, Water proofing – (level 3,4,5,6 & 7 all toilets in bedrooms completed) 95% completed
  • Electrical, Plumbing & Firefighting works – (electrical works – level 2 to level 13 – 80% completed), concealed plumbing works – level 3 – level 7(80% completed), fire fighting work @ level 3 to level 7 fittings and pipe installation completed
  • External Finishes – External plastering – Flat B and C balcony area plastering done from level 12 to level 1 completed, South side – (Flat H, level 18 to 11), Flat A and staircase side – level 18 completed

CLUB HOUSE

  • Structural Works – All sub-structural and structural works-completed
  • Civil Works – Ceiling plastering and wall Plastering- 100% Completed, Masonry – Block/ brick-100% Completed.
  • Internal Finishes – Waterproofing – 100% Completed, flooring – 80% completed, wall tiling – 80% completed, putty works & Painting- 90% Completed.
  • Electrical, Plumbing & Firefighting works – Concealed Plumbing works- 90% Completed, wall and floor risers – 50% completed.
  • Final Finishes – Fire fighting final fixtures – 75% completed
  • External Finishes – External Plastering – 100% Completed, External Painting-75% Completed.
  • Yard Work – External Infrastructure & MEP services & connections – 20% completed

As per the current work status from our site, we are targeted to complete the following works by the end of MARCH 2023.

ARTECH LIFE SPACES (TOWER-D)

  • Internal Finishes – Wall Tiling – 100% to be completed, flooring – 100% to be completed, Putty works and painting – 95% to be completed
  • Electrical, Plumbing & Firefighting works – Centralised Gas piping system – 97% to be completed.
  • Final Finishes – Final Painting – 94% to be completed, CP and Sanitary ware – 65% to be completed, Electrical final fixtures – 100% to be completed
  • External Finishes – Windows & Sliding doors – 100% to be completed, External Painting – 96% to be completed, Louvers/façade/wall cladding – 98% to be completed
  • Yard Work – External Infrastructure & MEP services & connections – 98% to be completed
  • Landscape – Hardscape – 100% to be completed, Specialist works in landscape area – 100% to be completed

ARTECH LIFE SPACES (TOWER A)

  • Structural Works – rear compound wall area retaining wall – (5m ht area) to be completed
  • Civil Works – Ceiling plastering and wall plastering – 17th floor 100% to be completed
  • Internal Finishes – Waterproofing – 13th level (B&C), 14th level (A,B,C,D) 100% to be completed, Painting Works – 16th (A,B,C,D) putty and primer work to be completed
  • Electrical, Plumbing & Firefighting works – Plumbing works – level 9th piping to be completed, Fire fighting Work piping work – 7th level to 10th level 100% piping to be completed
  • External Finishes – External Plastering – A Flat rear side 1st to 17th level hoist area 100% to be completed, D Flat balcony, m.bed, dress outside wall plastering 17th to 5th level parapet wall plastering inside terrace portion, service lift inside plastering to be completed

ARTECH LIFE SPACES (TOWER B)

  • Structural Works – Footings – 95 nos to be completed out of 95 (100 % to be completed (rock breaking work at STP area to be completed), Raft slab – 100% to be completed, Roof slab – 80 % to be completed in stilt level 2, Roof slab – 80 % to be completed in stilt 1, level 12 – C,D to be completed.
  • Civil Works – Ceiling Plastering – level 8th,9th level to be completed, block work for level 3 (A,B,C,D) to be completed

ARTECH LIFE SPACES (TOWER C)

  • Structural Works – Basement slab @ 101.35 – 70% to be completed & 104.35 – 80% to be completed, sub structural works – 80% to be completed
  • Civil Works – Ceiling Plastering- level 16 – 100% to be completed,Masonry – block/brick – level 14th – 100% to be completed, Inside plastering – level 13th – 40% to be completed.

CLUB HOUSE

  • Internal Finishes – flooring – 100% to be completed, wall tiling – 90% to be completed, putty works & Painting- 95% to be Completed.
  • Electrical, Plumbing & Firefighting works – Concealed Plumbing works -100% Completed, wall and floor risers – 75% to be completed.
  • Final Finishes – Fire fighting final fixtures – 100% to be completed
  • External Finishes – External Infrastructure & MEP services & connections – 35% to be completed

Work status as on 11-02-2023, we have completed the following.

ARTECH LIFE SPACES (TOWER-D)

  • Structural Works – All sub-structural and structural works-100% completed
  • Civil Works – Ceiling plastering and wall plastering – 100 % completed, Masonry – Block/ brick- 100 % completed, Internal plaster – 100 % completed
  • Internal Finishes – Main door – 100% completed, Waterproofing- 100% completed, Wall Tiling Work – 99% completed, Flooring – 99% completed, Putty works & Painting – 90% completed, Door frame fixtures – 100% completed, Handrails – 100% completed
  • Electrical, Plumbing & Firefighting works – Concealed plumbing works – 100% completed, Corridor handrail works – 100% completed, Wall and floor services, Risers – 100% completed, Centralised Gas piping system – 93% completed
  • Final Finishes – Door shutters – 100% completed, Final Painting – 90% completed, CP & Sanitaryware – (78 flats) 57% completed, Electrical final fixtures – 86% completed, Fire fighting final fixtures – 100% completed
  • External Finishes – Windows & Sliding doors – 98% completed, External Plastering – 100% completed, External Painting – 92% completed, Louvers/façade/wall cladding – 94% completed
  • Yard Work – External Infrastructure & MEP services & connections – 96% completed
  • Landscape – Hardscape – 92% completed, Landscape area – 95% completed
  • Mockup – Completed

ARTECH LIFE SPACES (TOWER A)

  • Structural Works – Footings – 100 % completed, all slab completed – (98% of overall completed), RCC of treated water tank cover slab, Fire and drinking water tank wall and cover slab, Main stair cover slab and beams, terrace parapet 100% completed , rear side RCC retaining wall (25m) completed.
  • Civil Works – Ceiling plastering – stilt 1 level 100% ceiling plastering completed, Masonry – Block/ brick- up to 16th level completed except client change flats, Brick work – 17th floor Completed, Internal plastering – ceiling and wall – up to 16th level completed except client change apartments.
  • Internal Finishes – Waterproofing- up to 12th level completed, Painting and putty work – putty and primer – up to 14th level A,B,C,D flats completed
  • Electrical, Plumbing & Firefighting works – Plumbing works – level 8th flats sunken floor work completed, concealed work of toilets – up to 6th floor completed, Electrical work – box fixing & piping upto 17th level completed, fire fighting piping work 2nd level completed.

ARTECH LIFE SPACES (TOWER B)

  • Structural Works – Footings – Footings – 88 nos completed out of 95 including lift (93%), Raft slab completed – 85% completed, Roof slab – Stilt 2 level roof slab 70 % completed, Stilt 1 – roof slab 70% completed, Roof slab podium – 70% completed, Level 1 to 11 – Type A, B, C & D flats completed.
  • Civil Works – Ceiling Plastering – level 1,2,3,4,5 completed, 6,7 (A & B) Completed, level 7 (C & D) progressing, Masonry – Block/brick – level 2A & B Completed

ARTECH LIFE SPACES (TOWER C)

  • Structural Works – Footings – 120 nos: completed out of 126 nos:, Basement slab @ 101.35 – 65% completed & Basement slab @ 104.35 – 75% completed , sub structural works – 75% completed, slab completed – up to 17th level 100% Completed, 18th level (roof slab) – 75% completed
  • Civil Works – Ceiling Plastering – basement ceiling – 80% completed, level 1 25% completed, 2nd-14th level, level 15 – 80% completed, level 16 – 25% completed, Masonary/Block work-level 1 35% completed, 2nd – 11th level-100% completed, level 12th – 100% completed, level 13th – 100% completed, level 14th – 45% completed, level 15 – 25% completed, level 16 – 15% completed, level 17 – 15% completed, Inside Plastering- level 1 – 25% completed, 2nd – 11th level 100%, level 12 – 50% completed
  • Internal Finishes – Door frame fixtures – (84 flats) 50% completed, putty and painting works – level 2 (75% completed), level 3 (100% completed), level 4 (100% completed), level 5 (100% completed), level 6 (100% completed), level 7- 70%, level 8 – 100% completed, level 9 – 70% completed, Water proofing – (level 3,4,5,6 & 7 all toilets in bedrooms completed) 95% completed
  • Electrical, Plumbing & Firefighting works – (electrical works – level 2 to level 12 – 80% completed), concealed plumbing works – level 3 – level 7(80% completed), fire fighting work @ level 3 to level 5 fittings and pipe installation completed
  • External Finishes – External plastering – Flat B and C balcony area plastering done from level 12 to level 6 completed

CLUB HOUSE

  • Structural Works – All sub-structural and structural works-completed
  • Civil Works – Ceiling plastering and wall Plastering- 100% Completed, Masonry – Block/ brick-100% Completed.
  • Internal Finishes – Waterproofing – 100% Completed, flooring – 80% completed, wall tiling – 80% completed, putty works & Painting- 90% Completed.
  • Electrical, Plumbing & Firefighting works – Concealed Plumbing works- 90% Completed, wall and floor risers – 50% completed.
  • Final Finishes – Fire fighting final fixtures – 75% completed
  • External Finishes – External Plastering – 100% Completed, External Painting-75% Completed.
  • Yard Work – External Infrastructure & MEP services & connections – 20% completed

As per the current work status from our site, we are targeted to complete the following works by the end of FEBRUARY 2023.

ARTECH LIFE SPACES (TOWER-D)

  • Internal Finishes – Wall Tiling – 100% to be completed, flooring – 100% to be completed, Putty works and painting – 95% to be completed
  • Electrical, Plumbing & Firefighting works – Centralised Gas piping system – 96% to be completed.
  • Final Finishes – Final Painting – 94% to be completed, CP and Sanitary ware – 63% to be completed, Electrical final fixtures – 100% to be completed
  • External Finishes – Windows & Sliding doors – 100% to be completed, External Painting – 96% to be completed, Louvers/façade/wall cladding – 98% to be completed
  • Yard Work – External Infrastructure & MEP services & connections – 95% to be completed
  • Landscape – Hardscape – 95% to be completed, Specialist works in landscape area – 100% to be completed

ARTECH LIFE SPACES (TOWER A)

  • Structural Works – rear compound wall area retaining wall – 15m length (5m ht area) to be completed
  • Civil Works – Ceiling plastering and wall plastering – 17th floor to be completed, Masonry – Block/ brick-Brick Masonry – P1,P2,P3 Passage area to be completed
  • Internal Finishes – Waterproofing – 13th level to be completed, Painting Works – 15th (A,B,C,D) putty and primer work to be completed
  • Electrical, Plumbing & Firefighting works – Plumbing works – level 9th flat sunken floor work to be completed, level 7th concealed works of A,B,C,D flats to be completed, Fire fighting Work piping work – 3rd to 6th level to be completed.
  • External Finishes – External Plastering – A & D Flat 1st to 17th level 100% to be completed, bed lift rear side wall plastering 100% to be completed

ARTECH LIFE SPACES (TOWER B)

  • Structural Works – Footings – 95 nos to be completed out of 95 (100 % to be completed (rock breaking work after dewatering for the STP area balance footing area to be completed), Raft slab – 100% to be completed, Roof slab – 80 % to be completed in stilt level 2, Roof slab – 80 % to be completed in stilt 1, level 12 – A,B,C,D to be completed.
  • Civil Works – Ceiling Plastering – level 7 (C & D), 8th,9th level to be completed, block work for level 1,2 and 3 to be completed

ARTECH LIFE SPACES (TOWER C)

  • Structural Works – Basement slab @ 101.35 – 70% to be completed & 104.35 – 80% to be completed, sub structural works – 80% to be completed, level 18th – 100% to be completed.
  • Civil Works – Ceiling Plastering- level 16 – 50% to be completed,Masonry – block/brick – level 14th – 75% to be completed, level 15 – 50% to be completed, Inside plastering – level 12th – 75% to be completed.

CLUB HOUSE

  • Internal Finishes – flooring – 100% to be completed, wall tiling – 90% to be completed, putty works & Painting- 95% to be Completed.
  • Electrical, Plumbing & Firefighting works – Concealed Plumbing works -100% Completed, wall and floor risers – 75% to be completed.
  • Final Finishes – Fire fighting final fixtures – 100% to be completed.
  • External Finishes – External Painting – 90% to be Completed.
  • Yard Work – External Infrastructure & MEP services & connections – 35% to be completed

Work status as on 14-01-2023, we have completed the following.

ARTECH LIFE SPACES (TOWER-D)

  • Structural Works – All sub-structural and structural works-100% completed
  • Civil Works – Ceiling plastering and wall plastering – 100 % completed, Masonry – Block/ brick- 100 % completed, Internal plaster – 100 % completed
  • Internal Finishes – Main door – 100% completed, Waterproofing- 100% completed, Wall Tiling Work – 99% completed, Flooring – 99% completed, Putty works & Painting – 90% completed, Door frame fixtures – 100% completed, Handrails – 100% completed
  • Electrical, Plumbing & Firefighting works – Concealed plumbing works – 100% completed, Corridor handrail works – 100% completed, Wall and floor services, Risers – 100% completed, Centralised Gas piping system – 92% completed
  • Final Finishes – Door shutters – 100% completed, Final Painting – 86% completed, CP & Sanitaryware – (72 flats) 52% completed, Electrical final fixtures – 86% completed, Fire fighting final fixtures – 100% completed
  • External Finishes – Windows & Sliding doors – 98% completed, External Plastering – 100% completed, External Painting – 90% completed, Louvers/façade/wall cladding – 93% completed
  • Yard Work – External Infrastructure & MEP services & connections – 94% completed
  • Landscape – Hardscape – 92% completed, Landscape area – 95% completed
  • Mockup – Completed

ARTECH LIFE SPACES (TOWER A)

  • Structural Works – Footings – 100 % completed, all slab completed – (98% of overall completed), RCC of treated water tank cover slab, Fire and drinking water tank wall and cover slab, Main stair cover slab and beams, terrace parapet 100% completed , rear side RCC retaining wall (15m) completed.
  • Civil Works – Ceiling plastering – stilt 1 level 100% ceiling plastering completed, Masonry – Block/ brick- up to 16th level completed except client change flats, Brick work – 17th floor Completed, Internal plastering – ceiling and wall – up to 15th level completed except client change apartments.
  • Internal Finishes – Waterproofing- up to 11th level completed, Painting and putty work – putty and primer – up to 13th level A,B,C,D flats completed
  • Electrical, Plumbing & Firefighting works – Plumbing works – level 7th flats sunken floor work completed, concealed work of toilets – up to 6th floor completed, Electrical work – box fixing & piping upto 16th level completed, fire fighting piping work 2nd level completed.

ARTECH LIFE SPACES (TOWER B)

  • Structural Works – Footings – 86 nos completed out of 95 including lift (91%), Raft slab completed – 80% completed, Roof slab – Stilt 2 level roof slab 70 % completed, Stilt 1 – roof slab 70% completed, Roof slab podium – 70% completed, Level 1,2,3,4,5,6,7,8,9,10 – Type A, B, C & D flats completed, level 11th – A & B completed.
  • Civil Works – Ceiling Plastering – level 1,2,3,4,5 completed

ARTECH LIFE SPACES (TOWER C)

  • Structural Works – Footings – 120 nos: completed out of 126 nos:, Basement slab @ 101.35 – 65% completed & Basement slab @ 104.35 – 75% completed , sub structural works – 75% completed, slab completed – up to 17th level 100% Completed, 18th level (roof slab) – 25% completed (G & H)
  • Civil Works – Ceiling Plastering – basement ceiling – 80% completed, level 1 25% completed, 2nd-12th level 100% Completed, level 13 – 100% completed, 14th – 45% completed, level 15 – 35% completed, Masonary/Block work-level 1 35% completed, 2nd – 11th level-100% completed, level 12th – 100% completed, level 13th – 100% completed, level 14th – 45% completed, Inside Plastering- level 1 – 25% completed, 2nd – 10th level 100%, level 11 – 85% completed
  • Internal Finishes – Door frame fixtures – (84 flats) 50% completed, putty and painting works – level 2 (75% completed), level 3 (100% completed), level 4 (100% completed), level 5 (100% completed), level 6 (100% completed), level 7- 70%, level 8 – 70% completed, Water proofing – (level 3,4,5 & 6 all toilets in bedrooms completed) 95% completed
  • Electrical, Plumbing & Firefighting works – (electrical works – level 2 to level 12 – 80% completed), concealed plumbing works – level 3 – level 6 (80% completed), fire fighting work @ level 3 – fittings completed
  • External Finishes – External plastering – Flat B and C balcony area plastering done from level 12 to level 6

CLUB HOUSE

  • Structural Works – All sub-structural and structural works-completed
  • Civil Works – Ceiling plastering and wall Plastering- 100% Completed, Masonry – Block/ brick-100% Completed.
  • Internal Finishes – Waterproofing – 100% Completed, flooring – 80% completed, wall tiling – 80% completed, putty works & Painting- 90% Completed.
  • Electrical, Plumbing & Firefighting works – Concealed Plumbing works- 90% Completed, wall and floor risers – 50% completed.
  • Final Finishes – Firefighting final fixtures – 75% completed
  • External Finishes – External Plastering – 100% Completed, External Painting-75% Completed.
  • Yard Work – External Infrastructure & MEP services & connections – 20% completed

As per the current work status from our site, we are targeted to complete the following works by the end of JANUARY 2023.

ARTECH LIFE SPACES (TOWER-D)

  • Internal Finishes – Wall Tiling – 100% to be completed, flooring – 100% to be completed, Putty works and painting – 95% to be completed
  • Electrical, Plumbing & Firefighting works – Centralised Gas piping system – 95% to be completed.
  • Final Finishes – Final Painting – 93% to be completed, CP and Sanitary ware – 60% to be completed, Electrical final fixtures – 100% to be completed
  • External Finishes – Windows & Sliding doors – 100% to be completed, External Painting – 95% to be completed, Louvers/façade/wall cladding – 98% to be completed
  • Yard Work – External Infrastructure & MEP services & connections – 95% to be completed
  • Landscape – Hardscape – 95% to be completed, Specialist works in landscape area – 100% to be completed

ARTECH LIFE SPACES (TOWER A)

  • Structural Works – rear compound wall area retaining wall – 10m length (5m ht area) to be completed
  • Civil Works – Ceiling plastering and wall plastering – 16th floor to be completed, Masonry – Block/ brick-Brick Masonry – terrace duct 100% to be completed, Lift machine room, stair, terrace toilet and wash area to be completed
  • Internal Finishes – Waterproofing – 12th level to be completed, Painting Works – 14th ( A,B,C,D) putty and primer work to be completed
  • Electrical, Plumbing & Firefighting works – Plumbing works – level 8th flat sunken floor work to be completed, level 7th concealed works of A,B,C,D flats to be completed. Electrical work – 17th level 100% to be completed, Fire fighting Work piping work – 3rd to 6th level to be completed.
  • External Finishes – External Plastering – A & D Flat 1st to 17th level 100% to be completed, bed lift rear side wall plastering 100% to be completed

ARTECH LIFE SPACES (TOWER B)

  • Structural Works – Footings – 95 nos to be completed out of 95 (100 % to be completed (rock breaking work after dewatering for the STP area balance footing area to be completed), Raft slab – 85% to be completed, Roof slab – 80 % to be completed in stilt level 2, Roof slab – 80 % to be completed in stilt 1, Level 11 – C,D to be completed, level 12 – A,B,C,D to be completed.
  • Civil Works – Ceiling Plastering – level 6 and 7 to be completed, block work for level 1,2 and 3 to be completed

ARTECH LIFE SPACES (TOWER C)

  • Structural Works – Footings – 17 more footings to be completed, Basement slab @ 101.35 – 70% to be completed & 104.35 – 80% to be completed, sub structural works – 80% to be completed, level 18th – 50% to be completed.
  • Civil Works – Ceiling Plastering- basement ceiling – 80% to be completed, level 14 – 50% to be completed, level 15 – 45% to be completed, Masonry – block/brick – level 14th – 50% to be completed, Inside plastering – level 11th – 90% to be completed.

CLUB HOUSE

  • Internal Finishes – flooring – 100% to be completed, wall tiling – 90% to be completed, putty works & Painting- 95% to be Completed.
  • Electrical, Plumbing & Firefighting works – Concealed Plumbing works -100% Completed, wall and floor risers – 75% to be completed.
  • Final Finishes – Fire fighting final fixtures – 100% to be completed
  • External Finishes – External Painting – 90% to be Completed.
  • Yard Work – External Infrastructure & MEP services & connections – 35% to be completed

Work status as on 13-12-2022, we have completed the following

As per the current work status from our site, we are targeted to complete the following works by the end of DECEMBER 2022.

ARTECH LIFE SPACES (TOWER-D)

  • Internal Finishes – Wall Tiling – 100% to be completed, flooring – 100% to be completed, Putty works and painting – 95% to be completed
  • Electrical, Plumbing & Firefighting works – Centralised Gas piping system – 95% to be completed (meter installation pending)
  • Final Finishes – Final Painting – 92% to be completed, CP and Sanitary ware – 55% to be completed, Electrical final fixtures – 100% to be completed
  • External Finishes – Windows & Sliding doors – 100% to be completed, External Painting – 95% to be completed, Louvers/façade/wall cladding – 98% to be completed
  • Yard Work – External Infrastructure & MEP services & connections – 95% to be completed
  • Landscape – Hardscape – 95% to be completed, Specialist works in landscape area – 100% to be completed

ARTECH LIFE SPACES (TOWER A)

  • Civil Works – Ceiling plastering and wall plastering – 10D, 16B & 16C to be completed, Masonry – Block/ brick- 14B,14C,15D to be completed, Brick Masonry – 17B & 17C to be completed, Lift machine room, stair, terrace toilet and wash area to be completed
  • Internal Finishes – Waterproofing – 11th level to be completed, Painting Works – 13th ( A,B,C,D) putty and primer work to be completed
  • Electrical, Plumbing & Firefighting works – Plumbing works – level 7th flat sunken floor work to be completed, level 6th concealed works of A,B,C,D flats to be completed. Electrical work – 17th level 100% to be completed, Fire fighting Work piping work – 1D Mockup flat, up to 6th level to be completed.

ARTECH LIFE SPACES (TOWER B)

  • Structural Works – Footings – 95 nos to be completed out of 95 (100 % to be completed (rock breaking work after dewatering for the balance footing area to be completed), Raft slab – 85% to be completed, Roof slab – 80 % to be completed in stilt level 2, Roof slab – 80 % to be completed in stilt 1, Level 10 – C,D to be completed, level 11 – A,B,C,D to be completed.
  • Civil Works – Ceiling Plastering – level 3 and 4 to be completed

ARTECH LIFE SPACES (TOWER C)

  • Structural Works – Footings – 18 more footings to be completed, Basement slab @ 101.35 – 70% to be completed & 104.35 – 80% to be completed, sub structural works – 80% to be completed, level 17th – 100% to be completed.
  • Civil Works – Ceiling Plastering- basement ceiling – 80% to be completed, level 13 – 100 % to be completed, level 14 – 50% more to be completed, Masonry – block/brick – level 12th – 100% to be completed, level 13th – 75% to be completed, Inside plastering – level 10th – 90% to be completed.

CLUB HOUSE

  • Internal Finishes – flooring – 100% to be completed, wall tiling – 90% to be completed, putty works & Painting- 95% to be Completed.
  • Electrical, Plumbing & Firefighting works – Concealed Plumbing works -100% Completed, wall and floor risers – 75% to be completed.
  • Final Finishes – Fire fighting final fixtures – 100% to be completed
  • External Finishes – External Painting – 90% to be Completed.
  • Yard Work – External Infrastructure & MEP services & connections – 35% to be completed

Work status as on 13-12-2022, we have completed the following.

ARTECH LIFE SPACES (TOWER-D)

  • Structural Works – All sub-structural and structural works-100% completed
  • Civil Works – Ceiling plastering and wall plastering – 100 % completed, Masonry – Block/ brick- 100 % completed, Internal plaster – 100 % completed
  • Internal Finishes – Main door – 100% completed, Waterproofing- 100% completed, Wall Tiling Work – 98% completed, Flooring – 98% completed, Putty works & Painting – 90% completed, Door frame fixtures – 100% completed, Handrails – 100% completed
  • Electrical, Plumbing & Firefighting works – Concealed plumbing works – 100% completed, Corridor handrail works – 100% completed, Wall and floor services, Risers – 100% completed, Centralised Gas piping system – 90% completed
  • Final Finishes – Door shutters – 100% completed, Final Painting – 85% completed, CP & Sanitaryware – (62 flats) 46% completed, Electrical final fixtures – 85% completed, Fire fighting final fixtures – 100% completed
  • External Finishes – Windows & Sliding doors – 98% completed, External Plastering – 100% completed, External Painting – 90% completed, Louvers/façade/wall cladding – 93% completed
  • Yard Work – External Infrastructure & MEP services & connections – 93% completed
  • Landscape – Hardscape – 90% completed, Landscape area – 95% completed
  • Mockup – Completed.

ARTECH LIFE SPACES (TOWER A)

  • Structural Works – Footings – 100 % completed, all slab completed – (98% of overall completed), RCC of treated water tank cover slab, Fire and drinking water tank wall and cover slab, Main stair cover slab and beams, terrace parapet 100% completed
  • Civil Works – Ceiling plastering – stilt 1 level 100% ceiling plastering completed, Masonry – Block/ brick- up to 16th level completed except client change flats, Brick work – 17A & D Completed, Internal plastering – ceiling and wall – up to 15th level completed except client change apartments.
  • Internal Finishes – Waterproofing- up to 10th level completed, Painting and putty work – putty and primer – up to 12th level A,B,C,D flats completed
  • Electrical, Plumbing & Firefighting works – Plumbing works – level 6th flats sunken floor work completed, concealed work of toilets – up to 5th floor completed, Electrical work – box fixing & piping upto 16th level completed

ARTECH LIFE SPACES (TOWER B)

  • Structural Works – Footings – 78 nos completed out of 95 including lift (82 % ), Raft slab completed – 80% completed, Roof slab – Stilt 2 level roof slab 70 % completed, Stilt 1 – roof slab 70% completed, Roof slab podium – 70% completed, Level 1,2,3,4,5,6,7,8,9 – Type A, B, C & D flats completed, level 10th – A & B completed.
  • Civil Works – Ceiling Plastering – level 1 and 2 completed

ARTECH LIFE SPACES (TOWER C)

  • Structural Works – Footings – 119 nos: completed out of 126 nos:, Basement slab @ 101.35 – 65% completed & Basement slab @ 104.35 – 75% completed , sub structural works – 75% completed, slab completed – up to 16th level 100% Completed, 17th level – 75% completed.
  • Civil Works – Ceiling Plastering – basement ceiling – 80% completed, level 1 25% completed, 2nd-12th level 100% Completed, level 13 – 90% completed, 14th – 45% completed, Masonary/Block work-level 1 35% completed, 2nd – 11th level-100% completed, level 12th – 90% completed, level 13th – 50% completed, Inside Plastering- level 1 – 25% completed, 2nd – 9th level 100%, level 10 – 70% completed
  • Internal Finishes – Door frame fixtures – (60 flats) 20% completed, putty and painting works – level 2 (75% completed), level 3 (100% completed), level 4 (100% completed), level 5 (100% completed), level 6 (75% completed), Water proofing – (level 3,4,5 & 6 all toilets in bedrooms completed) 70%
  • Electrical, Plumbing & Firefighting works – Wall and floor services, Risers – 55% completed (electrical works up to level 10), concealed plumbing works – level 3 – 100% completed, level 4 – 70% completed

CLUB HOUSE

  • Structural Works – All sub-structural and structural works-completed
  • Civil Works – Ceiling plastering and wall Plastering- 100% Completed, Masonry – Block/ brick-100% Completed.
  • Internal Finishes –
    Waterproofing – 100% Completed, flooring – 80% completed, wall tiling – 80% completed, putty works & Painting- 90% Completed.
  • Electrical, Plumbing & Firefighting works – Concealed Plumbing works- 90% Completed, wall and floor risers – 50% completed.
  • Final Finishes – Fire fighting final fixtures – 75% completed
  • External Finishes – External Plastering – 100% Completed, External Painting-75% Completed.
  • Yard Work – External Infrastructure & MEP services & connections – 20% completed

Work status as on 15-11-2022, we have completed the following.

ARTECH LIFE SPACES (TOWER-D)

  • Structural Works – All sub-structural and structural works-100% completed
  • Civil Works – Ceiling plastering and wall plastering – 100 % completed, Masonry – Block/ brick- 100 % completed, Internal plaster – 100 % completed
  • Internal Finishes – Main door – 100% completed, Waterproofing- 100% completed, Wall Tiling Work – 98% completed, Flooring – 98% completed, Putty works & Painting – 90% completed, Door frame fixtures – 100% completed, Handrails – 100% completed
  • Electrical, Plumbing & Firefighting works – Concealed plumbing works – 100% completed, Corridor handrail works – 100% completed, Wall and floor services, Risers – 100% completed, Centralised Gas piping system – 90% completed
  • Final Finishes – Door shutters – 100% completed, Final Painting – 83% completed, CP & Sanitaryware – (52 flats) 38% completed, Electrical final fixtures – 80% completed, Fire fighting final fixtures – 100% completed
  • External Finishes – Windows & Sliding doors – 98% completed, External Plastering – 100% completed, External Painting – 90% completed, Louvers/façade/wall cladding – 93% completed
  • Yard Work – External Infrastructure & MEP services & connections – 93% completed
  • Landscape – Hardscape – 90% completed, Landscape area – 95% completed
  • Mockup – Completed.

ARTECH LIFE SPACES (TOWER A)

  • Structural Works – Footings – 100 % completed, all slab completed – (98% of overall completed)
  • Civil Works – Ceiling plastering – stilt 1 level 100% ceiling plastering completed, Masonry – Block/ brick- up to 16th level completed except client change flats, Internal plastering – ceiling and wall – up to 13th level completed except client change apartments.
  • Internal Finishes – Waterproofing- up to 8th level completed, Painting and putty work – 9th level A,B,C,D flats completed
  • Electrical, Plumbing & Firefighting works – Plumbing works – level 5th flats sunken floor work completed, concealed work of toilets – 1st to 3rd completed, Electrical work – box fixing & piping upto 13th level completed

ARTECH LIFE SPACES (TOWER B)

  • Structural Works – Footings – 74 nos completed out of 95 including lift (71 % ), Raft slab completed – 80% completed, Roof slab – Stilt 2 level roof slab 70 % completed, Stilt 1 – roof slab 70% completed, Roof slab podium – 70% completed, Level 1,2,3,4,5,6,7,8 – Type A, B, C & D flats completed, level 9 – A & B completed.

ARTECH LIFE SPACES (TOWER C)

  • Structural Works – Footings – 119 nos: completed out of 126 nos:, Basement slab @ 101.35 – 65% completed & Basement slab @ 104.35 – 60% completed , sub structural works – 75% completed, slab completed – up to 16th level 100% Completed
  • Civil Works – Ceiling Plastering – basement ceiling – 78% completed, level 1 25% completed, 2nd-11th level 100% Completed, level 12 – 75% completed, 13th – 50% completed, Masonary/Block work-level 1 35% completed, 2nd – 11th level-100% completed, level 12th – 40% completed, level 13th – 30% completed, Inside Plastering- level 1 – 25% completed, 2nd – 8th level 100%, level 9 – 40% completed
  • Internal Finishes Door frame fixtures – (48 flats) 16% completed, putty and painting works – level 2 (75% completed), level 3 (95% completed), level 4 (30% completed), level 5 (75% completed), Water proofing – (level 3,4,5 all toilets in bedrooms completed) 70%
  • Electrical, Plumbing & Firefighting works – Wall and floor services, Risers – 35% completed (electrical works up to level 8), concealed plumbing works – level 3 – 80% completed

CLUB HOUSE

  • Structural Works – All sub-structural and structural works-completed
  • Civil Works – Ceiling plastering and wall Plastering- 100% Completed, Masonry – Block/ brick-100% Completed.
  • Internal Finishes – Waterproofing – 100% Completed, flooring – 80% completed, wall tiling – 80% completed, putty works & Painting- 90% Completed.
  • Electrical, Plumbing & Firefighting works – Concealed Plumbing works- 90% Completed, wall and floor risers – 50% completed.
  • Final Finishes – Fire fighting final fixtures – 75% completed
  • External Finishes – External Plastering – 100% Completed, External Painting-75% Completed.
  • Yard Work – External Infrastructure & MEP services & connections – 20% completed

As per the current work status from our site, we are targeted to complete the following works by the end of NOVEMBER 2022.

ARTECH LIFE SPACES (TOWER-D)

  • Internal Finishes – Wall Tiling – 100% to be completed, flooring – 100% to be completed, Putty works and painting – 95% to be completed
  • Electrical, Plumbing & Firefighting works – Centralised Gas piping system – 95% to be completed (meter installation pending)
  • Final Finishes – Final Painting – 90% to be completed, CP and Sanitary ware – 50% to be completed, Electrical final fixtures – 100% to be completed
  • External Finishes – Windows & Sliding doors – 100% to be completed, External Painting – 95% to be completed, Louvers/façade/wall cladding – 98% to be completed
  • Yard Work – External Infrastructure & MEP services & connections – 95% to be completed
  • Landscape – Hardscape – 95% to be completed, Specialist works in landscape area – 100% to be completed

ARTECH LIFE SPACES (TOWER A)

  • Structural Works – RCC of treated water tank cover slab, Fire and drinking water tank wall and cover slab, Main stair cover slab and beams, terrace parapet 100% to be completed
  • Civil Works – Ceiling plastering and wall plastering – 10D,11B,14A,14D, 15A & 15D, 16A & 16D to be completed, Masonry – Block/ brick- 14B,14C,15D to be completed, Brick Masonry – 17A & 17D to be completed.
  • Internal Finishes – Waterproofing – 9th & 10th level to be completed, Painting Works – 11th ( A,B,C,D) putty and primer work to be completed
  • Electrical, Plumbing & Firefighting works – Plumbing works – level 6th flat sunken floor work to be completed, level 4th and 5th concealed works of A,B,C,D flats to be completed. Electrical work – 16th level 100% to be completed.

ARTECH LIFE SPACES (TOWER B)

  • Structural Works – Footings – 95 nos to be completed out of 95 (100 % to be completed (rock breaking work after dewatering for the balance footing area to be completed), Raft slab – 85% to be completed, Roof slab – 80 % to be completed in stilt level 2, Roof slab – 80 % to be completed in stilt 1, Level 9 – C,D to be completed, level 10 – A,B,C,D to be completed.

ARTECH LIFE SPACES (TOWER C)

  • Structural Works Footings – 18 more footings to be completed, Basement slab @ 101.35 – 70% to be completed & 104.35 – 70% to be completed, sub structural works – 80% to be completed
  • Civil Works – Ceiling Plastering- basement ceiling – 80% to be completed, level 12 – 100 % to be completed, level 13 – 50% more to be completed

CLUB HOUSE

  • Internal Finishes – flooring – 100% to be completed, wall tiling – 90% to be completed, putty works & Painting- 95% to be Completed.
  • Electrical, Plumbing & Firefighting works – Concealed Plumbing works -100% Completed, wall and floor risers – 75% to be completed.
  • Final Finishes – Fire fighting final fixtures – 100% to be completed
  • External Finishes – External Painting – 90% to be Completed.
  • Yard Work – External Infrastructure & MEP services & connections – 35% to be completed

Work status as on 11-10-2022, we have completed the following.

ARTECH LIFE SPACES (TOWER-D)

  • Structural Works – All sub-structural and structural works-100% completed
  • Civil Works – Ceiling plastering and wall plastering – 100 % completed, Masonry – Block/ brick- 100 % completed, Internal plaster – 100 % completed
  • Internal Finishes – Main door – 100% completed, Waterproofing- 100% completed, Wall Tiling Work – 98% completed, Flooring – 98% completed, Putty works & Painting – 90% completed, Door frame fixtures – 100% completed, Handrails – 100% completed
  • Electrical, Plumbing & Firefighting works – Concealed plumbing works – 100% completed, Corridor handrail works – 100% completed, Wall and floor services, Risers – 100% completed, Centralised Gas piping system – 90% completed
  • Final Finishes – Door shutters – 100% completed, Final Painting – 83% completed, CP & Sanitaryware – (51 flats) 38% completed, Electrical final fixtures – 80% completed, Fire fighting final fixtures – 100% completed
  • External Finishes – Windows & Sliding doors – 98% completed, External Plastering – 100% completed, External Painting – 90% completed, Louvers/façade/wall cladding – 93% completed
  • Yard Work – External Infrastructure & MEP services & connections – 93% completed
  • Landscape – Hardscape – 90% completed
  • Mockup – Completed.

ARTECH LIFE SPACES (TOWER A)

  • Structural Works – Footings – 100 % completed, slab completed – Terrace level A & B 100% completed, B & C, Passage 17th level completed (90% of overall completed)
  • Civil Works – Ceiling plastering – stilt 1 level 100% ceiling plastering completed, Masonry – Block/ brick- 14A, 14D, 15A, 15D, 15B Completed, Internal plastering – ceiling and wall – 12B, 12C, 12D, 12A completed
  • Internal Finishes – Waterproofing- up to 8th level completed, Painting and putty work – 8th level A,B,C,D flats completed
  • Electrical, Plumbing & Firefighting works – Plumbing works – level 5th flats sunken floor work completed

ARTECH LIFE SPACES (TOWER B)

  • Structural Works – Footings – 67 nos completed out of 95 including lift (71 % ), Raft slab completed – 80% completed, Roof slab – Stilt 2 level roof slab 70 % completed, Stilt 1 – roof slab 70% completed, Roof slab podium – 70% completed, Level 1,2,3,4,5,6,7 – Type A, B, C & D flats completed, level 8 – A & B completed.

ARTECH LIFE SPACES (TOWER C)

  • Structural Works – Footings – 119 nos: completed out of 126 nos:, Basement slab @ 101.35 – 65% completed & Basement slab @ 104.35 – 50% completed , sub structural works – 77% completed, structural works – 75% completed, slab completed – up to 15th level 100% Completed, level 16th – 25% completed.
  • Civil Works – Ceiling Plastering – basement ceiling – 78% completed, level 1 25% completed, 2nd-11th level 100% Completed, level 12 – 50% completed, 13th – 25% completed, Masonary/Block work-level 1 35% completed, 2nd – 9th level-100% completed, 10th level – 85% completed, level 11th – 40% completed, Inside Plastering- level 1 – 25% completed, 2nd – 7th level 100%, level 8 – 75% completed
  • Internal Finishes – Door frame fixtures – (40 flats) 14% completed, putty and painting works – level 2 (75% completed), level 3 (95% completed), level 4 (30% completed), level 5 (25% completed), Water proofing – (level 3,4,5 all toilets in bedrooms completed) 70%
  • Electrical, Plumbing & Firefighting works – Wall and floor services, Risers – 35% completed (electrical works up to level 8), concealed plumbing works – level 3 – 80% completed

CLUB HOUSE

  • Structural Works – All sub-structural and structural works-completed
  • Civil Works – Ceiling plastering and wall Plastering- 100% Completed, Masonry – Block/ brick-100% Completed.
  • Internal Finishes – Waterproofing – 100% Completed, flooring – 80% completed, wall tiling – 80% completed, putty works & Painting- 90% Completed.
  • Electrical, Plumbing & Firefighting works – Concealed Plumbing works- 90% Completed, wall and floor risers – 50% completed.
  • Final Finishes – Fire fighting final fixtures – 75% completed
  • External Finishes – External Plastering – 100% Completed, External Painting-75% Completed.
  • Yard Work – External Infrastructure & MEP services & connections – 20% completed

As per the current work status from our site, we are targeted to complete the following works by the end of OCTOBER 2022.

ARTECH LIFE SPACES (TOWER-D)

  • Internal Finishes – Wall Tiling – 100% to be completed, flooring – 100% to be completed, Putty works and painting – 95% to be completed
  • Electrical, Plumbing & Firefighting works – Centralised Gas piping system – 95% to be completed (meter installation pending)
  • Final Finishes – Final Painting – 90% to be completed, CP and Sanitary ware – 50% to be completed, Electrical final fixtures – 100% to be completed
  • External Finishes – Windows & Sliding doors – 100% to be completed, External Painting – 95% to be completed, Louvers/façade/wall cladding – 98% to be completed
  • Yard Work – External Infrastructure & MEP services & connections – 95% to be completed
  • Landscape – Hardscape – 95% to be completed

ARTECH LIFE SPACES (TOWER A)

  • Structural Works – Slab and beams – Terrace floor slab of B & C, Passage to be completed.
  • Civil Works – Ceiling plastering and wall plastering – 13B, 13C, 10A, 15A to be completed, Masonry – Block/ brick- 14A, 14D, 15A, 15D & 15B to be completed
  • Internal Finishes – Painting Works – 9th ( A,B,C,D) putty and primer work to be completed
  • Electrical, Plumbing & Firefighting works – Plumbing works – level 6th flat sunken floor work to be completed, level 1 concealed works of A,B,C,D flats to be completed.

ARTECH LIFE SPACES (TOWER B)

  • Structural Works – Footings – 95 nos to be completed out of 95 (100 % to be completed (rock breaking work after dewatering for the balance footing area to be completed), Raft slab – 85% to be completed, Roof slab – 80 % to be completed in stilt level 2, Roof slab – 80 % to be completed in stilt 1, Level 8 – C,D to be completed, level 9 – A,B,C,D to be completed.

ARTECH LIFE SPACES (TOWER C)

  • Structural Works – Footings – 18 more footings to be completed, Basement slab @ 101.35 – 70% to be completed & 104.35 – 50% more to be completed, sub structural works – 80% to be completed, structural works – level 16th – 50% to be completed.
  • Civil Works – Ceiling Plastering- basement ceiling – 80% to be completed, level 12 – 100 % to be completed, level 13 – 50% to be completed, Masonary/block work level 11th 50% to be Completed.

CLUB HOUSE

  • Internal Finishes – flooring – 100% to be completed, wall tiling – 90% to be completed, putty works & Painting- 95% to be Completed.
  • Electrical, Plumbing & Firefighting works – Concealed Plumbing works -100% Completed, wall and floor risers – 75% to be completed.
  • Final Finishes – Fire fighting final fixtures – 100% to be completed
  • External Finishes – External Painting – 90% to be Completed.
  • Yard Work – External Infrastructure & MEP services & connections – 35% to be completed

Work status as on 17-09-2022, we have completed the following.

ARTECH LIFE SPACES (TOWER-D)

  • Structural Works – All sub-structural and structural works-100% completed
  • Civil Works – Ceiling plastering and wall plastering – 100 % completed, Masonry – Block/ brick- 100 % completed, Internal plaster – 100 % completed
  • Internal Finishes – Main door – 100% completed, Waterproofing- 100% completed, Wall Tiling Work – 98% completed, Flooring – 98% completed, Putty works & Painting – 90% completed, Door frame fixtures – 100% completed, Handrails – 100% completed
  • Electrical, Plumbing & Firefighting works – Concealed plumbing works – 100% completed, Corridor handrail works – 100% completed, Wall and floor services, Risers – 100% completed, Centralised Gas piping system – 90% completed
  • Final Finishes – Door shutters – 100% completed, Final Painting – 80% completed, CP & Sanitaryware – (49 flats) 36% completed, Electrical final fixtures – 80% completed, Fire fighting final fixtures – 100% completed
  • External Finishes – Windows & Sliding doors – 95% completed, External Plastering – 100% completed, External Painting – 85% completed, Louvers/façade/wall cladding – 90% completed
  • Yard Work – External Infrastructure & MEP services & connections – 90% completed
  • Landscape – Hardscape – 80% completed
  • Mockup – Completed.

ARTECH LIFE SPACES (TOWER A)

  • Structural Works – Footings – 100 % completed, slab completed – Up to Level 17th 100% completed (85% of overall completed)
  • Civil Works – Footings – 100 % completed, slab completed – Up to Level 17th 100% completed (85% of overall completed)
  • Internal Finishes – Waterproofing- up to 6th level completed, Painting and putty work – 6th level A,B,C,D flats completed
  • Electrical, Plumbing & Firefighting works – Plumbing works – level 5th flats sunken floor work completed

ARTECH LIFE SPACES (TOWER B)

  • Structural Works – Footings – 64 nos completed out of 95 including lift (67 % ), Raft slab completed – 80% completed, Roof slab – Stilt 2 level roof slab 70 % completed, Stilt 1 – roof slab 70% completed, Roof slab podium – 70% completed, Level 1,2,3,4,5 – Type A, B, C & D flats completed, level 6 – A & B completed.

ARTECH LIFE SPACES (TOWER C)

  • Structural Works – Footings – 118 nos: completed out of 126 nos:, Basement slab @ 101.35 – 65% completed & Basement slab @ 104.35 – 50% completed , sub structural works – 77% completed, structural works – 75% completed, slab completed – up to 14th level 100% Completed, level 15th – 75% completed.
  • Civil Works – Ceiling Plastering – basement ceiling – 78% completed, level 1 25% completed, 2nd-10th level 100% Completed, level 11 – 90% completed, Masonary/Block work-level 1 35% completed, 2nd – 9th level-100% completed, 10th level – 75% completed, Inside Plastering- level 1 – 25% completed, 2nd – 6th level 100%, level 7 – 95% completed
  • Internal Finishes – Door frame fixtures – 34 flats completed, putty and painting works – level 2 (75% completed), level 3 (95% completed), level 4 (30% completed), Water proofing – (level 3,4,5 all toilets in bedrooms completed) 70%
  • Electrical, Plumbing & Firefighting works – Wall and floor services, Risers – 35% completed (electrical works up to level 8), concealed plumbing works – level 3 – 70% completed

CLUB HOUSE

  • Structural Works – All sub-structural and structural works-completed
  • Civil Works – Ceiling plastering and wall Plastering- 100% Completed, Masonry – Block/ brick-100% Completed.
  • Internal Finishes – Waterproofing – 100% Completed, flooring – 80% completed, wall tiling – 80% completed, putty works & Painting- 85% Completed.
  • Electrical, Plumbing & Firefighting works – Concealed Plumbing works- 90% Completed, wall and floor risers – 50% completed.
  • Final Finishes – Fire fighting final fixtures – 50% completed
  • External Finishes – External Plastering – 100% Completed, External Painting-70% Completed.

As per the current work status from our site, we are targeted to complete the following works by the end of SEPTEMBER 2022.

ARTECH LIFE SPACES (TOWER-D)

  • Internal Finishes – Wall Tiling – 100% to be completed, flooring – 100% to be completed, Putty works and painting – 100% to be completed
  • Electrical, Plumbing & Firefighting works – Centralised Gas piping system – 95% to be completed (meter installation pending)
  • Final Finishes – Final Painting – 90% to be completed, CP and Sanitary ware – 50% to be completed, Electrical final fixtures – 100% to be completed
  • External Finishes – Windows & Sliding doors – 100% to be completed, External Painting – 95% to be completed, Louvers/façade/wall cladding – 95% to be completed
  • Yard Work – External Infrastructure & MEP services & connections – 95% to be completed
  • Landscape – Hardscape – 95% to be completed

ARTECH LIFE SPACES (TOWER A)

  • Structural Works – Slab and beams – Terrace floor slab to be completed.
  • Civil Works – Ceiling plastering and wall plastering – 12B, 12C, 12D, 12A to be completed, Masonry – Block/ brick- 14A, 14D, 15A, 15D & 15B to be completed
  • Internal Finishes – Waterproofing- up to 8th level 100% to be completed, Painting Works – 7th and 8th A,B,C,D putty and primer work to be completed
  • Electrical, Plumbing & Firefighting works – Plumbing works – level 6th flat sunken floor work to be completed

ARTECH LIFE SPACES (TOWER B)

  • Structural Works – Footings – 79 nos to be completed out of 95 (83 % to be completed (rock breaking work after dewatering for the balance footing area to be completed), Raft slab – 85% to be completed, Roof slab – 80 % to be completed in stilt level 2, Roof slab – 80 % to be completed in stilt 1, Level 6 – C,D to be completed, level 7 – A,B,C,D to be completed.

ARTECH LIFE SPACES (TOWER C)

  • Structural Works – Footings – 19 more footings to be completed, Basement slab @ 101.35 – 70% to be completed & 104.35 – 50% more to be completed, sub structural works – 80% to be completed, structural works – level 15th – 100% to be completed.
  • Civil Works – Ceiling Plastering- basement ceiling – 80% to be completed, level 11 – 100 % to be completed, Masonary/block work level 10th 100% to be Completed , Inside plastering level 7 – 100% to be completed

CLUB HOUSE

  • Internal Finishes – flooring – 100% to be completed, wall tiling – 90% to be completed, putty works & Painting- 95% to be Completed.
  • Electrical, Plumbing & Firefighting works – Concealed Plumbing works -100% Completed, Corridor handrail works – 20% to be Completed, wall and floor risers – 75% to be completed.
  • Final Finishes – Fire fighting final fixtures – 70% to be completed
  • External Finishes – External Painting – 90% to be Completed.

Work status as on 09-07-2022, we have completed the following.

ARTECH LIFE SPACES (TOWER-A)

  • Structural Works – Footings – 100 % completed, slab completed – Up to Level 14th 100 % completed and Type A & D 15th level completed (70% of overall completed )
  • Civil Works – Ceiling plastering – stilt 1 level 100% ceiling plastering completed, Masonry – Block/ brick- up to 9th level, 11A,11D, 12A, 12D completed, Internal plastering – ceiling and wall – 7C, 8B, 8C, 9D, & 5B completed
  • Internal Finishes – Waterproofing- up to 4th level completed, Painting – Level 1 & 2 A,B,C,D Flats putty and primer work completed
  • Electrical, Plumbing & Firefighting works – Plumbing works – level 3rd flat sunken floor work completed

ARTECH LIFE SPACES (TOWER B)

  • Structural Works – Footings – 60 nos completed out of 95 including lift (63 % ), Raft slab completed – 80% completed, Roof slab – Stilt 2 level roof slab 70 % completed, Stilt 1 – roof slab 70% completed, Roof slab podium – 70% completed, Level 1,2 – Type A, B, C & D flats completed, Level 3 A &B Completed.

ARTECH LIFE SPACES (TOWER C)

  • Structural Works – Footings – 8 more footings completed (105 nos: completed out of 126 nos:), Basement slab @ 101.35 – 65% completed & Basement slab @ 104.35 – 40% completed , sub structural works – 75% completed, structural works – 75% completed, slab completed – up to 13th level 100% Completed
  • Civil Works – Ceiling Plastering – basement ceiling – 70% completed, level 1 25% completed, 2nd-10th level 100% Completed, Masonary/Block work-level 1 35% completed, 2nd – 8th level-100% completed, 9th level – 75% completed, Inside Plastering level 1 – 25% completed, 2nd – 5th level 100%, level 6 – 30% completed
  • Internal Finishes – Door frame fixtures – 20 flats completed, putty and painting works – level 2 (20% completed)
  • Electrical, Plumbing & Firefighting works – Wall and floor services, Risers – 35% completed (electrical works up to level 6)

CLUB HOUSE

  • Structural Works – All sub-structural and structural works-completed
  • Civil Works – Ceiling plastering and wall Plastering- 100% Completed, Masonry – Block/ brick-100% Completed.
  • Internal Finishes – Waterproofing – 100% Completed, flooring – 75% completed, wall tiling – 60% completed, putty works & Painting- 75% Completed.
  • Electrical, Plumbing & Firefighting works – Concealed Plumbing works- 90% Completed, wall and floor risers – 50% completed.
  • External Finishes – Fire fighting final fixtures – 20% completed
  • External Finishes – External Plastering – 100% Completed, External Painting-70% Completed.

As per the current work status from our site, we are targeted to complete the following works by the end of JULY 2022.

ARTECH LIFE SPACES (TOWER-A)

  • Structural Works – Slab and beams – Type 15 th B & C, 16th A & D, stair and passage of 15th to be completed.
  • Civil Works – Ceiling plastering and wall plastering – 5A, 7B, 11A & 11D 100% to be completed, Masonry – Block/ brick- 11B, 11C, 12B, 12C, 10A, & 10D 100% to be completed
  • Internal Finishes – Waterproofing- 5th level 100% to be completed, Painting Works – 3B, 3C, 3A, 3D, 4A, & 4D putty and primer work 100% to be completed
  • Electrical, Plumbing & Firefighting works – Plumbing works – level 4th flat sunken floor work to be completed

ARTECH LIFE SPACES (TOWER B)

  • Structural Works – Footings – 79 nos to be completed out of 95 (83 % to be completed (rock breaking work after dewatering for the balance footing area to be completed), Raft slab – 85% to be completed, Roof slab – 80 % to be completed in stilt level 2, Roof slab – 80 % to be completed in stilt 1, Level 3 – Type C & D to be completed, Level 4 – Type A, B, C & D to be completed, Level 5 A & B to be completed.

ARTECH LIFE SPACES (TOWER C)

  • Structural Works – Footings – 21 more footings to be completed, Basement slab @ 101.35 & 104.35 – 50% to be completed, sub structural works – 80% to be completed, structural works – 80% to be completed
  • Civil Works – Ceiling Plastering- basement ceiling – 80% to be completed, Masonary/block work level 9th 85% to be Completed , Inside plastering level 6 – 85% more to be completed

CLUB HOUSE

  • Internal Finishes – flooring – 100% to be completed, wall tiling – 80% to be completed, putty works & Painting- 90% to be Completed.
  • Electrical, Plumbing & Firefighting works – Concealed Plumbing works -100% Completed, Corridor handrail works – 20% to be Completed, wall and floor risers – 75% to be completed.
  • Final Finishes – Fire fighting final fixtures – 70% to be completed
  • External Finishes – External Painting – 90% to be Completed.

Work status as on 09-06-2022, we have completed the following.

ARTECH LIFE SPACES (TOWER-D)

  • Structural Works – All sub-structural and structural works-100% completed
  • Civil Works – Ceiling plastering and wall plastering – 100 % completed, Masonry – Block/ brick- 100 % completed, Internal plaster – 100 % completed
  • Internal Finishes – Main door – 100% completed, Waterproofing- 100% completed, Wall Tiling Work – 98% completed,Flooring – 98% completed, Putty works & Painting – 90% completed, Door frame fixtures – 100% completed, Handrails – 98% completed
  • Electrical, Plumbing & Firefighting works – Concealed plumbing works – 100% completed, Corridor handrail works – 100% completed, Wall and floor services, Risers – 100% completed, Centralised Gas piping system – 85% completed
  • Final Finishes – D Door shutters – 98% completed, Final Painting – 75% completed, CP & Sanitaryware – (24 flats) 17% completed, Electrical final fixtures – 80% completed, Fire fighting final fixtures – 100% completed
  • External Finishes – Windows & Sliding doors- 90% completed, External Plastering- 100% completed, External Painting – 85% completed, Louvers/façade/wall cladding – 60% completed
  • Yard Work – External Infrastructure & MEP services & connections – 60% completed
  • Landscape – Hardscape – 70% completed
  • Mockup – Completed.

ARTECH LIFE SPACES (TOWER A)

  • Structural Works – Footings – 100 % completed, slab completed – Up to Level 12th 100 % completed and Type A & D 14th level completed (68% of overall completed )
  • Civil Works – Ceiling plastering – stilt 1 level 100% ceiling plastering completed ) Masonry – Block/ brick- 5B,5C,9B,9C completed, Internal plastering – ceiling and wall – 8A,8D,6A,6B,6C,6D completed
  • Internal Finishes – Waterproofing- up to 4th level completed, Painting – 1A,1D,2A,2D putty and primer work completed
  • Electrical, Plumbing & Firefighting works – Plumbing works – level 2 flat sunken floor work completed

ARTECH LIFE SPACES (TOWER B)

  • Structural Works – Footings – 60 nos completed out of 95 including lift(63 % ), Raft slab completed – 80% completed, Roof slab – Stilt 2 level roof slab 70 % completed, Stilt 1 – roof slab 70% completed, Roof slab podium – 70% completed, Level 1 – Type A, B, C & D completed

ARTECH LIFE SPACES (TOWER C)

  • Structural Works – Footings – 8 more footings completed (105 nos: completed out of 126 nos:), Basement slab – 65% completed, sub structural works – 70% completed, structural works – 70% completed, slab completed – up to 12th level 100% Completed, level 13th – 25% completed
  • Civil Works – Ceiling Plastering – basement ceiling – 70% completed, level 1 25% completed, 2nd-8th level 100% Completed, 9th level 85% & 10th level 15% Completed & level 8 10% completed, Masonary/Block work-level 1 35% completed, 2nd – 6th level-100% completed , 7th level 95% Completed, 8th level – 75% completed, Inside Plastering level 1 – 25% completed, 2nd level 100% and 3rd level 90% Completed, level 4 100% completed, level 5 – 50% completed
  • Internal Finishes – Door frame fixtures – 20 flats completed
  • Electrical, Plumbing & Firefighting works – Wall and floor services, Risers – 25% completed

CLUB HOUSE

  • Structural Works – All sub-structural and structural works-completed
  • Civil Works – Ceiling plastering and wall Plastering- 100% Completed, Masonry – Block/ brick-100% Completed.
  • Internal Finishes – Waterproofing-80% Completed, flooring – 40% completed, putty works & Painting- 50% Completed.
  • Electrical, Plumbing & Firefighting works – Concealed Plumbing works- 80% Completed.
  • External Finishes – External Plastering,-100% Completed, External Painting-20% Completed.

As per the current work status from our site, we are targeted to complete the following works by the end of JUNE 2022.

ARTECH LIFE SPACES (TOWER-D)

  • Internal Finishes – Wall Tiling – 100% to be completed, flooring – 100% to be completed, Putty works and painting – 100% to be completed, Handrail Fixing – 100% to be completed
  • Electrical, Plumbing & Firefighting works – Centralised Gas piping system – 95% to be completed
  • Final Finishes – Door shutters -100 % to be completed, Final Painting – 90% to be completed, CP and Sanitary ware – 25% to be completed, Electrical final fixtures – 100% to be completed
  • External Finishes – Windows & Sliding doors- 100% to be completed, External Painting – 95% to be completed, Louvers/façade/wall cladding – 90% to be completed
  • Yard Work – External Infrastructure & MEP services & connections – 85% to be completed
  • Landscape – Hardscape – 95% to be completed

ARTECH LIFE SPACES (TOWER A)

  • Structural Works – Slab and beams – Type 13th and 14th B & C, 15th A & D, 100% to be completed
  • Civil Works – Ceiling plastering and wall plastering – 7C, 8B, 8C, 9D,5B 100% to be completed, Masonry – Block/ brick- 7B,11A,11D, 12A,12D 100% to be completed
  • Internal Finishes – Waterproofing- 5th level 100% to be completed, Painting Works – 1B, 1C, 3A, 3D putty and primer work 100% to be completed
  • Electrical, Plumbing & Firefighting works – Plumbing works – level 3rd flat sunken floor work to be completed

ARTECH LIFE SPACES (TOWER B)

  • Structural Works – Footings – 79 nos to be completed out of 95 (83 % to be completed, Raft slab – 85% to be completed, Roof slab – 80 % to be completed in stilt level 2, Roof slab – 80 % to be completed in stilt 1, Roof slab -Podium- 80% to be completed, Level 2 – Type A, B, C & D to be completed, Level 3 – Type C & D to be completed

ARTECH LIFE SPACES (TOWER C)

  • Structural Works – Footings – 21 more footings to be completed, Basement slab – 80% to be completed, sub structural works – 80% to be completed, structural works – 75% to be completed, slab level 13th 100% to be completed
  • Civil Works – Ceiling Plastering- basement ceiling – 80% to be completed, level 9th 100% & level 10 20% to be Completed, Masonary/block work level 7th,8th level 100% to be Completed , Inside plastering level-3 100% to be Completed, level 5 – 50% more to be completed

CLUB HOUSE

  • Internal Finishes – Waterproofing-100% to be Completed, flooring – 60% to be completed, putty works & Painting- 70% to be Completed.
  • Electrical, Plumbing & Firefighting works – Concealed Plumbing works -100% Completed, Corridor handrail works – 20% to be Completed, Centralised Gas piping system-20% to be Completed.
  • External Finishes – External Painting-40% to be Completed.

Work status as on 12-04-2022, we have completed the following.

TOWER-D

  • Structural Works – All sub-structural and structural works-100% completed
  • Civil Works – Ceiling plastering and wall plastering – 100 % completed, Masonry – Block/ brick- 100 % completed, Internal plaster – 100 % completed
  • Internal Finishes – Main door – 98% completed, Waterproofing- 98% completed, Wall Tiling Work – 98% completed,Flooring – 98% completed, Putty works & Painting – 90% completed, Door frame fixtures – 100% completed, Handrails – 80% completed
  • Electrical, Plumbing & Firefighting works – Concealed plumbing works – 98% completed, Corridor handrail works – 100% completed, Wall and floor services, Risers – 90% completed, Centralised Gas piping system – 85% completed
  • Final Finishes – Door shutters – 98% completed, Final Painting – 60% completed, CP & Sanitaryware – (11 flats) 8% completed, Electrical final fixtures – 90% completed
  • External Finishes – Windows & Sliding doors- 85% completed, External Plastering- 100% completed, External Painting – 85% completed, Louvers/facade/wall cladding – 2% completed
  • Yard Work – External Infrastructure & MEP services & connections – 50% completed
  • Mockup – Completed.

TOWER A

  • Structural Works – Footings – 100 % completed, slab completed – Up to Level 9th 100 % completed and Type A & D 11th level completed (52% of overall completed )
  • Civil Works – Ceiling plastering – stilt 1 level 100% ceiling plastering completed ) ,up to 5th floor completed, Masonry – Block/ brick- 4th level work completed & 5th A,D & 6th B,C & 7th A,D,C & 8th A,D completed, Internal plaster – 4th level 100% flat completed.
  • Internal Finishes – Waterproofing- 1st & 2nd level completed.
  • Electrical, Plumbing & Firefighting works – Plumbing works – level 1 A & D flat sunken floor work completed.

TOWER B

  • Structural Works – Footings – 60 nos completed out of 95 including lift(63 % ), Raft slab completed – 75% completed, Roof slab – Stilt 2 level roof slab 70 % completed

TOWER C

  • Structural Works – Footings – 8 more footings completed (116 nos: completed out of 126 nos:), Basement slab – 35% completed, slab completed – up to 11th level 100% Completed.
  • Civil Works – Ceiling Plastering – basement ceiling – 45% completed, level 1 25% completed, 2nd-5th level 100% Completed, 6th level 75% & 7th level 50% Completed, Masonary/Block work-level 1 35% completed, 2nd – 4th level-100% completed , 5th level 60% Completed.Inside Plastering level 1 – 25% completed, 2nd level 100% and 3rd level 90% Completed.
  • Internal Finishes – Door frame fixtures – 12 flats completed (8%)

CLUB HOUSE

  • Structural Works – All sub-structural and structural works-completed
  • Civil Works – Ceiling plastering and wall Plastering- 100% Completed, Masonry – Block/ brick-100% Completed.
  • Internal Finishes – Waterproofing-80% Completed, flooring – 30% completed, putty works & Painting- 50% Completed.
  • Electrical, Plumbing & Firefighting works – Concealed Plumbing works- 80% Completed.
  • External Finishes – External Plastering,-100% Completed, External Painting-20% Completed.

As per the current work status from our site, we are targeted to complete the following works by the end of APRIL 2022.

  • Internal Finishes – Main door – 100% to be completed, Waterproofing- 100% to be completed, Wall Tiling – 100% to be completed, flooring – 100% to be completed, Putty works and painting – 100% to be completed, Handrail Fixing – 90% to be completed
  • Electrical, Plumbing & Firefighting works -Concealed plumbing works- 100% to be completed, Wall and floor services, Risers – 100% to be completed, Centralised Gas piping system – 95% to be completed
  • Final Finishes – Door shutters -100 % to be completed, Final Painting – 90% to be completed, Electrical final fixtures – 100% to be completed
  • External Finishes – Windows & Sliding doors- 95% to be completed, External Painting – 95% to be completed, Louvers/facade/wall cladding – 60% to be completed
  • Yard Work – External Infrastructure & MEP services & connections – 80% to be completed,

TOWER A

  • Structural Works – Level 11th B and C to be completed & 12th A&D to be Completed.
  • Civil Works – Ceiling plastering -7A,7D,8D,5A,5D ceiling plastering to be completed, Masonry – Block/ brick- 9A, 9D, 8B, 8C 100% to be completed, Internal plaster – 7A, 7D, 8D, 5A, 5D 100% to be completed.
  • Internal Finishes – Waterproofing- 3rd level A, B, C, D 100% to be completed.
  • Electrical, Plumbing & Firefighting works – Plumbing works – level 1 B & C flat sunken floor work to be completed.

TOWER B

  • Structural Works – Footings – 79 nos completed out of 95 (83 % to be completed, Raft slab – 80% to be completed, Roof slab – 80 % to be completed in stilt level 2, Roof slab – 70 % to be completed in stilt 1, Roof slab -Podium- 30% to be completed

TOWER C

  • Structural Works – Footings – 10 more footings to be completed, Basement slab – 50% to be completed, slab level 12th 100% to be completed, level 13th 50% to be completed.
  • Civil Works – Ceiling Plastering- basement ceiling – 65% to be completed, level 6th100% & level 7 75% to be Completed, Masonry/blockwork up to 6th level 75% to be Completed, Inside plastering level-3 100% to be Completed, level 4 – 50% to be completed.

CLUB HOUSE

  • Internal Finishes – Waterproofing-100% to be Completed, flooring – 50% to be completed, putty works & Painting- 70% to be Completed.
  • Electrical, Plumbing & Firefighting works – Concealed Plumbing works -100% Completed, Corridor handrail works – 20% to be Completed, Centralised Gas piping system-20% to be Completed.
  • External Finishes – External Painting-40% to be Completed.

Work status as on 10-03-2022, we have completed the following.

TOWER-D

  • Structural Works – All sub-structural and structural works-100% completed
  • Civil Works – Ceiling plastering and wall plastering – 100 % completed, Masonry – Block/ brick- 100 % completed, Internal plaster – 100 % completed
  • Internal Finishes – Main door – 95% completed, Waterproofing- 98% completed, Wall Tiling Work – 90% completed,Flooring – 95% completed, Putty works & Painting – 85% completed, Door frame fixtures – 100% completed, Handrails – 80% completed
  • Electrical, Plumbing & Firefighting works – Concealed plumbing works – 90% completed, Corridor handrail works – 100% completed, Wall and floor services, Risers – 80% completed, Centralised Gas piping system – 80% completed
  • Final Finishes – Door shutters – 90% completed, Final Painting – 45% completed, CP & Sanitaryware – (2 flats) 1.5% completed, Electrical final fixtures – 45% completed
  • External Finishes – Windows & Sliding doors- 70% completed, External Plastering- 100% completed, External Painting – 70% completed
  • Yard Work – External Infrastructure & MEP services & connections – 20% completed
  • Mockup – Completed.

TOWER A

  • Structural Works – Footings – 100 % completed, slab completed – Up to Level 9th 100 % completed and Type A & D 10th level completed (47% of overall completed )
  • Civil Works – Ceiling plastering – stilt 1 level 100% ceiling plastering completed ) ,up to 4th floor completed, Masonry – Block/ brick- 4th level work completed & 5th A,D & B completed, Internal plaster – 3rd level A,B&D 100% flat completed.
  • Internal Finishes – Waterproofing- 1st & 2nd level completed.

TOWER B

  • Structural Works – Footings – 60 nos completed out of 95 including lift(63 % ), Raft slab completed – 70% completed, Roof slab – Stilt 2 level roof slab 30 % completed

TOWER C

  • Structural Works – Footings -10 more footing completed. slab completed – up to 11th level 100% Completed, 9th level 50% completed,
  • Civil Works – Ceiling Plastering 2nd-5th level 100% Completed, 6th level 50% & 7th level 25% Completed, Masonary/Block work- 2nd – 4th level-100% completed , 5th level 40% Completed.Inside Plastering level 1 – 25% completed, 2nd level 100% and 3rd level 40% Completed.

CLUB HOUSE

  • Structural Works – All sub-structural and structural works-completed
  • Civil Works – Ceiling plastering and wall Plastering- 98% Completed, Masonry – Block/ brick-100% Completed.
  • Internal Finishes – Waterproofing-80% Completed, putty works & Painting- 50% Completed.
  • Electrical, Plumbing & Firefighting works – Plumbing works-75% Completed.
  • External Finishes – External Plastering,-100% Completed, External Painting-20% Completed.

As per the current work status from our site, we are targeted to complete the following works by the end of MARCH 2022.

  • Internal Finishes – Main door – 100% to be completed, Waterproofing- 100% to be completed, Wall Tiling – 95% to be completed, flooring – 100% to be completed, Putty works and painting – 95% to be completed, Handrail Fixing – 90% to be completed
  • Electrical, Plumbing & Firefighting works – Concealed plumbing works- 100% to be completed, Wall and floor services, Risers – 90% to be completed, Centralised Gas piping system – 90% to be completed
  • Final Finishes – Door shutters -100 % to be completed, Final Painting – 60% to be completed, Electrical final fixtures – 55% to be completed
  • External Finishes – Windows & Sliding doors- 90% to be completed, External Painting – 90% to be completed
  • Yard Work – External Infrastructure & MEP services & connections – 30% to be completed

TOWER A

  • Structural Works – Level 10th B and C to be completed & 11th A&D to be Completed.
  • Civil Works – Ceiling plastering -5D,5B,5C,7B,7C,8A,8D ceiling plastering to be completed, Masonry – Block/ brick- Level 6th 100% to be completed, Internal plaster – 3C,4A&4D 100% to be completed.

TOWER B

  • Structural Works – Footings – 79 nos completed out of 95 (83 % to be completed, Raft slab – 80% to be completed, Roof slab – 65 % to be completed in stilt level 2, Roof slab – 30 % to be completed in stilt 1

TOWER C

  • Structural Works – Footings – 105 nos completed out of 126 nos, slab level 12th, 50% to be completed.
  • Civil Works – Ceiling Plastering- level 6th100% & level 7 80% to be Completed, Masonary/block work up to 5th level 100% to be Completed. ,Inside plastering level-4 50% to be Completed.

CLUB HOUSE

  • Civil Works – Ceiling plastering and wall plastering -100% to be completed.
  • Internal Finishes – Waterproofing-100% to be Completed, putty works & Painting- 70% to be Completed.
  • Electrical, Plumbing & Firefighting works – Plumbing works -100% Completed, Corridor handrail works – 20% to be Completed, Centralised Gas piping system-20% to be Completed.
  • External Finishes – External Painting-40% to be Completed.

Work status as on 09-04-2021, we have completed the following.

D BLOCK

  • RCC Work – Completed
  • BLOCK WORK: Upto 17th floor :- 100% completed
  • CEILING PLASTERING WORK: Upto 17th floor :- 100% completed
  • WALL PLASTERING: upto Level -17th:-100% completed
  • FLOORING: 2nd-9th floor -90% completed
  • ELECTRICAL LT WALL CHASING: Upto Level 17th -100% completed
  • WIRE PULLING: Upto 16th floor :- 100% completed
  • WALL PUTTY: Upto 10th floor :- 100% completed
  • FIRE WORK: Upto 17th floor :- 85%   completed
  • PLUMBING WORK : Upto 2th -12th level:- 100% completed.(except cp fittings)
  • WATER PROOFING: UPTO LEVEL 15th :-100% Completed

 A BLOCK

  • Footing work
  • Total 51 footiings completed (out of 57)
  • (UNIT A )first slab – 25% completed
  • (UNIT A)Second  slab – 25% completed
  • (UNIT A )third slab – 25%  completed
  • (UNIT A )roof slab – 100%  completed

 B BLOCK

  • Footing work – Total 4 footings completed (out of 76)

 C BLOCK

  • Footing work
  • Building area – 100% completed
  • Podium level :70% completed
  • Tower area stilt level (104.35 slab) – 100% completed
  • Tower area second slab at( 108.35):-85% completed.
  • Retaining area RCC work
  • RCC Work: Retaining wall tower area east side RCC 40Meters(Out of 47 meters )

CLUBHOUSE AREA

  • Rock breaking work- 100% completed
  • Column footing -100% column footing work completed.
  • 1st level slab:- 90% completed ,2nd level slab:-90% completed,3rd level slab-90% completed.,4th level slab-50% completed.
  • 1st level column:-100% completed,2nd level column-100% completed,3rd level column-100% completed,4th level column-70% completed.

As per the current work status from our site, we are targeted to complete the following works by the end of APRIL 2021.

  • FLOORING
    • Up to 13th floor -90% to be completed
  • WIRE PULLING
    • Up to 17th floor:- 100% to be completed
  • WALL PUTTY
    • Up to 15th floor:- 100% to be completed
  • FIREWORK
    • Up to 17th floor:- 90% to be completed
  • PLUMBING WORK
    • Up to 15th floor-90% to be completed.
  • WATERPROOFING
    • up to level 17th:-100% to be completed

A BLOCK

  • Footing work
    • 57 footings (100%)to be completed (out of 57)
    • (UNIT B )first slab – 100% to be completed

B BLOCK

  • 15 footings to be completed (out of 76)

C BLOCK

  • Footing work
    • Podium level:100% to be completed
    • second slab at( 108.35):-100% to be completed.
  • Retaining area RCC work
    • RCC Work:Retaining wall RCC 100% to be completed

CLUBHOUSE AREA

  • up to 4th level slab:-100% to be completed
  • up to 4th level column:-100% to be completed

Work status as on 11-03-2021, we have completed the following.

D BLOCK

  • RCC Work – Completed
  • BLOCK WORK: Upto 17th floor :- 100% completed
  • CEILING PLASTERING WORK: Upto 17th floor :- 100% completed
  • WALL PLASTERING: upto Level -17th:-100% completed
  • FLOORING: 2nd-9th floor -90% completed
  • ELECTRICAL LT WALL CHASING: Upto Level 17th -100% completed
  • WALL PUTTY: Upto 9th floor :- 100% completed
  • FIRE WORK: Upto 17th floor :- 80%   completed
  • PLUMBING WORK : Upto 2th -9th level:- 100% completed.(except cp fittings)
  • WATER PROOFING: UPTO LEVEL 13th :-100% Completed (except balcony)

 A BLOCK

  • Footing work
  • Total 35 footiings completed (out of 57)
  • (UNIT A )first slab – 25% completed
  • (UNIT A)Second  slab – 25% completed
  • (UNIT A )third slab – 25%  completed

C BLOCK

  • Footing work
  • Building area – 100% completed
  • Podium level :60% completed
  • stilt level (104.35 slab) – 95% completed
  • second slab at( 108.35):-70%  completed.
  • Retaining area RCC work
  • RCC Work: Retaining wall tower area east side RCC 40Meters(Out of 47 meters )

CLUBHOUSE AREA

  • Rock breaking work- 100% completed
  • Column footing -100% column footing work completed.
  • 1st level slab:- 90% completed ,2nd level column:-90% completed,3rd level slab-90% completed.

As per the current work status from our site, we are targeted to complete the following works by the end of MARCH 2021.

D BLOCK

  • FLOORING
    • Up to 10th floor -90% to be completed
    • Up to 15th floor:- 100%  to be completed
  • FIREWORK
    • Up to 17th floor:- 90%  to be completed
  • PLUMBING WORK
    • Up to 12th floor-90% to be completed.
  • WATERPROOFING
    • up to level 17th:-100% to be completed

A BLOCK

Footing work 

  • 40 footings to be  completed (out of 57)
  • (UNIT B )first slab – 25% to be completed

C BLOCK

Footing work 

  • Podium level:100% to be completed
  • Parking slab 1st level:- 100% to be completed
  • second slab at( 108.35):-100% to be completed.

Retaining area RCC work

  • RCC Work: Retaining wall RCC 100% to be completed.

CLUBHOUSE AREA

  • 1st level slab:-100% to be completed

 

As per the current work status from our site, we are targeted to complete the following works by the end of February 2021.

  • FLOORING: 2nd-4th floor -100% to be completed
  • ELECTRICAL LT WALL CHASING: Up to 15th floor:- 100% to be completed
  • FIREWORK: Up to 17th floor:- 100% to be completed
  • PLUMBING WORK: Up to 13th floor-90% to be completed.
  • WATERPROOFING: up to level 17th:-100% to be completed
  • TOWER A Footing work : 36 footings to be completed (out of 57)(UNIT A )third slab – 25% completed

C BLOCK

  • Footing work: Podium level:100% to be completed, Parking slab 1st level:- 100% to be completed, second slab at( 108.35):-100% to be completed.
  • Retaining area RCC work: Retaining wall RCC 100% to be completed.

CLUB HOUSE AREA

  • Rock breaking work- 100% to be completed
  • 1st level slab:-100% to be completed

Work status as on 09-02-2021, we have completed the following.

D BLOCK

  • RCC Work – Completed
  • Block Work: Up to 17th floor:- 100% completed
  • CEILING PLASTERING WORK: Up to 17th floor:- 100% completed
  • WALL PLASTERING: up to Level -17th:-100% completed
  • FLOORING: 2nd-4th floor -90% completed
  • ELECTRICAL LT WALL CHASING: Up to Level 17th -100% completed
  • WALL PUTTY: Up to 9th floor:- 100% completed
  • FIREWORK: Up to 15th floor :- 95% completed
  • PLUMBING WORK: Up to 9th level(DBCEF):- 90% completed, up to 8th floor (AGH)-90% completed.
  • WATER PROOFING: UPTO LEVEL 13th :-100% Completed (except balcony)

TOWER A

  • Footing work:Total 31 footiings completed (out of 57), (UNIT A )first slab – 25% completed, (UNIT A)Second slab – 25% completed( centering and shuttering)

C BLOCK

  • Footing work: Building area – 100% completed Podium level :60% completed, stilt level (104.35 slab) – 90% completed,second slab at( 108.35):-60% completed.
  • RCC Work :RCC Work: Retaining wall RCC 40Meters(Out of 47 meters )

CLUB HOUSE AREA

  • Rock breaking work- 95% completed
  • Column footing -100% column footing work completed.
  • 1st level slab:- 90% completed, 2nd level column:-90% completed, 3rd level slab-90% completed.

As per the current work status from our site, we are targeted to complete the following works by the end of JANUARY 2021

  • FLOORING: 2nd-4th floor -100% to be completed
  • ELECTRICAL LT WALL CHASING: Up to 15th floor:- 100% to be completed
  • FIREWORK: Up to 15th floor:- 100% to be completed
  • PLUMBING WORK: Up to 13th floor-90% to be completed.
  • WATERPROOFING: up to level 17th:-100% to be completed
  • TOWER A Footing work : 30 footings to be completed (out of 57)(UNIT A )third slab – 25% completed

C BLOCK

  • Footing work: Podium level:100% to be completed, Parking slab 1st level:- 100% to be completed, second slab at( 108.35):-100% to be completed.
  • Retaining area RCC work: Retaining wall RCC 100% to be completed.

CLUB HOUSE AREA

  • Rock breaking work- 100% to be completed
  • Column footing -100% column footing work completed.
  • 1st level slab:-100% to be completed

Work status as on 07-01-2021, we have completed the following.

D BLOCK

  • RCC Work – Completed
  • Block Work: Up to 17th floor:- 100% completed
  • CEILING PLASTERING WORK: Up to 17th floor:- 100% completed
  • WALL PLASTERING: up to Level -17th:-100% completed
  • FLOORING: 2nd-4th floor -90% completed
  • ELECTRICAL LT WALL CHASING: Up to Level 17th -100% completed
  • WALL PUTTY: Up to 8th floor:- 100% completed
  • FIREWORK: Up to 12th floor :- 95% completed
  • PLUMBING WORK: Up to 9th level(DBCEF):- 90% completed, up to 8th floor (AGH)-90% completed.
  • WATER PROOFING: UPTO LEVEL 13th :-100% Completed (except balcony)

TOWER A

  • Footing work:Total 26 footiings completed (out of 57), (UNIT A )first slab – 25% completed, (UNIT A)Second slab – 25% completed( centering and shuttering)

C BLOCK

  • Footing work: Building area – 100% completed,Podium level :50% completed, stilt level (104.35 slab) – 80% completed,second slab at( 108.35):-50% completed.
  • RCC Work :RCC Work: Retaining wall RCC 40Meters(Out of 47 meters )

CLUB HOUSE AREA

  • Rock breaking work- 95% completed
  • Column footing -90% column footing work completed.
  • 1st level slab:- 90% completed ,2nd level column:-90% completed,3rd level slab-90% completed.

As per the current work status from our site, we are targeted to complete the following works by the end of July 2020

D BLOCK

  • Floor Slab RCC Work: Terrace (ALL): 100% to be completed
  • Ceiling plastering work: level 16th -100% to be completed, level 17th -100% to be completed
  • Wall Plastering: upto level 14th- 100% to be completed.
  • ELECTRICAL LT WALL CHASING: upto Level 15th:-100% to be completed
  • WATER PROOFING upto level 10th: 100% to be completed

C BLOCK

  • Earth work excavation at Tower C portion- 100% to be completed
  • Footing work: Parking slab 1st level:-50% to be completed
  • Retaining area RCC work: Retaining wall rcc 100% to be completed.

CLUB HOUSE AREA

  • Rock breaking work- 100% to be completed

Work status as on 11-06-2020, we have completed the following.

D BLOCK

  • Floor Slab RCC Work : 15th -17th LeveL: 100% Completed, Terrace: (AB) – 100% completed. (C,D) :- ready for casting
  • Block work: Level -1 -100% completed, Level -2 -75 %(A,D,E,F,G,H) completed, Level -3-12 -100% completed, Level -13th -100% completed, (ABCDFGH) Level -14th -95% completed, Level-15th-80% completed.
  • Ceiling plastering work: LEVEL :1,-12th – (A,B,C,D,E,F,G,H)1 100% completed, LEVEL -14-15th -100% completed, LEVEL16th -50% completed
  • Wall Plastering: upto Level -12th:-100% completed, level 13th- 40% completed.
  • ELECTRICAL LT WALL CHASING: Upto Level 13th – 100% completed
  • PLUMBING WORK: LEVEL 2 -100% completed, LEVEL 3 –100% completed, LEVEL 4- (A,B,C,D,E,F,G)-100% completed, LEVEL 5 -(A,B,C,D,F,G,H)-: 100% completed, LEVEL 6 -(B,E,C,D,F,G,H)-: 100% completed, LEVEL 7 -(B,E,C,D,F)-: 100% completed
  • WATER PROOFING: UPTO LEVEL 6th :-100% Completed, LEVEL 7th, 8th :-90% Completed.

C BLOCK

  • Earth work excavation at Tower C portion- 95% completed
  • Footing work: Building area – Total 67 nos completed, Podium level :25% completed, stilt level (104.35 slab) – 35% completed
  • RCC Work :Retaining wall rcc 40Meters(Out of 47 meters )

CLUB HOUSE AREA

  • Rock breaking work- 85% completed
  • Column footing -90% column footing work completed.
  • 1st level slab:- 90% completed, 2nd level column:-85% completed
  • Painting (putty work): 2nd – 5th level-100% completed

As per the current work status from our site, we are targeted to complete the following works by the end of JANUARY 2020

LEGACY TOWER

  • Floor Slab RCC Work : 15 th level,16 th level – 100% to be completed.
  • Block work – upto Level -13-100% to be completed .
  • Ceiling plastering work – LEVEL -15 -100% to be Completed
  • Wall Plastering – Level10,11-100% to be completed
  • ELECTRICAL LT WALL CHASING – LEVEL :9,10, 11-100% to be Completed .
  • LEVEL 5:to be started

INSPIRE TOWER

Footing work

  • Building area -67nos to be completed(Total 67 nos)

Retaining area RCC work

  • RCC Work :Retaining wall rcc 100% to be completed .
  • Silt floor slab centering and shuttering get started

Work status as on 10-01-2020, we have completed the following.

LEGACY TOWER

  • Earth work excavation at Tower D portion- 100% completed
  • Rock breaking work at Tower D portion- 100% completed
  • Footing work – 100% completed
  • Stilt level (Podium slab) – 100% completed
  • Floor Slab RCC Work : 15th Level (A,B,G,H) Completed ,16(A,B,G,H )Casted ,(C,D )-Centering and shuttering on progressing .

Block work

  • Level -1 -100% completed
  • Level -2 -75 %(A,D,E,F,G,H) completed
  • Level -3-11 -100% completed .
  • Level -12th -65% completed

Ceiling plastering work

  • LEVEL :1,-12th – (A,B,C,D,E,F,G,H)1 100% completed.
  • LEVEL -14-75% completed

Wall Plastering

  • Level -1-10%(1D,1C,1B) completed
  • Level -2 -75 %(A,D,E,F,G,H) completed
  • Level -3-8*(A,B,C,D,E,F,G,H)-100%completed
  • Level -9-(A,H)100%completed

ELECTRICAL LT WALL CHASING

  • LEVEL :1,3,4,5,6,7,8(A,B,C,D,E,F,G,H)-100% Completed
  • LEVEL :2(A,D,H,G,E,F)-75% Completed
  • LEVEL :9(A,C)-100% Completed ,10th -(A,H) Completed

PLUMBING WORK

  • LEVEL 2 -(A,D,,E,F,G,H )-In progressing
  • LEVEL 3 -(A,C,D,E,F,H )-in progressing
  • LEVEL 4-6 -(D,E,F)-in progressing

WATER PROOFING

  • LEVEL 2-3(A,H,G,E,F,D) 100% Completed
  • LEVEL 3: 100% Completed ,LEVEL 4:In progress

INSPIRE TOWER

  • Earth work excavation at Tower C portion- 95% completed

Footing work

  • Building area -60nos completed(Total 67 nos)
  • Podium level :7Nos completed

Retaining area RCC work

  • RCC Work :Retaining wall rcc 40Meters(Out of 47 meters )

CLUB HOUSE AREA

  • Rock breaking work- 80% completed
  • Column footing -65% column footing work completed.

As per the current work status from our site we are targeted to complete the following works by end of September 2019
D Block

  • Floor Slab RCC Work : 13 th level& 14 th level – 100% to be completed.
  • Block work upto Level -11-100% to be completed .
  • Ceiling plastering work: LEVEL -12,13 -100% to be Completed
  • Wall Plastering: Up to Level -10-100% to be comppleted

C Block

  • Footing work – Building area -49nos to be completed(Total 67 nos)
  • Retaining area RCC Work :Retaining wall rcc 100% to be completed

Work status as on 05.09.2019, we have completed the following
D block

  • Earth work excavation at Tower D portion- 100% completed
  • Rock breaking work at Tower D portion- 100% completed
  • Footing work – 100% completed
  • Stilt level (Podium slab) – 100% completed
  • Floor Slab RCC Work : 1-12th level completed,13th- level( A ,B ),-Casted ,G&H -Rebar fixing on progress
  • Block work -Level -1-100% completed
  • Block work -Level -2 -75%(A,D,E,F,G,H) completed
  • Level -3-,4,5,6,7 ,8 th -100%completed
  • Ceiling plastering work: LEVEL :1,-10 th – (A,B,C,D,E,F,G,H)1 100% completed.
  • Ceiling plastering work: LEVEL -11 -40% Completed
  • Wall Plastering: Level -1-10%(1D,1E,1F) completed
  • Wall Plastering: Level -2 -75 %(A,D,E,F,G,H) completed
  • Wall Plastering: Level -3-90%(A,B,C,E,F,G,H)completed
  • Wall Plastering: Level -4-50%(A.E,F)completed
  • Wall Plastering: Level -5-D(Completed )-A in Progress
  • Wall Plastering: Level -6-E& F Completed ,B& G in Progress
  • Electrical LT Work -Wall Chasing: LEVEL :1(C,D,E,F )-75% Completed
  • Electrical LT Work -Wall Chasing: LEVEL :2(A,D,H,G,E,F)-75% Completed
  • Electrical LT Work -Wall Chasing: LEVEL :3(A,B,F,E,D,G )-100% Completed
  • Electrical LT Work -Wall Chasing: LEVEL :4(A,B,F,E,D,G )-100% Completed
  • Electrical LT Work -Wall Chasing: LEVEL :5(B,C,D,F,E,G )-80% Completed

C block

  • Earth work excavation at Tower C portion- 95% completed
  • Footing work – Building area -34nos completed(Total 67 nos)
  • Footing work – Retaining wall area-7 nos completed (Total 18 nos)
  • RCC Work :RCC Work :Retaining wall rcc 39 Meters(Out of 47 meters )

As per the current work status from our site we are targeted to complete the following works by end of August 2019
D Block

  • Floor Slab RCC Work : Floor Slab RCC Work : 12th &13 th level- 100 to be completed.
  • Block work upto Level -11-100% to be completed .
  • Ceiling plastering work: LEVEL -12,13 -100% to be Completed
  • Wall Plastering: Up to Level -10-100% to be comppleted

C Block

  • Footing work – Building area -45nos to be completed(Total 67 nos)
  • Retaining area RCC Work :Retaining wall rcc 45 Meters to be completed (Out of 47 meters )

Work status as on 05.08.2019, we have completed the following
D block

  • Earth work excavation at Tower D portion- 100% completed
  • Rock breaking work at Tower D portion- 100% completed
  • Footing work – 100% completed
  • Stilt level (Podium slab) – 100% completed
  • Floor Slab RCC Work : 1-11th level completed,12th- level( A ,B ,G,H),-Casted ,C&D -Rebar fixing ,(E&F)Centering and shuttering on Progressing
  • Block work -Level -1-100% completed
  • Block work -Level -2 -75 %(A,D,E,F,G,H) completed
  • Level -3-,4,5,6,7 ,8 th -100%completed
  • Ceiling plastering work: LEVEL :1,-10 th – (A,B,C,D,E,F,G,H)1 100% completed.
  • Ceiling plastering work: LEVEL -11 -40% Completed
  • Wall Plastering: Level -1-10%(1D,1E,1F) completed
  • Wall Plastering: Level -2 -75 %(A,D,E,F,G,H) completed
  • Wall Plastering: Level -3-90%(A,B,C,E,F,G,H)completed
  • Wall Plastering: Level -4-50%(A.E,F)completed
  • Electrical LT Work -Wall Chasing: LEVEL :1(C,D,E,F )-75% Completed
  • Electrical LT Work -Wall Chasing: LEVEL :2(A,D,H,G,E,F)-75% Completed
  • Electrical LT Work -Wall Chasing: LEVEL :3(A,B,F,E,D,G )-75% Completed

C block

  • Earth work excavation at Tower C portion- 95% completed
  • Footing work – Building area -30nos completed(Total 67 nos)
  • Footing work – Retaining wall area-7 nos completed (Total 18 nos)
  • RCC Work :RCC Work :Retaining wall rcc 35 Meters(Out of 47 meters )

As per the current work status from our site we are targeted to complete the following works by end of July 2019
D Block

  • Floor Slab RCC Work : 11th level- 100 to be completed,12 th level -50% to be completed.
  • Block work -Level -5&6-100% to be completed.
  • Ceiling plastering work: LEVEL -7,8,9 -100% to be Completed
  • Wall Plastering: Up to Level -6 -100% to be comppleted

C Block

  • Footing work – Building area -33nos to be completed(Total 67 nos)
  • RCC Work :Retaining wall rcc 45 Meters to be completed (Out of 47 meters)

Work status as on 06.07.2019, we have completed the following
D block

  • Earth work excavation at Tower D portion- 100% completed
  • Rock breaking work at Tower D portion- 100% completed
  • Footing work – 100% completed
  • Stilt level (Podium slab) – 100% completed
  • Floor Slab RCC Work : 1-10 th level completed,11 th- level A &B -Casted.
  • Block work -Level -1-100% completed
  • Block work -Level -2 -75 %(A,D,E,F,G,H) completed
  • Block work -Level -3-100%completed
  • Block work -Level -4 -50% (A,B,C,D) completed
  • Block work -Level -5- On Progressing
  • Ceiling plastering work: LEVEL :1,2,3,4,5,6- (A,B,C,D,E,F,G,H)1 100% completed.
  • Ceiling plastering work: LEVEL -7 -65% Completed
  • Wall Plastering: Level -1-10%(1D,1E,1F) completed
  • Wall Plastering: Level -2 -75 %(A,D,E,F,G,H) completed
  • Wall Plastering: Level -3-50%(A,E,F,G,H)completed
  • Electrical LT Work -Wall Chasing: LEVEL :1(C,D,E,F )-75% Completed
  • Electrical LT Work -Wall Chasing: LEVEL :2(A,D,H,G,E,F)-75% Completed
  • Electrical LT Work -Wall Chasing: LEVEL :3(A,B,F,E,D,G )-75% Completed

C block

  • Earth work excavation at Tower C portion- 95% completed
  • Footing work – Building area -23nos completed(Total 67 nos)
  • Footing work – Retaining wall area-7 nos completed (Total 18 nos)
  • RCC Work :Retaining wall rcc 35 Meters(Out of 47 meters )

As per the current work status from our site we are targeted to complete the following works by end of June 2019
D Block

  • column RCC work -10 th level – (A,B,C,D,E,F,G,H)100%completed
  • 10th level,11th level floor slab Rcc work -(100% to be completed)
  • Ceiling plastering work – upto 8th level -100% to be completed
  • Block work -upto 6 th level -100% to becompleted
  • Wall Plastering – up to -level-5-100% to be Completed

C Block

  • Footing work – 34nos to be completed(Total 67 nos)
  • Retaining wall work -100% to be completed

Work status as on 06.06.2019, we have completed the following
D block

  • Earth work excavation at Tower D portion- 100% completed
  • Rock breaking work at Tower D portion- 100% completed
  • Footing work – 100% completed
  • Stilt level (Podium slab) – 100% completed
  • 1st level, 2nd leve3rd level,4th level ,5th level,6 th level ,7 th level ,8 th level ,9 th level .column RCC work – (A,B,C,D,E,F,G,H)100%completed
  • 1-9 th level floor slab -100% completed,10 th level floor slab A,B,G,H (100%Completed),C,D,E,F(Shuttering completed),
  • Ceiling plastering work – 1,2,3,4- (A,B,C,D,E,F,G,H)1 100% completed,5level -100% completed,6 th level -60% completed
  • Block work – level -1,3 (A,B,C,D,E,F,G,H)100%completed -level -2- (A,D,E,F,G,H)100%completed ,level -4 (A,B,C,D)100%,,E(90%),F(50%), 5 th level -A,B,C,D(Started )-Level -6(A-30%)
  • Wall Plastering -level-2(A ,E,G,H)-100% Completed,level 1(1D -100% Completed),3A-(75% Completed)

C Block

  • Earth work excavation at Tower C portion- 95% completed
  • Soil Investigation test -completed
  • Footing work – 23nos completed(Total 67 nos)
  • Retaining wall area PCC work on progress














As per the current work status from our site we are targeted to complete the following works by end of May 2019
D Block

  • 8 th level column RCC Work :100% to be completed,9 th level column RCC Work :100% to be completed,
  • 9th level,10 th level floor slab Rcc work -(100% to be completed)
  • Ceiling plastering work – 5,6 th level -100% to be completed
  • Block work -upto 6 th level -100% to becompleted
  • Wall Plastering – up to -level-3-100% to be Completed

Work status as on 06.05.2019, we have completed the following
D block

  • Earth work excavation at Tower D portion- 100% completed
  • Rock breaking work at Tower D portion- 100% completed
  • Footing work – 100% completed
  • Stilt level (Podium slab) – 100% completed
  • 1st level, 2nd leve3rd level,4th level ,5th level,6 th level ,7 th level ,column RCC work – (A,B,C,D,E,F,G,H)100%completed
  • 8 th level column RCC Work :75%(A,B,C,D,G,H) completed
  • 1-8 th level floor slab -100% completed,9th level floor slab Rcc work – (A,B)100% completed ,(G,H ) Reinforcement completed,(C.D) Shuttering completed.
  • Ceiling plastering work – 1,2,3,4- (A,B,C,D,E,F,G,H)1 100% completed,5level -40% completed
  • Block work – level -1,2,3 (A,B,C,D,E,F,G,H)100%completed -level -4 (A,D)-100% completed,B-75 % Completed
  • Wall Plastering -level-2(A ,H)-100% Completed,G -wall plastering -25% completed,level 1(1B -90% Completed)

C Block

  • Earth work excavation at Tower C portion- 95% completed
  • Soil Investigation test -completed
  • Footing work – 14nos completed

As per the current work status from our site we are targeted to complete the following works by end of April 2019
D Block

  • 7th level column RCC – (C,D,E,F )100% to be Completed,
  • 8th level floor slab,9 th level RCC work – (A,B,C,D,E,F,G,H)100%completed
  • Block work -upto 6 th level -100% to becompleted
  • Wall Plastering – up to -level-3-100% Completed

C Block

  • Footing work – 100% to be completed

Work status as on 05.04.2019, we have completed the following
D Block

  • Earth work excavation at Tower D portion- 100% completed
  • Rock breaking work at Tower D portion- 100% completed
  • Footing work – 100% completed
  • Stilt level (Podium slab) – 100% completed
  • 1st level column RCC work – (A,B,C,D,E,F,G,H)100%completed
  • 2nd level floor slab Rcc work – (A,B,C,D,E,F,G,H)100% completed
  • 2nd level column RCC work – (A,B,C,D,E,F,G,H)100% completed
  • 3rd level floor Slab rcc work – (A,B,C,D,E,F,G,H)100% completed
  • 3rd level column RCC work – (A,B,C,D,E,F,G,H)100%completed
  • 4th level floor slab RCC work – (A,B,C,D,E,F,G,H)100%completed
  • 4th level column RCC – (A,B,C,D,E,F,G,H)100%completed
  • 5th level floor slab RCC work – (A,B,C,D,E,F,G,H)100%completed
  • 5th level column RCC – (A,B,C,D,E,F,G,H)100%completed
  • 6th level floor slab RCC work – (A,B,C,D,E,F,G,H)100%completed
  • 7th level floor slab RCC work – (A,B,C,D,E,F,G,H)100%completed
  • 7th level column RCC – (A,B,G,H )100% Completed
  • 8th level floor slab RCC work – (A,B,G,H)100%completed
  • Ceiling plastering work – 1,2,3,4- (A,B,C,D,E,F,G,H)1 100% completed,5,6 th level (A,B,C,D,E,F,G,H)95% completed
  • Block work – level -1 (A,B,C,D,E,F,G,H)100%completed ,level -1 (A,D,E,F,G,H)-100% completed,level -2 (A,E,F,G,H)-100% completed,
  • Wall Plastering -level-2(A )-100% Completed

C Block

  • Earth work excavation at Tower C portion- 95% completed
  • Soil Investigation test -completed
  • Footing work – 11nos completed

As per the current work status from our site we are targeted to complete the following works by end of March 2019
D Block

  • 7th level column RCC – (A,B,C,D,E,F,G,H)100% to be completed
  • 7th level floor slab RCC work – 100% to be completed
  • Ceiling plastering work – 5 th Level 100%to be completed
  • Block work -upto 5 th level -100% to be completed

C Block

  • Footing work – 15 nos to be completed

Work status as on 06-03-2019, we have completed the following
D Block

  • Earth work excavation at Tower D portion- 100% completed
  • Rock breaking work at Tower D portion- 100% completed
  • Footing work – 100% completed
  • Stilt level (Podium slab) – 100% completed
  • 1st level column RCC work – (A,B,C,D,E,F,G,H)100%completed
  • 2nd level floor slab Rcc work – (A,B,C,D,E,F,G,H)100% completed
  • 2nd level column RCC work – (A,B,C,D,E,F,G,H)100% completed
  • 3rd level floor Slab rcc work – (A,B,C,D,E,F,G,H)100% completed
  • 3rd level column RCC work – (A,B,C,D,E,F,G,H)100%completed
  • 4th level floor slab RCC work – (A,B,C,D,E,F,G,H)100%completed
  • 4th level column RCC – (A,B,C,D,E,F,G,H)100%completed
  • 5th level floor slab RCC work – (A,B,C,D,E,F,G,H)100%completed
  • 5th level column RCC – (A,B,C,D,E,F,G,H)100%completed
  • 6th level floor slab RCC work – (A,B,C,D,E,F,G,H)100%completed
  • 6th level column RCC – (A,B,C,D,E,F,G,H)100%completed
  • 7th level floor slab RCC work – centering and shuttering on progress
  • Ceiling plastering work – 1,2,3,4- (A,B,C,D,E,F,G,H)1 100% completed
  • Block work -upto 5 th level -50% completed

C Block

  • Earth work excavation at Tower C portion- 95% completed
  • Soil Investigation test -completed
  • Rock breaking work at Tower C portion- on progressing
  • Footing work – 6 nos completed

As per the current work status from our site we are targeted to complete the following works by end of February 2019
D BLOCK

  • 4th level column RCC – (C,D,E,F)100 %to be completed
  • 5th level floor slab RCC work – (C,D,E,F)100% to be completed
  • 6th level column RCC – (A,B,G &H)100% to be completed7th level floor slab RCC work –
  • (A,B,G &H)100% to be completed
  • Ceiling plastering work – 5 th Level(A,B,G,H flats) 100%to be completed
  • Block work -2nd and third level A,G,H-100% to be completed

C & D BLOCK

  • Upper Basement floor Slab RCC work – 100% to be completed

Work status as on 05-02-2019, we have completed the following
D BLOCK

  • Earth work excavation at Tower D portion- 100% completed
  • Rock breaking work at Tower D portion- 100% completed
  • Footing work – 100% completed
  • Stilt level (Podium slab) – 100% completed
  • 1st level column RCC work – (A,B,C,D,E,F,G,H)100%completed
  • 2nd level floor slab Rcc work – (A,B,C,D,E,F,G,H)100% completed
  • 2nd level column RCC work – (A,B,C,D,E,F,G,H)100% completed
  • 3rd level floor Slab rcc work – (A,B,C,D,E,F,G,H)100% completed
  • 3rd level column RCC work – (A,B,C,D,E,F,G,H)100%completed
  • 4th level floor slab RCC work – (A,B,C,D,E,F,G,H)100%completed
  • 4th level column RCC – (A,B,G &H)100%completed
  • 5th level floor slab RCC work – (A,B.G &H)100%completed
  • 5th level column RCC – (A,B.G &H)100%completed
  • 6th level floor slab RCC work – (A,B.G &H)100%completed
  • Ceiling plastering work – 1,2,3,4- 100% completed (A,B,G, H flats),1,2(C,D,E,F)completed.
  • Block work – 1st level (A,G,H)Completed.

C BLOCK

  • Earth work excavation at Tower C portion- 95% completed
  • Soil Investigation test -completed
  • Rock breaking work at Tower C portion- on progressing

As per the current work status from our site we are targeted to complete the following works by end of January 2019
D BLOCK

  • 3rd level column RCC work – 100% to be completed
  • 4th level floor Slab RCC work – 100% to be completed
  • 4th level column RCC -100 to be completed
  • 5th level floor slab RCC work – 100% to be completed
  • Ceiling plastering work – 1,2,3,4 Level 100%to be completed (A,B,G,H flats)
  • Block work -level(1,2,3) A,G,H-100% to be completed

C & D BLOCK

  • Upper Basement floor Slab RCC work – 100% to be completed

Work status as on 08-01-2019, we have completed the following
D BLOCK

  • Earth work excavation at Tower D portion- 100% completed
  • Rock breaking work at Tower D portion- 100% completed
  • Footing work – 99.50% completed
  • Stilt level (Podium slab) – 100% completed
  • 1st level column RCC work – 100%completed
  • 2nd level floor slab Rcc work – 100% completed
  • 2nd level column RCC work – 100% completed
  • 3rd level floor Slab rcc work – 100% completed
  • 3rd level column RCC work – (A,B.G &H)100%completed
  • 4th level floor slab RCC work – (A,B.G &H)100%completed
  • 4th level column RCC – (A,B.G &H)100%completed
  • 5th level floor slab RCC work – (A,B.G &H)100%completed
  • Ceiling plastering work – 1,2, 100% completed (A,B,G, H flats),3rd level- G,H in progress
  • Block work – 1st level (A,B )Completed.

C BLOCK

  • Earth work excavation at Tower C portion- 95% completed
  • Soil Investigation test -completed

As per the current work status from our site we are targeted to complete the following works by end of December 2019
D BLOCK

  • Footing work -100% to be completed
  • Stilt level (Podium slab) – 100% to be completed
  • 1st level column RCC work – 100% to be completed
  • 2nd level floor slab Rcc work – 80% to be completed
  • 2nd level column RCC work – 80% to be completed
  • 3rd level floor Slab rcc work – 60% to be completed
  • 3rd level column RCC work – 60% to be completed
  • 4th level floor Slab RCC work – 60% to be completed
  • 4th level column RCC – 60% to be completed(A,B&H flats)
  • 5th level floor slab RCC work – 60% to be completed(A,B,G&H flats)
  • Ceiling plastering work – 1,2,3,4,5 Level 100%to be completed (A,B,H flats)
  • Block work – 1st level -A,G,H,B-100% to be completed

Work status as on 06-12-2018, we have completed the following
D BLOCK

  • Earth work excavation at Tower D portion- 100% completed
  • Rock breaking work at Tower D portion- 100% completed
  • Footing work – 99.50% completed
  • Stilt level (Podium slab) – 90% completed
  • 1st level column RCC work – 60% completed (A,B,G&H)
  • 2nd level floor slab Rcc work – 60% completed (A,B.G &H)
  • 2nd level column RCC work – 60% completed (A,B.G &H)
  • 3rd level floor Slab rcc work – 60% completed (A,B.G &H)
  • 3rd level column RCC work – 60% completed (A,B.G &H)
  • 4th level floor slab RCC work – 60% completed (A,B.G &H)
  • 4th level column RCC – 60% completed (A,B.G &H)
  • 5th level floor slab RCC work – 50% completed(A,B, G&H flats)
  • Ceiling plastering work – 1,2, 80% completed (A,B,G, H flats),3rd ,4th ,5 th level on progressing
  • Block work – 1st level -A,G,H,B On progressing

C BLOCK

  • Earth work excavation at Tower C portion- 95% completed
  • Soil Investigation test -on progress

C & D BLOCK

  • Upper Basement floor Slab RCC work – 100% to be completed

As per the current work status from our site we are targeted to complete the following works by end of November 2018
D BLOCK

  • Footing work -100% to be completed
  • 1st level column RCC work – 100% to be completed
  • 2nd level floor slab Rcc work – 100% to be completed
  • 2nd level column RCC work – 90% completed
  • 3rd level floor Slab rcc work – 80% to be completed
  • 4th level floor Slab RCC work – 85% to be completed
  • 4th level column RCC – 80% to be completed
  • 5th level floor slab RCC work – 100% to be completed
  • Ceiling plastering work – 1st level and 2nd level – 100% to be completed
  • Block work – 1st level – 50% to be completed

C BLOCK

  • Earth work excavation at Tower C portion- 100% to be completed
  • Rock breaking work at Tower C portion- 100% to be completed

C & D BLOCK

  • Upper Basement floor Slab RCC work – 100% to be completed

Work status as on 16-11-2018, we have completed.
D BLOCK

  • Earth work excavation at Tower D portion- 100% completed
  • Rock breaking work at Tower D portion- 100% completed
  • Footing work – 98% completed
  • Stilt level (Podium slab) – 85% completed
  • 1st level column RCC work – 85% completed
  • 2nd level floor slab Rcc work – 60% completed
  • 2nd level column RCC work – 80% completed
  • 3rd level floor Slab rcc work – 60% to be completed
  • 3rd level column RCC work – 60% completed
  • 4th level floor Slab work – shuttering & steel work- 70% completed

C BLOCK

  • Earth work excavation at Tower C portion- 95% completed
  • Rock breaking work at Tower C portion – 95% completed

Work Schedule for the Month of July 2018 .

    • Rock breaking work at Tower D portion- 100% to be completed
    • Footing work – 100% to be completed
    • RCC for structure (Podium slab) – 95% to be completed
    • 1st floor Slab rcc work – 60% to be completed
    • Earth work excavation at Tower C portion- 100% to be completed
    • Rock breaking work at Tower C portion- 100% to be completed

Work status as on 05-06-2018, we have completed the following.

    • Earth work excavation at Tower D portion- 100% completed
    • Rock breaking work at Tower D portion- 95% completed
    • Footing work – 90% completed
    • 1st floor column steel work – started
    • Earth work excavation at Tower C portion- 65% completed
    • Rock breaking work at Tower C portion – 65% completed

As per the current work status from our site we are targeted to complete the following works by end of May 2018.

  • Earth work excavation at Tower D portion- 100% to be completed
  • Rock breaking work at Tower D portion- 100% to be completed
  • Footing work – 80% to be completed
  • Earth work excavation at Tower C portion- 100% completed
  • Rock breaking work at Tower C portion- 100% completed

Work status as on 05-05-2018, we have completed the following.

  • Earth work excavation at Tower D portion- 95% completed
  • Rock breaking work at Tower D portion- 95% completed
  • Footing work – 65% completed
  • RCC for structure – 20% completed
  • Earth work excavation at Tower C portion- 50% completed
  • Rock breaking work at Tower C portion- 35% completed

As per the current work status from our site we are targeted to complete the following works by end of April 2018

  • Earth work excavation at Tower D portion- 100% to be completed
  • Rock breaking work at Tower D portion- 100% to be completed
  • Footing work – 60% to be completed
  • Earth work excavation at Tower C portion- 100% completed
  • Rock breaking work at Tower C portion- 100% completed

Work status as on 1 9 -0 4-2018, we have completed.

  • Earth work excavation at Tower D portion- 95% completed
  • Rock breaking work at Tower D portion- 95% completed
  • Footing work – 40% completed
  • Earth work excavation at Tower C portion- 35% completed
  • Rock breaking work at Tower C portion- 30% completed

As per the current work status from our site we are targeted to complete the following works by end of March 2018

  • Earth work excavation at Tower D portion- 100% to be completed
  • Rock breaking work at Tower D portion- 100% to be completed
  • Footing work – 60% to be completed
  • Earth work excavation at Tower C portion- 100% completed
  • Rock breaking work at Tower C portion- 100% completed


Work status as on 1 3 -0 3 -2018, we have completed.

    • Earth work excavation at Tower D portion- 90% completed
    • Rock breaking work at Tower D portion- 90% completed
    • Footing work – 30% completed
    • Earth work excavation at Tower C portion- 30% completed
    • Rock breaking work at Tower C portion- 20% completed