Artech City Malathy - Progress

​​As per the current work status from our site we are targeted to complete the following works by end of March 2018

    • Inside painting work(1st coat) -100 % to be completed
    • Inside painting work(2nd coat)-100 % to be completed
    • Aluminium Windows and Ventilators -100% to be completed
    • Door shutter fixing- 100% to be completed
    • Electrical LT work-100% to be completed
    • Electrical HT work – 100 % to be completed
    • Tiling work -100% to be completed
    • CP sanitary fixing work – 100% to be completed
    • Yard work-100% to be completed

​Work status as on ​10-03-2018, we have completed the following.

  • Aluminium Windows and Ventilators – 1st floor(100% completed);2nd to 14th floor(98% completed)
  • Door shutter fixing- 1st,2nd,3rd floor(90% completed);4th & 5th floor (100% completed);6th,7th,& 8th floor (90% completed);9th floor(100% completed)10th floor (90% completed)11th floor(60% completed)12th floor(50% completed);13th &14th floor(90% completed)
  • Electrical LT work-BF (90% completed);GF(90% completed);1st floor (98% completed);2nd,3rd,4th,5th,6th & 7th floor (100% completed),8th floor(90% completed);9th floor(100% completed);10th floor(90% completed);11th floor(80% completed);12th floor(80% completed);13th & 14th floor(90% completed);Terrace floor(100% completed)
  • Electrical HT work – 90 % completed
  • Tiling work -1st to 6th floor(100% completed)7th,8th,9th &10th floor (100% completed);11th & 12th floor (90% completed);13th & 14th floor(95% completed); Terrace floor(100% completed)
  • Water Proofing work – GF to Terrace floor (100% completed)
  • Plumbing work- 1st to Terrace floor -100% completed
  • CP sanitary fixing work – 40% completed
  • Yard work- 95% completed

As per the current work status from our site we are targeted to complete the following works by end of February-2018

  • Wall plastering – 100% to be completed
  • Inside putty work -100% to be completed
  • Inside primer work – 100% to be completed
  • Inside painting work(1st coat) -100 % to be completed
  • Inside painting work(2nd coat)-100 % to be completed
  • Tiling work -100% to be completed​​
  • Electrical LT work-100% to be completed
  • Electrical HT work – 100 % to be completed
  • CP sanitary fixing work – 100% to be completed
  • Aluminium Windows and Ventilators -100% to be completed
  • Water Proofing work – 100% to be completed
  • Door shutter fixing- 100% to be completed
  • Yard work-100% to be completed


Work status as on 10​-02-2018, we have completed the following.

  • Inside primer work -BF (balance); GF to Terrace floor (100% completed)
  • Inside painting work(1st coat) -1st floor(90% completed);2nd,(60% completed);3rd to 9th floor, 13th & 14th floor(100% completed);10th,11th & 12th(50% completed)
  • Inside painting work(2nd coat) -1st,3rd,4th,5th&7th floor(50% completed);
  • External wall plastering work -100% completed
  • Outside painting work -100% completed
  • Tiling work -1st to 6th floor(100% completed)7th,8th,9th &10th floor (90% completed);11th & 12th floor (80% completed);13th & 14th floor(85% completed);)& Terrace floor(100% completed)
  • Electrical LT work-BF (50% completed);GF(90% completed);1st floor (98% completed);2nd to 14th &Terrace floor(100% completed)
  • Electrical HT work – 80 % completed
  • Plumbing work- 1st to Terrace floor -100% completed
  • CP sanitary fixing work – 30% completed
  • Aluminium Windows and Ventilators – 1st floor(100% completed);2nd to 14th floor(90% completed)
  • Water Proofing work – GF to Terrace floor (100% completed)
  • Door shutter fixing- 1st floor(90% completed);2nd to 9th floor(80% completed);10th to 14th floor(75% completed)
  • Yard work-80% completed

Work status as on 9-8-2017, we have completed

  • RCC for Structure – completed
  • Wall plastering – completed
  • Ceiling Plastering work – completed
  • Block /brick masonry – completed
  • Inside panting work -progressing
  • External wall plastering work – progressing

Work status as on 9-6-2017, we have completed

  • RCC for Structure – completed
  • Ceiling Plastering work – progressing
  • Wall plastering – progressing

Work status as on 9-5-2017, we have completed

  • RCC for Structure – completed
  • Ceiling Plastering work – completed
  • Block /brick masonry – progressing
  • Wall plastering – progressing

Work status as on 8-3-2017, we have completed

  • RCC for Structure – progressing
  • Wall plastering – progressing
  • External wall plastering work -progressing

Work status as on 8-2-2017, we have completed:

  • RCC for Structure – progressing
  • Ceiling Plastering work – progressing
  • Block /brick masonry – progressing
  • Wall plastering – progressing
  • External wall plastering work – 85% completed

Construction status as on June 2015:

  • Slab shuttering and steel work – 4th floor – progressing
  • Ceiling plastering – Ground, 1st and 2nd floor- completed
  • Block work – 1st floor – A Type Started

The following works are expected to be completed by the end of June 2015:

  • Slab RCC – 4th floor       -100% completion
  • Ceiling plastering – 3 rd &4th floor  -100% completion
  • Block work – 1st& 2nd floor   -100% completion
  • 1st floor Slab RCC work of Artech Malathy has been completed.
  • We are targeted to complete the 2nd Slab RCC work by the end of March 2015.
  • Ground floor slab of the project Artech Malathy, Vazhuthacaud, Trivandrum has been completed.
  • We are targeted to complete the Slab concrete work of 1st & 2nd floor by the end of January 2015.
  • Few snaps of model apartment is also attached here with for your reference.