Artech Rio - Progress

As per the current work status from our site we are targeted to complete the following works by end of September 2019

  • Lift Work -100% tobe completed
  • HT Electrical work-100% to be completed.
  • Common lobby work-100% to be completed
  • Grills &Handrails :2-18 th floor -100% to be completed

Work status as on 05.09.2019, we have completed the following

  • RCC for Structure – (Main building +Amenity Block – 100% completed
  • Ceiling plastering work – 100% completed
  • Block/Brick masonry – (Main Building +Amenity Block) – 100% completed
  • Door Frame Fixing -(GF+FF)100% completed,2-19 th floor (100% completed)
  • Electrical chasing work – 100% completed
  • Wall plastering work – GF to 19th floor – 100% completed
  • Wire pulling work – 100% Completed
  • DB Dressing & Switch fixing :GF-1 st floor (80% completed),SF -90% completed,3rd -85% completed,4 th -80% ,5 th -70%,6 th -60%,7 th -70%,8 th -60%,9 th -70%,10th -88%,11 th -85%,12 th -80%,13 th -70%,14 th -50%,15 th -50%,16 th -45%,17 th -55%,18 th -50%,19 th -50% completed.
  • Aluminium Doors And Window Fixing -100% completed
  • Tiling work -100%completed
  • Dadoing of Toilets& kitchen walls: 100% completed
  • water proofing work -100% completed
  • External plastering work ,Internal wall plastering – 100% completed
  • Door shutter Fixing -100% completed
  • Plumbing work -(GF,FF )95% completed,2-18th flooor (100% completed)
  • CP sanitary fittings -GF,FF-95% completed,SF-16 th floor -80% ,17 th -60% completed,18 th -20% completed.
  • Lift Work -90%completed
  • Painting : external painting completed.first coat painting (internal ) completed
  • Second coat painting :2 nd floor -60%,{3rd,4th ,6th ,8-9 th }-20% completed ,10 th -60%,11 th -20%,12 th -60%,13-40%,16 th -20% completed .
  • Reticulated Gas work-100% completed.
  • HT Electrical work-90% completed
  • Common lobby work-90% completed
  • Grills &Handrails :(GF+FF)-100% Completed,2-18 th floor -99% completed
  • Fire fighting -90% Completed
  • Yard Work:97% completed

As per the current work status from our site we are targeted to complete the following works by end of August 2019

  • Lift Work -100% tobe completed
  • HT Electrical work-100% to be completed.
  • Common lobby work-100% to be completed
  • Grills &Handrails :2-18 th floor -100% to be completed

Work status as on 05.08.2019, we have completed the following

  • RCC for Structure – (Main building +Amenity Block – 100% completed
  • Ceiling plastering work – 100% completed
  • Block/Brick masonry – (Main Building +Amenity Block) – 100% completed
  • Door Frame Fixing -(GF+FF)95% completed,2-19 th floor (100% completed)
  • Electrical chasing work – 100% completed
  • Wall plastering work – GF to 19th floor – 100% completed
  • Wire pulling work – 100% Completed
  • DB Dressing & Switch fixing :GF-1 st floor (80% completed),SF -90% completed,3rd -85% completed,4 th -80% ,5 th -70%,6 th -60%,7 th -70%,8 th -60%,9 th -70%,10th -88%,11 th -85%,12 th -75%,13 th -70%,14 th -50%,15 th -50%,16 th -45%,17 th -55%,18 th -50%,19 th -30% completed.
  • Aluminium Doors And Window Fixing -100% completed
  • Tiling work -100%completed
  • Dadoing of Toilets& kitchen walls: 100% completed
  • water proofing work -100% completed
  • External plastering work ,Internal wall plastering – 100% completed
  • Door shutter Fixing -100% completed
  • Plumbing work -(GF,FF )95% completed,2-18th flooor (100% completed)
  • CP sanitary fittings -GF,FF-90% completed,SF-16 th floor -80% ,17 th -40% completed,18 th -20% completed.
  • Lift Work -90%completed
  • Painting : external painting completed.first coat painting (internal ) completed
  • Second coat painting :2 nd floor -60%,3rd-5 th -20%,7th -60%,8-9 th -20%,10th -60%,11 th -20%,12 th -60%,13 th -40% ,16 th -20% completed.
  • Reticulated Gas work-100% completed.
  • HT Electrical work-90% completed
  • Common lobby work-90% completed
  • Grills &Handrails :(GF+FF)-100% Completed,2-18 th floor -98% completed
  • Fire fighting -80% Completed
  • Yard Work:97% completed

As per the current work status from our site we are targeted to complete the following works by end of July 2019

  • Aluminium Doors And Window Fixing -GF-19 th floor -100% completed.
  • Fire Work -100% to becompleted
  • Plumbing work -100% to be completed.
  • Lift Work -100% tobe completed
  • HT Electrical work-100% to be completed.
  • Common lobby work-100% to be completed
  • Grills &Handrails :2-18 th floor -100% to be completed

Work status as on 06.07.2019, we have completed the following

    • RCC for Structure – (Main building +Amenity Block – 100% completed
    • Ceiling plastering work – 100% completed
    • Block/Brick masonry – (Main Building +Amenity Block) – 100% completed
    • Door Frame Fixing -(GF+FF)95% completed,2-19 th floor (100% completed)
    • Electrical chasing work – 100% completed
    • Wall plastering work – GF to 19th floor – 100% completed
    • Wire pulling work – 100% Completed
    • DB Dressing & Switch fixing :GF-1 st floor (80% completed),SF -90% completed,3rd -85% completed,4 th -80% ,5 th -70%,6 th -60%,7 th -70%,8 th -60%,9 th -65%,10th -88%,11 th -85%,12 th -75%,13 th -65%,14 th -50%,15 th -50%,16 th -45%,17 th -55%,18 th -50%,19 th -30% completed.
    • Aluminium Doors And Window Fixing -GF-13th floor -100% completed,14-19 th floor -98% completed.
    • Tiling work -98%completed
    • Dadoing of Toilets& kitchen walls: 100% completed
    • Fire Work -80%completed
    • water proofing work -100% completed
    • External plastering work ,Internal wall plastering – 100% completed
    • Door shutter Fixing -100% completed
    • Plumbing work -(GF,FF )95% completed,2-18th flooor (100% completed)
    • CP sanitary fittings -GF,FF-90% completed,SF-5 th floor -80% completed,6 th -70%,7-8 th -60%,9 th -75%,10th -85%,11-12 th -65%,13 th -45%,14-15 th -60%,16 th -40%,17 th -20% completed
    • Lift Work -90%completed
    • Painting : external painting completed.first coat painting (internal ) GF-12 th floor -100% completed,13-19 th floor -80% completed.
    • Second coat painting :2 nd floor -60%,3rd-5 th -20%,7th -60%,8-9 th -20%,10th -60%,11 th -20%,12 th -60%,13 th -40% completed.
    • Reticulated Gas work-100% completed.
    • HT Electrical work-90% completed
    • Common lobby work-90% completed
    • Grills &Handrails :(GF+FF)-100% Completed,2-18 th floor -98% completed
    • Fire fighting -80% Completed
    • Yard Work:97% completed

As per the current work status from our site we are targeted to complete the following works by end of June 2019

        • Wire pulling work – 100% to be completed
        • Aluminium Doors And Window Fixing -GF-19 th floor -100% completed.
        • Fire Work -100% to becompleted
        • Plumbing work -100 % to be completed.
        • Lift Work -100% tobe completed
        • HT Electrical work-100% to be completed.
        • Common lobby work-100% to be completed
        • Grills &Handrails :2-18 th floor -100% to be completed

Work status as on 06.06.2019, we have completed the following

        • RCC for Structure – (Main building +Amenity Block – 100% completed
        • Ceiling plastering work – 100% completed
        • Block/Brick masonry – (Main Building +Amenity Block) – 100% completed
        • Door Frame Fixing -(GF+FF)95% completed,2-19 th floor (100% completed)
        • Electrical chasing work – 100% completed
        • Wall plastering work – GF to 19th floor – 100% completed
        • Wire pulling work – 95% Completed
        • DB Dressing & Switch fixing :GF-4 TH FLOOR (80% Completed),5-7(60% completed),8 th( 50%completed),9 th (60% completed),10 th (80% completed),10-12 th floor (75% completed),13 th -17th floor (45% completed)
        • Aluminium Doors And Window Fixing -GF-90%,FF-95%,SF-9 th Floor-13-100%,14 th-19th floor -98% completed.
        • Tiling work -GF-95% completed,FF-19 th floor -100% completed
        • Dadoing of Toilets& kitchen walls: 100% completed
        • Fire Work -80%completed
        • water proofing work -100% completed
        • External plastering work ,Internal wall plastering – 100% completed
        • Door shutter Fixing -100% completed
        • Plumbing work -(GF,FF )95% completed,2-18th flooor (100% completed)
        • CP sanitary fittings -GF,FF-90% completed,SF-80%,3-6th floor -60%,7-8(40%),9th(65%),10 th (85%),11-12 th(65%),13 th(45%),14-15th (60%),16 th(40%),17 th(20%)
        • Lift Work -90%completed
        • Painting : external painting completed.first coat painting (internal ) GF-12 th floor -100% completed,13-16 th floor -80% completed,17 th -19 th floor (80% completed),second coat painting -9-11 th (20%),12 th (60%),13 th &16th -40%,completed,
        • Reticulated Gas work-100% completed.
        • HT Electrical work-80% completed
        • Common lobby work-90% completed
        • Grills &Handrails :(GF+FF)-100% Completed,2-18 th floor -98% completed
        • Fire fighting -80% Completed
        • Yard Work:97% completed

As per the current work status from our site we are targeted to complete the following works by end of May 2019

        • Wire pulling work – 100% to be completed
        • Aluminium Doors And Window Fixing -GF-19 th floor -100% completed.
        • Fire Work -100% to be completed
        • Plumbing work -100 % to be completed.
        • Lift Work -100% to be completed
        • HT Electrical work-100% to be completed.
        • Common lobby work-100% to be completed
        • Grills &Handrails :2-18 th floor -100% to be completed

Work status as on 06.05.2019, we have completed the following

        • RCC for Structure – (Main building +Amenity Block) – 100% completed
        • Ceiling plastering work – 100% completed
        • Block/Brick masonry – (Main Building +Amenity Block) – 100% completed
        • Door Frame Fixing -(GF+FF)95% completed,2-19 th floor (100% completed)
        • Electrical chasing work – 100% completed
        • Wall plastering work – GF to 19th floor – 100% completed
        • Wire pulling work – 95% Completed
        • DB Dressing & Switch fixing :GF-4 TH FLOOR (80% Completed),5-6(40% completed),7 th( 60%completed),8 th (40% completed),9 th (60% completed),10-12 th floor (70% completed),13 th -17 th floor (40% completed)
        • Aluminium Doors And Window Fixing -GF-90%,FF-95%,SF-9 TH Floor-100%,7 TH -19 TH floor -98% completed.
        • Tiling work -GF-95% completed,FF-19 th floor -100% completed
        • Dadoing of Toilets& kitchen walls: 100% completed
        • Fire Work -80%completed
        • water proofing work -100% completed
        • External plastering work ,Internal wall plastering – 100% completed
        • Door shutter Fixing -100% completed
        • Plumbing work -(GF,FF )80% completed,2-18th floor (100% completed)
        • CP sanitary fittings -GF,FF-90% completed,SF-60%,3-4 th floor -40%,5th -9th-(20%),10th floor -60%,10-13 th (20% ),14th-40%,15,16 th(20%)
        • Lift Work -90%completed
        • Painting : external painting completed.first coat painting (internal ) GF-12 th floor -100% completed,13-16 th floor -80% completed,17 th -19 th floor (60% completed),second coat painting (9-13 th ,16 th floor ,7th ,second floor )-20% completed
        • Reticulated Gas work-100% completed.
        • HT Electrical work-80% completed
        • Common lobby work-90% to be completed
        • Grills &Handrails :(GF+FF)-100% Completed,2-18 th floor -98% completed
        • Fire fighting -80% Completed
        • Yard Work:97% completed

As per the current work status from our site we are targeted to complete the following works by end of April 2019

        • Wire pulling work – 100% to be completed
        • Dadoing of Toilets: 100% to be completed,kitchen walls (100 % to be completed)
        • Fire Work -100% to be completed
        • Plumbing work -100 % to be completed.
        • Lift Work -100% tobe completed
        • Painting : internal 100 % to be completed
        • HT Electrical work-100% to be completed.
        • Yard Work:100% to be completed
        • Grills &Handrails :2-19 th floor -100% to be completed
        • Common lobby work-100% to be completed

Work status as on 05.04.2019, we have completed the following

        • RCC for Structure – (Main building +Amenity Block – 100% completed
        • Ceiling plastering work – 100% completed
        • Block/Brick masonry – (Main Building +Amenity Block) – 100% completed
        • Door Frame Fixing -(GF+FF)95% completed,2-19 th floor (100% completed)
        • Electrical chasing work – 100% completed
        • Wall plastering work – GF to 19th floor – 100% completed
        • Wire pulling work – 95% Completed
        • DB Dressing & Switch fixing :GF-4 TH FLOOR (80% Completed),4-5(40% completed),7 th( 60%completed),8 th (40% completed),9 th (60% completed),10-12 th floor (70% completed),13 th -17 th floor (40% completed)
        • Aluminium Doors And Window Fixing -98%completed.
        • Tiling work -100% completed
        • Dadoing of Toilets: 95% completed,kitchen walls (95 % completed)
        • Fire Work -80%completed
        • water proofing work -100% completed
        • External plastering work – 100% completed
        • Door Fixing -100% completed
        • Plumbing work -(GF+FF)80% completed,2-18 th floor (100% completed),19 th floor -90% completed
        • Lift Work -90%completed
        • Painting : external painting completed.first coat painting (internal ) GF-12 th floor -100% completed,,13-16 th floor -80% completed,17 th -19 th floor (60% completed),second coat painting (9-11 th ,16 th floor )-20% completed
        • Reticulated Gas work-100% completed.
        • HT Electrical work-95% completed
        • Yard Work:97% completed
        • Grills &Handrails :(GF+FF)-100% Completed,2-19 th floor -90% completed
        • Common lobby work-90% to be completed

As per the current work status from our site we are targeted to complete the following works by end of March 2019

        • Wire pulling work – 100% to be completed
        • Fire Work -100% to be completed
        • Plumbing work -100 % to be completed.
        • Lift Work -100% tobe completed
        • Painting : internal 100 % to be completed
        • HT Electrical work-100% to be completed.
        • Yard Work:100% to be completed

Work status as on 06.03.2019, we have completed the following

        • RCC for Structure – Amenity Block – 100% completed
        • Ceiling plastering work – 100% completed
        • Block/Brick masonry – Amenity Block – 100% completed
        • Electrical chasing work – 100% completed
        • Wall plastering work – GF to 19th floor – 100% completed
        • Wire pulling work – 95% Completed
        • Aluminium Doors And Window Fixing -100% completed.
        • Tiling work -100% completed
        • Fire Work -98%completed
        • External plastering work – 100% completed
        • Door Fixing -100% completed
        • Plumbing work -97% completed.
        • Lift Work -90%completed
        • Painting : internal (90%)completed, external painting completed.
        • Reticulated Gas work-100% completed.
        • HT Electrical work-95% completed
        • Yard Work:97% completed

As per the current work status from our site we are targeted to complete the following works by end of February 2019

        • Wire pulling work – 100% to be completed
        • Fire Work -100% to be completed
        • Plumbing work -100 % to be completed.
        • Lift Work -100% tobe completed
        • Painting : internal 100 % to be completed
        • HT Electrical work-100% to be completed.
        • Yard Work:100% to be completed

Work status as on 05-02-2019, we have completed the following

        • RCC for Structure – Amenity Block – 100% completed
        • Ceiling plastering work – 100% completed
        • Block/Brick masonry – Amenity Block – 100% completed
        • Electrical chasing work – 100% completed
        • Wall plastering work – GF to 19th floor – 100% completed
        • Wire pulling work – 90% Completed
        • Aluminium Doors And Window Fixing -100%completed.
        • Tiling work -100% completed
        • Fire Work -95%completed
        • External plastering work – 100% completed
        • Door Fixing -100% completed
        • Plumbing work -97% completed.
        • Lift Work -90%completed
        • Painting : internal (90%)completed,external painting completed.
        • Reticulated Gas work-100% completed.
        • HT Electrical work-90% completed
        • Yard Work:95% completed

 

    As per the current work status from our site we are targeted to complete the following works by end of January 2019

          • Wire pulling work – 100% to be completed
          • Plumbing work -100 % to be completed.
          • Lift Work -100% tobe completed
          • Painting : internal 100 % to be completed
          • Reticulated Gas work-100% to be completed.
          • HT Electrical work-100% to be completed.
          • Yard Work:100% to be completed

    Work status as on 08-01-2019, we have completed the following

          • RCC for Structure – Amenity Block – 90% completed
          • Ceiling plastering work – 100% completed
          • Block/Brick masonry – Amenity Block – 90% completed
          • Electrical chasing work – completed
          • Wall plastering work – GF to 19th floor – 100% completed
          • Wire pulling work – 90% Completed
          • Aluminium Doors And Window Fixing -100%completed.
          • Tiling work -100% completed
          • External plastering work – 100% completed
          • Door Fixing -100% completed
          • Plumbing work -95% completed.
          • Lift Work -75%completed
          • Painting : internal (85%)completed,external painting completed.
          • Reticulated Gas work-95% completed.
          • HT Electrical work-75% completed
          • Yard Work:95% completed

    As per the current work status from our site we are targeted to complete the following works by end of December 2019

          • Wire pulling work – 16 th,17th ,18,19 th floor – 100% to be completed
          • Door Fixing -100% to be completed
          • Plumbing work -100 % to be completed.
          • Reticulated Gas work-100% to be completed.
          • HT Electrical work-100% to be completed.

    Work status as on 06-12-2018, we have completed the following

          • RCC for Structure – Amenity Block – 90% completed
          • Ceiling plastering work – 100% completed
          • Block/Brick masonry – Amenity Block – 100% completed
          • Electrical chasing work – completed
          • Wall plastering work – GF to 19th floor – 100% completed
          • Wire pulling work – SF to 13th (100% completed); 14th floor (70% completed); 15th floor (completed); 16th floor (70% completed); 17th floor (80% completed); 18th floor ,19 TH floor on progressing
          • Tiling work -100% completed
          • External plastering work – 100% completed
          • Door Fixing -95% completed
          • Plumbing work -80% completed.
          • Reticulated Gas work-75% completed.
          • HT Electrical work-On progressing

    Work status as on 06-08-2018, we have completed the following

          • RCC for Structure – GF to 19th floor – 100% completed
          • Ceiling plastering work – GF(95% completed); 1st floor (90% completed); 2nd to 19th floor (100% completed)
          • Block/Brick masonry – GF & 1st floor (95% completed);2nd to 18th floor (100% completed); 19th floor (90% completed)
          • Electrical chasing work – 1st floor (90% completed); 2nd to 18th floor(100% completed); 19th floor (60% completed)
          • Wall plastering work – GF,1st floor (90% completed);2nd to 13th floor (100% completed); 14th floor(90% completed); 15th floor (100% completed); 16th floor(90% completed); 17th floor (100% completed); 18th floor(90% completed); 19th floor (40% completed)
          • External plastering work – 80% completed

     

        • As per the current work status from our site we are targeted to complete the following works by end of June 2018

          • Ceiling plastering work – 100% to be completed
          • Block/Brick masonry – 19th floor – 100% to be completed
          • Electrical chasing work – 19th floor – 100% to be completed
          • Wall plastering work – 18th & 19th floor – 100% to be completed
          • External plastering work – 100% to be completed
          • Earth work – 100% to be completed
          • Pile chipping work – 315nos to be completed (out of 323)
          • Pile cap work – 66 nos to be completed (out of 72)
          • Grade slab work – 100% to be completed

    As per the current work status from our site we are targeted to complete the following works by end of February 2018

          • RCC for Structure – GF – 100% to be completed
          • Block/Brick masonry – 100% to be completed
          • Electrical chasing work – 100% to be completed
          • Wall plastering work – 100% to be completed
          • External plastering work – 100% to be completed
          • Aluminium Windows and Ventilators – 100% to be completed
          • Tiling work – 100% to be completed
          • Grill making & fixing -100% to be completed
          • Electrical LT work -100% to be completed
          • Door frame fixing work- 100% to be completed
          • Water Proofing work – 100% to be completed
          • Plumbing work – 100% to be completed

    Work status as on 10-02-2018, we have completed the following.

          • Block/Brick masonry -GF ,1st floor (95% completed);2nd to 18th floor (100% completed);19th floor (90% completed)
          • Electrical chasing work – 2nd to 17th floor (100% completed)
          • Wall plastering work – GF,1st floor (90% completed);2nd to 13th, 15th & 17th floor (100% completed);14th floor(50% completed);16th floor(60% completed)
          • External plastering work – 2nd floor (25% completed);3rd to 19th floor (60 % completed)
          • Aluminium Windows and Ventilators – 3rd, 4th & 5th floor(70% completed);6th floor (60% completed)
          • Tiling work- 2nd floor(80% completed);3rd to 8th,10th& 11th floor(95% completed);9th & 12th floor(50% completed).
          • Grill making & fixing -2nd & 4th to 19th floor(60% completed);3rd floor (70% completed)
          • Electrical LT work -2nd to 11th floor(100% completed);12th & 13th floor(80% completed)
          • Door frame fixing work- 3rd to 5th floor (100% completed);6th floor(60% completed)
          • Water Proofing work – 2nd to 13th floor (100% completed)
          • Plumbing work – 2nd to 13th floor(100% completed)

     

        • Work status as on 5-7-2017, we have completed

          • RCC for Structure – completed
          • Ceiling plastering work – 19th floor – completed
          • Block/Brick masonry – progressing
          • Wall plastering work – progressing
          • External plastering work – progressing

     

        • Work status as on 10-6-2017, we have completed

          • RCC for Structure – GF – completed
          • Ceiling plastering work – progressing
          • Wall plastering work – progressing
          • External plastering work – progressing

     

        • Work status as on 8-3-2017, we have completed

          • RCC for Structure – GF – progressing
          • Ceiling plastering work – 100% completed
          • External plastering work – progressing

     

        • Construction status as on March 2016:

          • RCC Works:
            13 floor slab completed and 14 colomn RCC works are going on.
            14 th floor slab shuttering and steel works going on.
          • Parking block : Piling machinery are mobilized and work will be starting on Monday
          • Masonry Work : Block works going on at 5 th floor. Plastering works in 2 floor going on, 3 rd floor completed

     

        • Construction status as on June 2015:

          • Earth work excavation – 100% completed
          • PCC work – 100% completed
          • Pile chipping work – 100% completed
          • Pile cap RCC work – 100% completed
          • Tie Beam RCC work – 100% completed
          • Plinth beam RCC work – 100% completed
          • Column RCC work – GF to First floor – 100% completed
          • 1st floor slab RCC – 100% completed
          • Column RCC work – 1st floor to 2nd floor – 60% completed
          • Slab shuttering work – 2nd floor – 40% completed

     

        • The work progress as on 03-01-2015 of our project- Artech “RIO” at Thazhathangadi, Kottayam.

          • Pile cap work – 23nos completed (out of 56)
          • Tie beam work – progressing
          • Plinth beam work – progressing

    We are expected to complete the following works by the end of January 2015.

          • Pile cap work – 90% completion
          • Tie beam work – 100% completion
          • Plinth beam work – 60% completion
          • 1st floor column work – 50% completion
          • 1st floor Slab shuttering work – 50% completion