Artech -The Address - Progress

As per the current work status from our site we are targeted to complete the following works by end of February-2018

  • Inside Putty work -100% to be completed
  • 1st coat painting work – 100% to be complete
  • 2nd coat painting work – 100% to be complete
  • Aluminium Windows and Ventilators – 100% to be completed
  • CP Sanitary fixing work -100% to be completed
  • Tiling – 100 % to be completed
  • Door frame fixing work – 100% completed
  • Yard work- 100% to be completed

Work status as on 10-​02-2018, we have completed the following.

  • 2nd coat painting work – 1st & 3rd floor (A-flat-100% completed) & 5th,11th & 13th floor (B-flat-100% completed); 7th floor(A & D flat-100% completed) & 8th floor(C & B flat- 100% completed)
  • Aluminium Windows and Ventilators – 60% completed
  • CP Sanitary fixing work- 1st & 3rd (A flat 100% completed);4th floor(A flat & Bflat-100% complete);7th (A,D flat-100% completed);8th floor( C & Bflat-100% completed);13th floor (B flat- 100% completed); 21st floor (Common area- 100% completed)
  • Electrical HT work – 100 % completed
  • Electrical LT work -Wire pulling-100% completed
  • Tiling – 1st floor & 3rd to 20th floor(100% completed);2nd floor(80% completed)
  • Water proofing work -100% completed
  • Door frame fixing work – 3rd to 9th, 11th to 16th & 18th to 20th floor(100% completed);1st floor( 50% completed);2nd ,10th & 17th floor(75% completed)
  • Yard work- 85% completed

Work status as on 10-7-2017, we have completed

  • RCC for Structure – completed
  • Ceiling Plastering – completed
  • Block/Brick Masonry – progressing
  • InsideWall Plastering work – progressing

Work status as on 7-5-2017, we have completed

  • RCC for Structure – completed
  • Ceiling Plastering – completed
  • Block/Brick Masonry – progressing
  • External Wall Plastering work – progressing

Work status as on 7-3-2017, we have completed

  • Ceiling Plastering – 100% completed
  • Block/Brick Masonry – progressing
  • External Wall Plastering work – progressing
  • InsideWall Plastering work – progressing

Construction status as on June 2015

  • Slab shuttering work – 14th roof – progressing
  • Block work – 12th floor – completed
  • Ceiling plastering work – 13th roof – progressing
  • Water proofing work – 7th floor – progressing
  • Electrical wall chasing work- 11th floor- progressing
  • Plumbing work – 6th & 7th floor – progressing

Following works are expected to be completed by June 2015:

  • Slab RCC – 14th floor roof – 100% completion
  • Block work – 13th floor – 100% completion
  • Ceiling plastering work – 13th roof  – 100% completion
  • Water proofing work – 7th & 8th floor – 100% completion
  • Electrical wall chasing work – 12th floor – 100% completion
  • Plumbing work – 7th & 8th floor     – 100% completion
  • Slab concrete work – 2nd floor roof slab completed
  • Column work – 3rd floor – 50% completed
  • Ceiling plastering work- 1st floor – 60% completed
  • Block work – 1st floor progressing