Artech Varsha - Progress

Work status as on 5-7-2017, we have completed

A – BLOCK

  • RCC for Structure – completed
  • Ceiling Plastering work – completed
  • Block/Brick masonry work – completed
  • Wall plastering inside – completed
  • Wire pulling -progressing-
  • External plastering work – progressing

B – BLOCK

  • RCC for Structure – completed
  • Ceiling Plastering work – completed
  • Block/Brick masonry work – completed
  • Wall plastering inside – completed
  • Wire pulling – completed
  • Plumbing work – completed
  • External plastering work – completed
  • Flooring – completed

C – BLOCK

  • RCC for Structure – completed
  • Ceiling Plastering work – completed
  • Block/Brick masonry work – completed
  • Electrical rope pulling work – completed
  • Wall plastering – completed

Work status as on 9-6-2017, we have completed

A – BLOCK

  • RCC for Structure – completed
  • Ceiling Plastering work – completed
  • Block/Brick masonry work – completed
  • Wall plastering inside – completed
  • Plumbing work – progressing

B – BLOCK

  • RCC for Structure – completed
  • Ceiling Plastering work – completed
  • Block/Brick masonry work – completed
  • Wall plastering inside – completed
  • External plastering work – completed
  • Flooring – completed

C – BLOCK

  • RCC for Structure – completed
  • Ceiling Plastering work – completed
  • Block/Brick masonry work – completed
  • Electrical rope pulling work – completed
  • Wall plastering – completed

Work status as on 9-5-2017, we have completed

A – BLOCK

  • RCC for Structure – completed
  • Ceiling Plastering work – completed
  • Block/Brick masonry work – completed
  • Wall plastering inside – completed
  • Flooring and skirting – progressing
  • External plastering work – progressing

B – BLOCK

  • RCC for Structure – completed
  • Ceiling Plastering work – completed
  • Block/Brick masonry work – completed
  • Wall plastering inside – completed
  • Plumbing work – progressing
  • External plastering work – completed

C – BLOCK

  • RCC for Structure – completed
  • Ceiling Plastering work – completed
  • Block/Brick masonry work – completed
  • 1st coat painting work – progressing
  • External painting work – progressing
  • Wall plastering – completed

Work status as on 8-3-2017, we have completed

A – BLOCK

  • RCC for Structure – 100% completed
  • Ceiling Plastering work – 100% completed
  • Block/Brick masonry work – 100% completed
  • Wall plastering inside – 100% completed

B – BLOCK

  • RCC for Structure – 100% completed
  • Ceiling Plastering work – 100% completed
  • Block/Brick masonry work – 100% completed
  • Wall plastering inside – 100% completed
  • External plastering work – 100% completed
  • Flooring – 1st floor to terrace floor – 100% completed

C – BLOCK

  • RCC for Structure – 100% completed
  • Ceiling Plastering work – 100% completed
  • Block/Brick masonry work – 100% completed
  • Electrical rope pulling work – 100% completed
  • Wall plastering – 100% completed

Work status as on 8-2-2017, we have completed

A – BLOCK

  • RCC for Structure – completed
  • Ceiling Plastering work – completed
  • Block/Brick masonry work – completed
  • Wall plastering inside – completed
  • External plastering work – progressing

B – BLOCK

  • RCC for Structure – completed
  • Ceiling Plastering work – completed
  • Block/Brick masonry work – completed
  • Wall plastering inside – completed
  • Plumbing work – progressing
  • External plastering work – completed
  • Flooring – 1st floor to terrace floor – 100% completed

C – BLOCK

  • RCC for Structure – 100% completed
  • Ceiling Plastering work – 100% completed
  • Block/Brick masonry work – 100% completed
  • Putty work outside – progressing
  • Wall plastering – completed

Work status as on 06-5-2016, we have completed

A-Block

  • RCC for Structure – completed
  • External plastering work – 12th & 13th floor completed

B-Block

  • RCC for Structure – completed
  • External plastering work – completed

Current work progress at our site Artech “Varsha” Nalanchira, Trivandrum as on 23rd July 2015

B-Block

  • Ceiling plastering work – completed
  • Block work – completed
  • Inside Wall plastering – completed
  • Outside plastering work- 50% completed
  • Putty work, water proofing work, Hand rail work (Balcony and Stair) -progressing

A-Block

  • Slab RCC work –Roof slab work of 5th floor completed and roof slab work of 6th floor progressing
  • Ceiling plastering work- 4th floor progressing
  • Block work – 2nd floor progressing