Artech Varsha - Progress
Work status as on 5-7-2017, we have completed
A – BLOCK
- RCC for Structure – completed
- Ceiling Plastering work – completed
- Block/Brick masonry work – completed
- Wall plastering inside – completed
- Wire pulling -progressing-
- External plastering work – progressing
B – BLOCK
- RCC for Structure – completed
- Ceiling Plastering work – completed
- Block/Brick masonry work – completed
- Wall plastering inside – completed
- Wire pulling – completed
- Plumbing work – completed
- External plastering work – completed
- Flooring – completed
C – BLOCK
- RCC for Structure – completed
- Ceiling Plastering work – completed
- Block/Brick masonry work – completed
- Electrical rope pulling work – completed
- Wall plastering – completed
Work status as on 9-6-2017, we have completed
A – BLOCK
- RCC for Structure – completed
- Ceiling Plastering work – completed
- Block/Brick masonry work – completed
- Wall plastering inside – completed
- Plumbing work – progressing
B – BLOCK
- RCC for Structure – completed
- Ceiling Plastering work – completed
- Block/Brick masonry work – completed
- Wall plastering inside – completed
- External plastering work – completed
- Flooring – completed
C – BLOCK
- RCC for Structure – completed
- Ceiling Plastering work – completed
- Block/Brick masonry work – completed
- Electrical rope pulling work – completed
- Wall plastering – completed
Work status as on 9-5-2017, we have completed
A – BLOCK
- RCC for Structure – completed
- Ceiling Plastering work – completed
- Block/Brick masonry work – completed
- Wall plastering inside – completed
- Flooring and skirting – progressing
- External plastering work – progressing
B – BLOCK
- RCC for Structure – completed
- Ceiling Plastering work – completed
- Block/Brick masonry work – completed
- Wall plastering inside – completed
- Plumbing work – progressing
- External plastering work – completed
C – BLOCK
- RCC for Structure – completed
- Ceiling Plastering work – completed
- Block/Brick masonry work – completed
- 1st coat painting work – progressing
- External painting work – progressing
- Wall plastering – completed
Work status as on 8-3-2017, we have completed
A – BLOCK
- RCC for Structure – 100% completed
- Ceiling Plastering work – 100% completed
- Block/Brick masonry work – 100% completed
- Wall plastering inside – 100% completed
B – BLOCK
- RCC for Structure – 100% completed
- Ceiling Plastering work – 100% completed
- Block/Brick masonry work – 100% completed
- Wall plastering inside – 100% completed
- External plastering work – 100% completed
- Flooring – 1st floor to terrace floor – 100% completed
C – BLOCK
- RCC for Structure – 100% completed
- Ceiling Plastering work – 100% completed
- Block/Brick masonry work – 100% completed
- Electrical rope pulling work – 100% completed
- Wall plastering – 100% completed
Work status as on 8-2-2017, we have completed
A – BLOCK
- RCC for Structure – completed
- Ceiling Plastering work – completed
- Block/Brick masonry work – completed
- Wall plastering inside – completed
- External plastering work – progressing
B – BLOCK
- RCC for Structure – completed
- Ceiling Plastering work – completed
- Block/Brick masonry work – completed
- Wall plastering inside – completed
- Plumbing work – progressing
- External plastering work – completed
- Flooring – 1st floor to terrace floor – 100% completed
C – BLOCK
- RCC for Structure – 100% completed
- Ceiling Plastering work – 100% completed
- Block/Brick masonry work – 100% completed
- Putty work outside – progressing
- Wall plastering – completed
Work status as on 06-5-2016, we have completed
A-Block
- RCC for Structure – completed
- External plastering work – 12th & 13th floor completed
B-Block
- RCC for Structure – completed
- External plastering work – completed
Current work progress at our site Artech “Varsha” Nalanchira, Trivandrum as on 23rd July 2015
B-Block
- Ceiling plastering work – completed
- Block work – completed
- Inside Wall plastering – completed
- Outside plastering work- 50% completed
- Putty work, water proofing work, Hand rail work (Balcony and Stair) -progressing
A-Block
- Slab RCC work –Roof slab work of 5th floor completed and roof slab work of 6th floor progressing
- Ceiling plastering work- 4th floor progressing
- Block work – 2nd floor progressing