Artech Rainforest - Progress
Work status as on 08-03-2023, we have completed the following.
- Structural Works – Swimming pool wall – 100% completed, basement 2 level parapet – 90% completed, Ground floor – 90% completed
- Civil Works – Ceiling and wall plastering 85% completed, Masonry – Block/ brick- Basement 1 floor 100% completed, basement 2 floor – 75% completed, Ground floor – 50% completed
- Internal Finishes – Main door – 42 apartments completed, Waterproofing – 15th floor – 75% completed, terrace – 25% completed, wall tiling – 43 apartments completed, flooring – 30 apartments completed, putty works – 100% completed, Door frame fixtures- 100% completed, Handrails – fire stair handrail – 50% Completed
- Electrical, Plumbing & Firefighting works – Concealed plumbing works – 72 nos: completed, Corridor handrail works – 90% completed, Centralised gas piping system – mockup only, fire fighting work – 2nd to 10th floor – 100% completed, Electrical LT work – wire pulling – 25 apartments completed, HT work – cable tray work started
- External Finishes – Windows and sliding doors – mockup only, External plastering – 95% completed, External painting – primer 85% completed
- Mockup – Blockwork, Internal plaster – 100% completed, Firefighting – 100% completed, Concealed plumbing – 100% completed, Waterproofing – 100% completed, Electrical wall services – 100% completed, Reticulated gas piping – 100% completed, Painting – Primer 100% completed, HVAC -100% completed, Flooring – 100% completed, balcony handrail – 100% completed, duct door – 100% completed.
As per the current work status from our site, we are targeted to complete the following works by the end of MARCH 2023.
- Structural Works – basement 2 level parapet – 100% to be completed, Ground floor – 100% to be completed
- Civil Works – Masonry – Block/Brick – basement 2 floor – 100% to be completed, Ground floor – 100% to be completed
- Internal Finishes – Maindoor – 56 more numbers to be fixed, Waterproofing – 15th floor 100% to be completed, terrace 50% to be completed, Flooring – 5 more apartments to be completed, Handrail – fire stair handrail – 100% to be completed.
- Electrical, Plumbing & Firefighting works – Concealed plumbing works – 6nos: more to be completed, Electrical LT work – wire pulling 7 more apartments to be completed, fire fighting work – 1st floor – 100% to be completed
- External Finishes – External plastering – 100% to be completed, Painting – primer 95% to be completed
Work status as on 11-02-2023, we have completed the following.
- Structural Works – Swimming pool wall – 100% completed, basement 2 level parapet – 80% completed, Ground floor – 80% completed, OHT wall – 100% completed
- Civil Works – Ceiling and wall plastering 85% completed, Masonry – Block/ brick- Basement 1 floor 100% completed, basement 2 floor – 50% completed, Ground floor – 50% completed
- Internal Finishes – Main door – 42 apartments completed, Waterproofing – 13th, 14th floor 50% completed, basement 2 50% completed, wall tiling – 42 apartments completed, flooring – 20 apartments completed, putty works – 100% completed, Door frame fixtures- 100% completed.
- Electrical, Plumbing & Firefighting works – Concealed plumbing works – 71 nos: completed, Centralised gas piping system – mockup only, fire fighting work – 2nd to 10th floor – 100% completed, Electrical LT work – wire pulling – 25 apartments completed, HT work – cable tray work started
- External Finishes – Windows and sliding doors – mockup only, External plastering – 90% completed, External painting – primer 80% completed
- Mockup – Blockwork, Internal plaster – 100% completed, Firefighting – 100% completed, Concealed plumbing – 100% completed, Waterproofing – 100% completed, Electrical wall services – 100% completed, Reticulated gas piping – 100% completed, Painting – Primer 100% completed, HVAC -100% completed, Flooring – 100% completed, balcony handrail – 100% completed, duct door – 100% completed.
As per the current work status from our site, we are targeted to complete the following works by the end of FEBRUARY 2023.
- Structural Works – basement 2 level parapet – 100% to be completed, Ground floor – 90% to be completed
- Civil Works – Masonry – Block/Brick – basement 2 floor – 100% to be completed, Ground floor – 100% to be completed
- Internal Finishes – Waterproofing – 13th floor 100% to be completed, 1st floor – 100% to be completed, basement 2 floor – 100% to be completed, Wall tiling – 1 more apartment to be completed, Flooring – 3 more apartments to be completed, Handrail -staircase handrail – 50% to be completed.
- Electrical, Plumbing & Firefighting works – Concealed plumbing works – 6nos: more to be completed, Electrical LT work – wire pulling 7 more apartments to be completed, fire fighting work – 1st floor – 100% to be completed.
- External Finishes – External plastering – 95% to be completed, Painting – primer 85% to be completed
Work status as on 14-01-2023, we have completed the following.
- Structural Works – Swimming pool wall – 100% completed, basement 2 level parapet – 80% completed, Ground floor – 75% completed, OHT Slab – 100% completed
- Civil Works – Ceiling and wall plastering 85% completed, Masonry – Block/ brick- Basement 1 floor 90% completed, basement 2 floor – 50% completed, Ground floor – 50% completed
- Internal Finishes – Main door – 42 apartments completed, Waterproofing – 13th floor 50% completed, basement 2 50% completed, 1st – 50% completed, 2nd, 3rd floor – 100% completed, wall tiling – 42 apartments completed, flooring – 13 apartments completed, putty works – 95% completed, Door frame fixtures- 100% completed.
- Electrical, Plumbing & Firefighting works – Concealed plumbing works – 49 nos: completed, Corridor handrail works -90% completed, Centralised gas piping system – mockup only, fire fighting work – 2nd to 10th floor – 100% completed, Electrical LT work – wire pulling – 15 apartments completed, HT work – cable tray work started
- External Finishes – Windows and sliding doors – mockup only, External plastering – 90% completed, External painting – primer 80% completed
- Mockup – Blockwork, Internal plaster – 100% completed, Firefighting – 100% completed, Concealed plumbing – 100% completed, Waterproofing – 100% completed, Electrical wall services – 100% completed, Reticulated gas piping – 100% completed, Painting – Primer 100% completed, HVAC -100% completed, Flooring – 100% completed, balcony handrail – 100% completed, duct door – 100% completed.
As per the current work status from our site, we are targeted to complete the following works by the end of JANUARY 2023.
- Structural Works – basement 2 level parapet – 100% to be completed, Ground floor – 100% to be completed, OHT wall – 100% to be completed
- Civil Works – Masonry – Block/Brick – Basement 1 floor 100% to be completed, basement 2 floor – 75% to be completed, Ground floor – 100% to be completed
- Internal Finishes – Waterproofing – 13th floor 100% to be completed, 1st floor – 100% to be completed, basement 2 floor – 100% to be completed, Wall tiling – 1 more apartment to be completed, putty works – 100% to be completed, Flooring – 3 more apartments to be completed, Handrail -staircase handrail – 50% to be completed.
- Electrical, Plumbing & Firefighting works – Concealed plumbing works – 6nos: more to be completed, Electrical LT work – wire pulling 12 more apartments to be completed, fire fighting work – 1st floor – 100% to be completed
- External Finishes – External plastering – 95% to be completed, Painting – primer 85% to be completed
Work status as on 13-12-2022, we have completed the following
As per the current work status from our site, we are targeted to complete the following works by the end of DECEMBER 2022.
- Structural Works – basement 2 level parapet – 100% to be completed, Ground floor – 100% to be completed
- Civil Works – wall plastering – 15th floor 100% to be completed, Masonry – Block/Brick – Basement 1 floor 100% to be completed, basement 2 floor – 75% to be completed, Ground floor – 50% to be completed
- Internal Finishes – Main door – 20 apartments more to be fixed, Waterproofing – 12th floor 100% to be completed, 13th floor 50% to be completed, Wall tiling – 1st floor 100% to be completed, putty works – 15th floor 100% to be completed.
- Electrical, Plumbing & Firefighting works – Concealed plumbing works – 6nos: more to be completed, Corridor handrail works – 13th, 14th, 15th floor 100% to be completed, Electrical LT work – wire pulling 12 more apartments to be completed
- External Finishes – External plastering – 90% to be completed, Painting – primer 85% to be completed
Work status as on 13-12-2022, we have completed the following.
- Structural Works – LMR – 100% completed, Swimming pool slab – 100% completed, basement 2 level parapet – 75% completed, Ground floor – 75% completed
- Civil Works – Ceiling plastering – 15th floor 100% completed, wall plastering – 15th floor 90% completed, Masonry – Block/ brick- 15th floor 100% completed, Basement 1 floor 50% completed, basement 2 floor – 50% completed, Ground floor – 25% completed
- Internal Finishes – Main door – 20 apartments completed, Waterproofing – 13th floor 50% completed, basement 2 50% completed, 1st, 2nd, 3rd floor – 50% completed, wall tiling – 42 apartments completed, flooring – 6 apartments completed, putty works – 95% completed, Door frame fixtures- 100% completed.
- Electrical, Plumbing & Firefighting works – Concealed plumbing works – 43 nos: completed, Corridor handrail works -12th floor 100% completed, Centralised gas piping system – mockup only, fire fighting work – 10th floor – 100% completed, Electrical LT work – wire pulling – 6 apartments completed, HT work – cable tray work started
- External Finishes – Windows and sliding doors – mockup only, External plastering – 80% completed, External painting – primer 80% completed
- Mockup – Blockwork, Internal plaster – 100% completed, Firefighting – 100% completed, Concealed plumbing – 100% completed, Waterproofing – 100% completed, Electrical wall services – 100% completed, Reticulated gas piping – 100% completed, Painting – Primer, putty, primer, 1 coat emulsion application completed, HVAC -100% completed, Flooring – 100% completed, balcony handrail – 100% completed, duct door – 100% completed.
As per the current work status from our site, we are targeted to complete the following works by the end of NOVEMBER 2022.
-
- Structural Works – swimming pool – 75% to be completed, basement 2 level parapet – 100% to be completed
- Civil Works – wall plastering – 15th floor 100% to be completed, Masonry – Block/Brick – Basement 1 floor 100% to be completed
- Internal Finishes – Main door – 15 apartments more to be fixed, Waterproofing – 12th floor 100% to be completed, 13th floor 50% to be completed, Wall tiling – 1st floor 100% to be completed, putty works – 15th floor 100% to be completed.
Electrical, Plumbing & Firefighting works – Concealed plumbing works – 2nd, 1st floor 100% to be completed, Corridor handrail works – 13th, 14th, 15th floor 100% to be completed, Fire fighting work – 10th floor 100% to be completed, Electrical LT work – wire pulling 6 more apartments to be completed
- External Finishes – External plastering – 90% to be completed, Painting – primer 85% to be completed
Work status as on 15-11-2022, we have completed the following.
- Structural Works – Pile cap – 100% completed, slab completed – 16th Floor 100% completed, LMR – 100% completed, Swimming pool – 40% completed, basement 1 level parapet – 100% completed, basement 2 level parapet – 75% completed.
- Civil Works – Ceiling plastering – 15th floor 100% completed, wall plastering – 15th floor 90% completed, Masonry – Block/ brick- 15th floor 100% completed, Basement 1 floor 50% completed.
- Internal Finishes – Main door – 13 apartments completed, Waterproofing – 12th floor 50% completed, basement 1 floor 100% completed, basement 2 50% completed, wall tiling – 2nd, 3rd, 8th floor 100% completed, flooring – mock up only, putty works – 14th floor – 100% completed, Door frame fixtures-15th floor 100% completed.
- Electrical, Plumbing & Firefighting works – Concealed plumbing works – 8th floor 100% completed, Corridor handrail works -12th floor 100% completed, Centralised gas piping system – mockup only, fire fighting work – 9th floor – 100% completed, Electrical LT work – upto 15th floor 100% completed, wire pulling – 3 apartments completed, HT work – cable tray work started
- External Finishes – Windows and sliding doors – mockup only, External plastering – 80% completed, External painting – primer 80% completed
- Mockup – Blockwork, Internal plaster – 100% completed, Firefighting – 100% completed, Concealed plumbing – 100% completed, Waterproofing – 100% completed, Electrical wall services – 100% completed, Reticulated gas piping – 100% completed, Painting – Primer, putty, primer, 1 coat emulsion application completed, HVAC -100% completed, Flooring – 100% completed, balcony handrail – 100% completed, duct door – 100% completed.
Work status as on 11-10-2022, we have completed the following.
- Structural Works – Pile cap – 100% completed, slab completed – 16th Floor 100% completed, LMR – 75% completed, Swimming pool – 40% completed, basement 1 level parapet – 100% completed, basement 2 level parapet – 50% completed.
- Civil Works – Ceiling plastering – 15th floor 90% completed, wall plastering – 14th floor 100% completed, Masonry – Block/ brick- 15th floor 100% completed
- Internal Finishes – Main door – 5 apartments completed, Waterproofing – 10th floor 90% completed, 11th floor 90% completed, wall tiling – 8th floor 80% completed, 3rd floor – 75% completed, flooring – mock up only, putty works – 14th floor – 100% completed, Door frame fixtures-15th floor 100% completed.
- Electrical, Plumbing & Firefighting works – Concealed plumbing works – 8th floor 100% completed, Corridor handrail works -12th floor 100% completed, Centralised gas piping system – mockup only, fire fighting work – 8th floor – 100% completed, Electrical LT work – upto 14th floor 100% completed, HT work – cable tray work started
- External Finishes – Windows and sliding doors – mockup only, External plastering – 80% completed, External painting – primer 80% completed
- Mockup – Blockwork, Internal plaster – 100% completed, Firefighting – 100% completed, Concealed plumbing – 100% completed, Waterproofing – 100% completed, Electrical wall services – 100% completed, Reticulated gas piping – 100% completed, Painting – Primer, putty, primer, 1 coat emulsion application completed, HVAC -100% completed, Flooring – 100% completed, balcony handrail – 100% completed, duct door – 100% completed.
As per the current work status from our site, we are targeted to complete the following works by the end of OCTOBER 2022.
- Structural Works – LMR – 100% to be completed, swimming pool – 75% to be completed, basement 2 level parapet – 100% to be completed
- Civil Works – Ceiling plastering – 15th Floor 100% to be completed, wall plastering – 15th floor 100% to be completed
- Internal Finishes – Main door – 15 apartments more to be fixed, Waterproofing – 12th floor 100% to be completed, Wall tiling – 1st & 2nd, 3rd, 8th floor – 100% to be completed, putty works – 15th floor 100% to be completed.
- Electrical, Plumbing & Firefighting works – Concealed plumbing works – 2nd, 1st floor 100% to be completed, Corridor handrail works – 13th, 14th, 15th floor 100% to be completed, Fire fighting work – 9th floor 100% to be completed, Electrical LT work – up to 15th floor to be completed
- External Finishes – External plastering – 90% to be completed, Painting – primer 85% to be completed
Work status as on 17-09-2022, we have completed the following.
- Structural Works – Pile cap – 100% completed, slab completed – 16th Floor 100% completed, LMR – 50% completed, Swimming pool – 40% completed
- Civil Works – Ceiling plastering – 15th floor 85% completed, wall plastering – 14th floor completed, Masonry – Block/ brick- 15th floor 100% completed
- Internal Finishes – Main door – MOCKUP only, Waterproofing – 10th floor 90% completed, 11th floor 75% completed, wall tiling – 5th floor 60% completed, 3rd floor – 30% completed, flooring – mock up only, putty works – 13th floor 70% completed, 14th floor – 100% completed, Door frame fixtures-14th floor 100% completed.
- Electrical, Plumbing & Firefighting works – Concealed plumbing works – 7th floor 100% completed, Corridor handrail works -12th floor 100% completed, Centralised gas piping system – mockup only, fire fighting work – 3rd to 7th floor – 100% completed, Electrical LT work – upto 14th floor 100% completed, HT work – cable tray work started
- External Finishes – External plastering – 75% completed, External painting – primer 50% completed
- Mockup – Blockwork, Internal plaster – 100% completed, Firefighting – 100% completed, Concealed plumbing – 100% completed, Waterproofing – 100% completed, Electrical wall services – 100% completed, Reticulated gas piping – 100% completed, Painting – Primer, putty, primer, 1 coat emulsion application completed, HVAC -100% completed, Flooring – 100% completed
As per the current work status from our site, we are targeted to complete the following works by the end of SEPTEMBER 2022.
- Structural Works – LMR – 100% to be completed, swimming pool – 75% to be completed, basement 1 level parapet – 100% to be completed
- Civil Works – Ceiling plastering – 15th Floor 100% to be completed, wall plastering – 15th floor 100% to be completed
- Internal Finishes – Main door – 10 apartments more to be fixed, Waterproofing – 10th,11th floor 100% to be completed, Wall tiling – 5th floor 100% to be completed, 3rd floor – 100% to be completed, putty works – 15th floor 100% to be completed, Door frame fixtures – 15th floor 100% to be completed
- Electrical, Plumbing & Firefighting works – Concealed plumbing works – 3rd floor 100% to be completed, Corridor handrail works – 13th, 14th, 15th floor 100% to be completed, Fire fighting work – 8th floor 100% to be completed, Electrical LT work – up to 15th floor to be completed
- External Finishes – External plastering – 85% to be completed, Painting – primer 75% to be completed.
Work status as on 09-07-2022, we have completed the following.
- Structural Works – All Sub-Structural and Structural work 98% Completed. GF north side drive way – 50% completed
- Civil Works – Ceiling plastering and wall plastering- Inside flat 100% completed, Masonry – Block/ brick- inside flat area completed , Screeding – 45% (till 10th floor – 100% completed).
- Internal Finishes – Main door – frame only -100% completed, Waterproofing up to 13th floor completed, (lift well -2, rainwater harvesting tank outside completed), Wall tiles – up to 11th floor completed, Floor Tiling up to 10th floor inside flat area completed, putty works & inside painting works – 72% completed (2nd coat putty completed, 1 coat primer completed), Handrails – 87% completed (main stair – till 14 th floor completed , fire stair – till 14 th floor completed, balcony handrail – till 19th floor completed).
- Electrical, Plumbing & Firefighting works – Concealed plumbing works- up to 13th floor, 18th floor completed, Fire fighting works – (2nd, 3rd, 5th, 6th floor – 70% completed) 20% completed
- External Finishes – Windows and sliding door – mockup only, External Plastering – Elevation 2 (100%) & 3 (97%)Completed, Elevation 1 – 90% completed, Elevation 4 completed, External painting – Elevation 1 Damp proof – 90% completed, first coat putty work – 70% completed, elevation 2 – damp proof – 80% completed, 1st coat putty 65% completed, elevation 3 – damp proof -50% completed, 1st coat putty – 50% completed, elevation 4 – dramp proof & 1st coat putty completed
- Mockup – Completed.
As per the current work status from our site, we are targeted to complete the following works by the end of JULY 2022.
- Structural Works – All Sub-Structural and Structural work 98% Completed. GF north side drive way – 50% completed
- Civil Works – Ceiling plastering and wall plastering- Inside flat 100% completed, Masonry – Block/ brick- inside flat area completed , Screeding – 45% (till 10th floor – 100% completed).
- Internal Finishes – Main door – frame only -100% completed, Waterproofing up to 13th floor completed, (lift well -2, rainwater harvesting tank outside completed), Wall tiles – up to 11th floor completed, Floor Tiling up to 10th floor inside flat area completed, putty works & inside painting works – 72% completed (2nd coat putty completed, 1 coat primer completed), Handrails – 87% completed (main stair – till 14 th floor completed , fire stair – till 14 th floor completed, balcony handrail – till 19th floor completed).
- Electrical, Plumbing & Firefighting works -Concealed plumbing works- up to 13th floor, 18th floor completed, Fire fighting works – (2nd, 3rd, 5th, 6th floor – 70% completed) 20% completed
- External Finishes – Windows and sliding door – mockup only, External Plastering – Elevation 2 (100%) & 3 (97%)Completed, Elevation 1 – 90% completed, Elevation 4 completed, External painting – Elevation 1 Damp proof – 90% completed, first coat putty work – 70% completed, elevation 2 – damp proof – 80% completed, 1st coat putty 65% completed, elevation 3 – damp proof -50% completed, 1st coat putty – 50% completed, elevation 4 – dramp proof & 1st coat putty completed
- Mockup – Completed.
Work status as on 09-06-2022, we have completed the following.
- Structural Works – Pile cap – 99% completed, slab completed – 16th Floor 100% completed
- Civil Works – Ceiling plastering- Basement 2 – 100% completed, 15th floor 70% completed, wall plastering- 13th floor 50% completed, Masonry – Block/ brick- 14th floor 100% completed
- Internal Finishes – Main door – MOCKUP only, Waterproofing- 9th floor 50% completed, 10th floor – 50% completed, wall tiling – mockup only, flooring – mock up only, putty works – 12th floor 20% completed, Door frame fixtures-14th floor 100% completed.
- Electrical, Plumbing & Firefighting works – Concealed plumbing works- 6th floor 75% completed, Corridor handrail works -12th floor 100% completed
- External Finishes – External plastering – 50% completed
- Mockup – Blockwork, Internal plaster – 100% completed, Firefighting – 100% completed, Concealed plumbing – 100% completed, Waterproofing – 100% completed, Electrical wall services – ongoing, Reticulated gas piping – 100% completed, Painting – Primer application completed, HVAC -50% completed, Toilet tile work-90% completed
As per the current work status from our site, we are targeted to complete the following works by the end of JUNE 2022.
- Structural Works – Pile cap – 100% to be completed
- Civil Works – Ceiling plastering-15th Floor 100% to be completed, wall plastering – 13th floor 100% to be completed, Masonry – Block/ brick- 15th floor 100% to be completed
- Internal Finishes – Waterproofing – 9th floor, 10th floor 100% to be completed, putty works- 12th floor 100% to be completed
- Electrical, Plumbing & Firefighting works -Concealed plumbing works – 7th floor 100% to be completed, Corridor handrail works – 13 floor 100% to be completed
- External Finishes – External plastering – 75% to be completed
Work status as on 12-04-2022, we have completed the following.
- Structural Works – Entire structure is completed
- Civil Works – Ceiling plastering- Basement 2 – 50% completed, 14th floor 100% completed, , wall plastering- 11th floor 70% completed, Masonry – Block/ brick- 14th floor 90% completed
- Internal Finishes – Main door – MOCKUP only, Waterproofing- 8th floor 50% completed, putty works – 8th floor 100% completed, Door frame fixtures-13th floor 100% completed.
- Electrical, Plumbing & Firefighting works – Concealed plumbing works- 4th floor, 5th floor 90% completed, Corridor handrail works -12th floor 100% completed.
- External Finishes – External plastering – 30% completed.
- Mockup – Blockwork, Internal plaster – 100% completed, Firefighting – 100% completed, Concealed plumbing – 100% completed, Waterproofing – 100% completed, Electrical wall services – ongoing, Reticulated gas piping – 100% completed, Painting – Primer application completed, HVAC -50% completed, Toilet tile work-90% completed.
As per the current work status from our site, we are targeted to complete the following works by the end of APRIL 2022.
- Civil Works – Ceiling plastering-15th Floor 100% to be completed, wall plastering-11th floor 100% to be completed, 12th floor – 30% to be completed, Masonry – Block/ brick- 14th floor 100% to be completed
- Internal Finishes – Waterproofing-8th floor 100% to be completed, putty works- 9th floor 50% to be completed, Door frame fixtures- 14th floor 100% to be completed.
- Electrical, Plumbing & Firefighting works – Concealed plumbing works- 4th, 5th floor – 100% to be completed, 6th floor – 50% to be completed, Corridor handrail works -13 floor 100% to be completed.
- External Finishes – External plastering – 50% to be completed.
Work status as on 10-03-2022, we have completed the following.
- Structural Works – Pile cap – 99% completed, slab completed – 16th Floor 80% completed
- Civil Works – Ceiling plastering-14th floor100% completed, wall plastering- 11th floor 30% completed, Masonry – Block/ brick- 14th floor 60% completed
- Internal Finishes – Main door – MOCKUP only, Waterproofing- 7th floor 100% completed, putty works – 6th floor 100% completed, Door frame fixtures-12th floor 100% completed.
- Electrical, Plumbing & Firefighting works – Concealed plumbing works- 13% completed, Corridor handrail works -11th floor 100% completed
- Mockup – Blockwork, Internal plaster – 100% completed, Firefighting – 100% completed, Concealed plumbing – 100% completed, Waterproofing – 100% completed, Electrical wall services – ongoing, Reticulated gas piping – 100% completed, Painting – Primer application completed, HVAC -50% completed, Toilet tile work-90% completed
As per the current work status from our site, we are targeted to complete the following works by the end of MARCH 2022.
- Structural Works – Pile cap – 100% to be completed, slab – 16th floor100% to be completed
- Civil Works – Ceiling plastering-15th Floor 100% to be completed, wall plastering-11th floor 100% to be completed, 12th floor – 30% to be completed, Masonry – Block/ brick- 14th floor 100% to be completed
- Internal Finishes – Waterproofing-8th floor 100% to be completed, putty works- 7th floor 100% to be completed, Door frame fixtures- 13th floor 100% to be completed, 14th floor 100% to be completed
- Electrical, Plumbing & Firefighting works – Concealed plumbing works- 20% to be completed, Corridor handrail works -12 floor 100% to be completed
Work status as on 09-04-2021, we have completed the following.
-
- Earthwork – 90% completed
- Pile chipping work – completed
- Pile cap work -92% completed
- RCC for slab
- BF2-11th floor slab -RCC work -100% completed
- Column work :
- BF2 – 10 th floor -100% completed ,11th floor -50% completed.
- RCC for Ramp
- BF2- 80% completed, BF1- 90% completed
- Ceiling Plastering
- 1st floor:- 70% completed
- Ceiling Plastering (2nd floor-9th floor ):90% completed
- Electrical wall chasing
- 2nd floor – 20% completed,3rd floor-70% completed,4th floor-80% completed.
- wall plastering
- 2nd floor – 20% completed.
- Blockwork
- 1st floor-50% completed ,2ndfloor -75% completed, 3rd-5th floor -90% completed,6th floor – 25% completed.
As per the current work status from our site, we are targeted to complete the following works by the end of APRIL 2021.
-
-
-
- RCC for slab
- 12th floor-75% to be completed
- Column work :
- 11th floor – 100% to be completed
- 12th floor-20% to be completed.
- Rcc for Retaining wall
- Base floor2-25% to be completed.
- RCC for Ramp
- Ceiling – 1st floor:- 90% to be completed
- Electrical wall chasing
- 2nd floor – 25% to be completed
- Blockwork
- 6th floor:-90% to be completed, 7th floor-30% to be completed.
- RCC for slab
-
-
Work status as on 11-03-2021, we have completed the following.
Tower 1
-
-
-
-
-
- Internal wall plastering work -up to 18th floor -100% completed, Roof-75% completed.
- Dadoing of toilets: up to 15th floor -100% completed.
- Dadoing of kitchen walls :GF – 50% completed,1st floor-13th floor-100% completed,
- Wire pulling : GF -30%,1st and 3 rd,5 th ,7 th -90%,2,4,8th -25% completed,6th,9th-15th floor-100% completed,16th floor- 50% completed.
- Water Proofing work – Upto 18th floor- 100% completed,terrace -75% completed
- External (1st coat) Putty work -at south and west -85% completed.
- External (2nd coat) Putty work -at south and west -85% completed.
- Primer – at south and west -85% completed.’
- Plumbing work – upto 17th floor- 100% completed
- Flooring and skirting ,, -GF,15th floor-25% Completed 3rd-5th ,7th,8th,11th,12thfloor:-100% completd,1st,6th,9th,10th floor -80% completed,,13th-14th floor:-50% completed.
- Fixing of door shutters -1st Floor -25%completed
- Fire Fighting work :GF-18th floor-85% completed
-
-
-
-
Tower 2
-
-
-
-
-
- RCC for slab – Upto 10th floor- 100% completed, 11th floor-60% completed.
- Ceiling plastering : BF3-90% completed
- Electrical Wall Chasing: 1st floor-4th floor- 100 % completed.
- Wall Plastering: 1st – 2nd floor-100% completed.
- Block Work
- GF -75% completed, BF2 :-70% completed, BF1-50% completed , BF3-25% completed.
- 1st floor-5th floor – 100 % completed
- Yard work
- STP RCC -100% completed.
- Front gate -100% completed.
- Compound wall-100% completed.
- MLCP
- BF1 ceiling & column plastering -100% completed.
- BF2 ceiling & column plastering -80% completed.
- BF3 ceiling & column plastering -50% completed.
-
-
-
-
As per the current work status from our site, we are targeted to complete the following works by the end of MARCH 2021.
Tower 1
-
-
-
-
-
- Internal wall plastering work -Roof-100% to be completed.
- Dadoing of toilets:16th floor -100% to be completed
- Dadoing of kitchen walls:14th floor-100% to be completed,
16th floor -100% to be completed, - Water Proofing work -floor, terrace -100% to be completed
- External (1st coat) Putty work -at north 85%to be completed.
- External (2nd coat) Putty work -.at north 85%to be completed.
- Primer – at north -85% to be completed.
- Plumbing work -18th floor-100% to be completed
- Flooring and skirting :-,14th floor- 100% to be completed, 15th floor:- 50% to be completed
GF-18th floor- 90% to be completed.
-
-
-
-
Tower 2
-
-
-
-
-
- RCC for slab -11th roof slab -100% to be completed.,12th-50% to be completed.
- Ceiling plastering
- 8th -100% to be completed
- Electrical Wall Chasing
- 5th floor :-100% to be completed.
- Wall Plastering
- 3rd floor :-100% to be completed.
- Block Work
- BF2:-100% to be completed.
- 6th floor -100% to be completed.
- Yardwork: full side retaining wall-50% to be completed.
-
-
-
-
As per the current work status from our site, we are targeted to complete the following works by the end of February 2021
-
-
-
-
-
- RCC for slab: 11th floor-100% to be completed.
- Column work: 10th floor – 100% to be completed
- Rcc for Retaining wall: Base floor2-25% to be completed.
- RCC for Ramp: BF2- 100% to be completed, BF1- 60% to be completed
- Ceiling: 9th floor:-50% to be completed
- Wall plastering: 2ndfloor – 25% to be completed
- Blockwork: 5th floor:-50% to be completed
-
-
-
-
Work status as on 09-02-2021, we have completed the following.
-
-
-
-
-
- Earthwork – 90% completed
- Pile chipping work – completed
- Pile cap work -92% completed
- RCC for slab: BF2-10th floor slab-RCC work 100% completed
- Column work : BF2 – 9 th floor -100% completed ,10th floor -45% completed, RCC for ramp, BF1,BF2 :80% completed,
- RCC for Ramp: BF2- 60% completed, BF1- 30% completed
- Ceiling Plastering: 1st floor:- 70% completed
- Ceiling Plastering (2nd floor-8th floor ):90% completed
- wall plastering: 2ndfloor – 20% completed
- Block work: 2ndfloor -3rd floor-75% completed, 4th floor -90% completed,5th floor – 10% completed.
-
-
-
-
As per the current work status from our site, we are targeted to complete the following works by the end of JANUARY 2021
RCC for slab
-
-
-
-
-
- 11th floor-100% to be completed.
-
-
-
-
Column work :
-
-
-
-
-
- 10th floor – 70% to be completed
-
-
-
-
Rcc for Retaining wall
-
-
-
-
-
- Base floor2-25% to be completed.
-
-
-
-
RCC for Ramp
-
-
-
-
-
- BF2- 100% to be completed, BF1- 30% to be completed
-
-
-
-
Ceiling
-
-
-
-
-
- 9th floor:-50% to be completed
-
-
-
-
Wall plastering
-
-
-
-
-
- 2ndfloor – 25% to be completed
-
-
-
-
Blockwork
-
-
-
-
-
- 4th floor:- 100% to be completed
-
-
-
-
Work status as on 07-01-2021, we have completed the following.
-
-
-
-
-
- Earth work – 90% completed
- Pile chipping work – completed
- Pile cap work -92% completed
-
-
-
-
RCC for slab
-
-
-
-
-
- BF2-10th floor slab -RCC work 100% completed
-
-
-
-
Column work :
-
-
-
-
-
- BF2 – 9 th floor -100% completed
- RCC for ramp, BF2 :50% completed
-
-
-
-
RCC for Ramp
-
-
-
-
-
- BF2- 60% completed, BF1- 30% completed
-
-
-
-
Ceiling
-
-
-
-
-
- Ceiling Plastering (2nd floor-8th floor ):90% completed, 1st floor:- 70% completed
-
-
-
-
wall plastering
-
-
-
-
-
- 2ndfloor – 20% completed
-
-
-
-
Block work
-
-
-
-
-
- 2ndfloor – 50% completed,3rd floor-25% to be completed, 4th floor -80% completed.
-
-
-
-
As per the current work status from our site, we are targeted to complete the following works by the end of July 2020
RCC for slab
-
-
-
-
-
- 8th floor -90% to be completed.
-
-
-
-
Column work :
-
-
-
-
-
- 8th floor -20% to be completed.
-
-
-
-
Ceiling
-
-
-
-
-
- Third floor:-100% to be completed,Fourth floor:-90% completed.
-
-
-
-
Block work
-
-
-
-
-
- Second floor:50% Completed
-
-
-
-
Work status as on June, we have completed the following.
-
-
-
-
-
- Earth work – 90% completed
- Pile chipping work – 319 nos completed (out of 323)
- Pile cap work -92% completed
-
-
-
-
RCC for slab
-
-
-
-
-
- BF2-7th floor slab -RCC work 100% completed
- 8th floor slab -RCC work 60% completed
-
-
-
-
Column work :
-
-
-
-
-
- BF2 – 6 th floor -100% completed.
- 7 th floor -85% completed .
- RCC for ramp, BF2 :35% completed
-
-
-
-
Ceiling
-
-
-
-
-
- Ceiling Plastering (2nd floor ):90% completed (3rd floor); 90% completed, forth floor :- 35% completed.
-
-
-
-
Block work
-
-
-
-
-
- Second floor:10% Completed
-
-
-
-
As per the current work status from our site, we are targeted to complete the following works by the end of March 2020
-
-
-
-
-
- Rcc for slab upto 8th floor -100% to be completed.
- Column work : 7th-100% to be completed, 8th floor – 30% to be completed
- Ceiling: Second floor :100% to be completed, Third floor;100% to be completed.
- Block work: Second floor:50% to be Completed
-
-
-
-
Work status as on 11-03-2020, we have completed the following.
-
-
-
-
-
- Piling work – 100% completed
- Earth work – 90% completed
- Pile chipping work – 319 nos completed (out of 323)
- Pile cap work -92% completed
- RCC for slab – BF1-6th floor slab -RCC work 100% completed, 7th floor slab -RCC work 90% completed
- Column work: 6th floor -100% completed, 7th floor -40% completed, RCC for ramp, BF2 :35% completed
- Ceiling Plastering (2nd floor ):90% completed (3rd floor); 70% completed
- Block work: Second floor:10% Completed
-
-
-
-
As per the current work status from our site, we are targeted to complete the following works by the end of February 2020
-
-
-
-
-
- Rcc for slab 7th 100% to be completed.
- Column work : 6th-100% to be completed, 7th 30% to be completed, Base floor 2 : 35% to be completed
- Ceiling: Second floor: 100% to be completed, Third floor: 70% to be completed
- Block work (2ndfloor): 50% to be Completed
-
-
-
-
Work status as on 08-02-2020, we have completed the following.
-
-
-
-
-
- Piling work – 100% completed
- Earth work – 90% completed
- Pile chipping work – 319 nos completed (out of 323)
- Pile cap work -66nos completed (out of 72)
- RCC for slab – BF2 slab – 100%completed.
- BF1-6th floor slab -RCC work 100% completed
- Column work: 6th -45% completed.
- RCC for ramb, BF2 :15% Completed
- Ceiling Plastering (2nd floor ): 90% completed, (3rd floor): 20% completed
- Block work (2nd floor): 10% Completed
-
-
-
-
As per the current work status from our site, we are targeted to complete the following works by the end of JANUARY 2020
-
-
-
-
-
- 6th floor slab -100% to be completed.
- Column work : 5 th -6 th -100%,6-7 th -25% to be completed
- Block work (2 ndfloor):25% to be Completed
-
-
-
-
Work status as on 10-01-2020, we have completed the following.
-
-
-
-
-
- Piling work – 100% completed
- Earth work – 90% completed
- Pile chipping work – 319 nos completed (out of 323)
- Pile cap work -66nos completed (out of 72)
- RCC for slab – BF2 slab – 100%completed.
- BF1-5 th floor slab -RCC work 100% completed
- 6 th floor -60% completd.
- Column work : 5-6 th -75% completed .
- Ceiling Plastering (2nd floor ): 50% completed
- Block work (2nd floor): 10% Completed
-
-
-
-
As per the current work status from our site we are targeted to complete the following works by end of September 2019
-
-
-
-
-
- 5 th floor slab -45% to be completed,6 th floor slab -30% to be completed .
- Third floor Column work-80% completed, 4 th floor column work -45% completed,5 th floor -25% to be completed.
-
-
-
-
Work status as on 05.09.2019, we have completed the following
-
-
-
-
-
- Piling work – 100% completed
- Earth work – 90% completed
- Pile chipping work – 319 nos completed (out of 323)
- Pile cap work -66nos completed (out of 72)
- RCC for slab – BF2 slab – 100%completed.
- BF1 slab -RCC work 100% completed
- Ground floor slabs -RCC Work100%completed.
- First floor slab -100%completed
- Second floor slab -100% completed
- Third floor slab -100% completed 4th floor -45% completed 5 th -30% completed
- BF2- 1st floor Column Rcc work -100% completed,Second floor Column work – 100% completed
- Third floor Column work-51% completed, 4 th floor column work -37% completed,5 th floor -25% completed.
-
-
-
-
As per the current work status from our site we are targeted to complete the following works by end of August 2019
-
-
-
-
-
- Third floor slab -100% ,4 th floor slab -60%,5 th floor slab -45% to be completed.
- Fourth floor Column work-40% to be completed,5 th floor column work -25% to be completed
-
-
-
-
Work status as on 05.09.2019, we have completed the following
-
-
-
-
-
- Piling work – 100% completed
- Earth work – 90% completed
- Pile chipping work – 319 nos completed (out of 323)
- Pile cap work -66nos completed (out of 72)
- RCC for slab – BF2 slab – 100%completed.
- BF1 slab -RCC work 100% completed
- Ground floor slabs -RCC Work100%completed.
- First floor slab -100%completed
- Second floor slab -100% completed
- Third floor slab -75% completed, 4th floor -45% completed, 5th -30% completed
- BF2- 1st floor Column Rcc work -100% completed,Second floor Column work – 100% completed
- Third floor Column work-42% completed, 4 th floor column work -36% completed.
-
-
-
-
As per the current work status from our site we are targeted to complete the following works by end of July 2019
-
-
-
-
-
- Third floor slab -100% ,4 th floor slab -45%,5 th floor slab -30% to be completed.
- Second floor Column work -100% to be completed
- Fourth floor Column work-40% to be completed
-
-
-
-
Work status as on 06.07.2019, we have completed the following
-
-
-
-
-
- Piling work – 100% completed
- Earth work – 90% completed
- Pile chipping work – 319 nos completed (out of 323)
- Pile cap work -66nos completed (out of 72)
- RCC for slab – BF2 slab – 100%completed.
- BF1 slab -RCC work 100% completed
- Ground floor slabs -RCC Work100%completed.
- First floor slab -100%completed
- Second floor slab -100% completed
- Third floor slab -60% completed,4th floor -30% completed
- BF2- 1st floor Column Rcc work -100% completed
- Second floor Column work – 95% completed
- Third floor Column work-42% completed, 4 th floor column work -10% to be completed.
-
-
-
-
As per the current work status from our site we are targeted to complete the following works by end of June 2019
-
-
-
-
-
- Pile chipping work -321 nos to be completed
- Third floor slab -100% to be completed
- Second floor Column work -100% to be completed
- Third floor Column work-40% to be completed
- Retaining wall -10% to be completed
-
-
-
-
Work status as on 06.06.2019, we have completed the following
-
-
-
-
-
- Piling work – 100% completed
- Earth work – 90% completed
- Pile chipping work – 319 nos completed (out of 323)
- Pile cap work -66nos completed (out of 72)
- RCC for slab – BF2 slab – 100%completed.
- BF1 slab -RCC work 100% completed
- Ground floor slabs -RCC Work100%completed.
- First floor slab -100%completed
- Second floor slab -100% completed
- Third floor slab -45% completed
- BF2- 1st floor Column Rcc work -100% completed
- Second floor Column work – 84% completed
- Third floor Column work-24% completed
-
-
-
-
As per the current work status from our site we are targeted to complete the following works by end of May 2019
-
-
-
-
-
- Pile chipping work -321 nos to be completed
- Pile cap work – 68 to be completed (out of 72)
- Second floor slab -100% tobe completed
- Third floor slab -45% to be completed
- Second floor Column work – 70% completed
-
-
-
-
Work status as on 06.05.2019, we have completed the following
-
-
-
-
-
- Piling work – 100% completed
- Earth work – 90% completed
- Pile chipping work – 319 nos completed (out of 323)
- Pile cap work -66nos completed (out of 72)
- RCC for slab – BF2 slab – 100%completed.
- BF1 slab -RCC work 100% completed
- Ground floor slabs -RCC Work100%completed.
- First floor slab -100%completed
- Second floor slab -90% completed
- Third floor slab -30% completed
- BF2- 1st floor Column Rcc work -100% completed
- Second floor Column work – 53.50% completed
- Third floor Column work-15% completed
-
-
-
-
As per the current work status from our site we are targeted to complete the following works by end of April 2019
-
-
-
-
-
- Pile chipping work -321 nos to be completed
- Pile cap work – 68 to be completed (out of 72)
- Second floor column work -40% completed
- Second floor roof slab -40% to be completed
-
-
-
-
Work status as on 05.04.2019, we have completed the following
-
-
-
-
-
- Piling work – 100% completed
- Earth work – 90% completed
- Pile chipping work – 319 nos completed (out of 323)
- Pile cap work -66nos completed (out of 72)
- Grade slab work – 100% completed
- RCC for slab – BF2 roof slab – 100%completed.
- BF1roof slab -RCC work 100% completed
- Ground floor roof slabs -RCC Work100%completed.
- First floor roof slab -100%completed
- BF1 Column Rcc work -100% completed
- GF Column work – 100% completed
- First Floor Column work-100% completed
- Second floor column work -20% completed
- Second floor roof slab -20%completed
-
-
-
-
As per the current work status from our site we are targeted to complete the following works by end of March 2019
-
-
-
-
-
- Second floor roof slab -40% to be completed
- Pile chipping work -321 nos to be completed
- Pile cap work – 100% to be completed (out of 72)
-
-
-
-
Work status as on 06-03-2019, we have completed the following
-
-
-
-
-
- Piling work – 100% completed
- Earth work – 90% completed
- Pile chipping work – 319 nos completed (out of 323)
- Pile cap work – 69 nos completed (out of 72)
- Grade slab work – 100% completed
- RCC for slab – BF2 roof slab – 100%completed.
- BF1 roof slab -RCC work 100% completed
- Ground floor roof slabs -RCC Work 100%completed.
- First floor roof slab -100%completed
- Rear Portion Transfer Slab -100% completed
- BF1 Column Rcc work -100% completed
- GF Column work – 100% completed
- First Floor Column work-100% completed
- Second floor roof slab -20%completed
-
-
-
-
As per the current work status from our site we are targeted to complete the following works by end of February 2019
-
-
-
-
-
- Pile chipping work – 100% to be completed
- Pile cap work – 100% to be completed (out of 72)
- Rear Portion Transfer Slab -100% to be completed
- Second floor roof slab -40% to be completed
-
-
-
-
Work status as on 05-02-2019, we have completed the following
-
-
-
-
-
- Piling work – 100% completed
- Earth work – 90% completed
- Pile chipping work – 317 nos completed (out of 323)
- Pile cap work – 69nos completed (out of 72)
- Grade slab work – 100% completed
- RCC for slab – BF2 roof slab – 100%completed.
- BF1 roof slab -RCC work 100% completed
- Ground floor roof slabs -RCC Work100%completed.
- First floor roof slab -100%completed
- Rear Portion Transfer Slab -90% completed
- BF1 Column Rcc work -100% completed
- GF Column work – 100% completed
- First Floor Column work-100% completed
- Second floor roof slab -20%completed
-
-
-
-
As per the current work status from our site we are targeted to complete the following works by end of January 2019
-
-
-
-
-
- Earth work – 100% to be completed
- Pile cap work – 67 nos to be completed (out of 72)
- Rear Portion Transfer Slab -100% to be completed
-
-
-
-
Work status as on 08-01-2019, we have completed the following
-
-
-
-
-
- Piling work – 100% completed
- Earth work – 90% completed
- Pile chipping work – 317 nos completed (out of 323)
- Pile cap work – 66 nos completed (out of 72)
- Grade slab work – 100% completed
- RCC for slab – BF2 roof slab – 100%completed.
- BF1roof slab -RCC work 100% completed
- Ground floor roof slabs -RCC Work100%completed.
- First floor roof slab -60%completed
- Rear Portion Transfer Slab -50% completed
- BF1 Column Rcc work -100% completed
- GF Column work – 100% completed
- First Floor Column work-60% completed
-
-
-
-
As per the current work status from our site we are targeted to complete the following works by end of December 2019
-
-
-
-
-
- Earth work – 100% to be completed
- Pile cap work – 67 nos to be completed (out of 72)
- First floor roof slab (A flat portion)-100% to be completed
- Rear Portion Transfer slab -100% to be completed.
- GF Column work – 100% to be completed
-
-
-
-
Work status as on 06-12-2018, we have completed the following
-
-
-
-
-
- Piling work – 100% completed
- Earth work – 90% completed
- Pile chipping work – 317 nos completed (out of 323)
- Pile cap work – 66 nos completed (out of 72)
- Grade slab work – 100% completed
- RCC for slab – BF2 roof slab – 100%completed.
- Ground floor slab RCC Work-100%completed.
- BF1 Column Rcc work -100% completed
- BF1 roof slab work – 100% completed
- GF Column work – 85% completed
- First Floor Column work-10% completed
-
-
-
-
As per the current work status from our site we are targeted to complete the following works by end of November 2018
-
-
-
-
-
- Earth work – 100% to be completed
- Pile cap work – 67 nos to be completed (out of 72)
- Grade slab work – 100% to be completed
- RCC for slab – BF2 roof slab – 100% to be completed
- B1 Column Rcc work – 100% to be completed
- BF1 roof slab work – 100% to be completed
- GF Column work – 50% to be completed
- GF Slab RCC work – 50% to be completed
-
-
-
-
Work status as on 16-11-2018, we have completed the following
-
-
-
-
-
- Piling work – 100% completed
- Earth work – 90% completed
- Pile chipping work – 317 nos completed (out of 323)
- Pile cap work – 66 nos completed (out of 72)
- Grade slab work – 94% completed
- RCC for slab – BF2 roof slab – 90% completed
- BF1 Column Rcc work – 95% completed
- BF1 roof slab work – 95% completed
- GF Column work – 25% completed
- GF Slab RCC work – 10% completed
-
-
-
-
As per the current work status from our site we are targeted to complete the following works by end of May 2018
-
-
-
-
-
- Earth work – 100% to be completed
- Pile chipping work – 315nos to be completed (out of 323)
- Pile cap work – 66 nos to be completed (out of 72)
- Grade slab work – 100% to be completed
- RCC for slab – BF- 30% to be completed
-
-
-
-
We are pleased to inform you the current work progress at our site Artech “RAINFOREST”, Jawahar nagar Trivandrum. Few snaps of the work progress attached for your reference.
-
-
-
-
-
- Piling work – 100% completed
- Earth work – 85% completed
- Pile chipping work – 295 nos completed (out of 323)
- Grade slab work – 80% completed
- RCC for slab – BF roof slab – 15% completed
-
-
-
-
As per the current work status from our site we are targeted to complete the following works by end of April 2018
-
-
-
-
-
- Earth work – 100% to be completed
- Pile chipping work – 310 nos to be completed (out of 323)
- Pile cap work – 65 nos to be completed (out of 72)
- Grade slab work – 100% to be completed
- RCC for slab – BF- 20% to be completed
-
-
-
-
Work status as on 16-04-2018, we have completed the following.
-
-
-
-
-
- Piling work – 100% completed
- Earth work – 75% completed
- Pile chipping work – 270 nos completed (out of 323)
- Pile cap work – 54 nos completed (out of 72)
- Grade slab work – 60% completed
- RCC for slab – BF roof slab – progressing
-
-
-
-
As per the current work status from our site we are targeted to complete the following works by end of March 2018
-
-
-
-
-
- Earth work – 100% to be completed
- Pile chipping work – 280 nos to be completed (out of 323)
- Pile cap work – 45 nos to be completed (out of 72)
- Grade slab work – 100% to be completed
- Piling work -134 to be completed (out of 174)
-
-
-
-
Work status as on 10-03-2018, we have completed the following.
-
-
-
-
-
- Piling work – 100% completed
- Earth work – 70% completed
- Pile chipping work – 240 nos completed (out of 323)
- Pile cap work – 39 nos completed (out of 72)
- Grade slab work – 40% completed
-
-
-
-
As per the current work progress from our site we are progressing with the same and will complete it by the end of February 2018
-
-
-
-
-
- Earth work – 60% to be completed
- Pile chipping work – 234 nos to be completed (out of 323)
- Pile cap work – 37 nos to be completed (out of 72)
- Piling work -107 to be completed (out of 174)
-
-
-
-
Work status as on 09-02-2018, we have completed the following.
-
-
-
-
-
- Piling work – 100% completed
- Earth work – 55% completed
- Pile chipping work – 210 nos completed (out of 323)
- Pile cap work – 31 nos completed (out of 72)
-
-
-
-
Work status as on 5-7-2017, we have completed.
-
-
-
-
-
- Piling work – progressing
-
-
-
-
As per the current work progress from our site we are progressing with the same and will complete it by the end of JULY, 2017
Work status as on 9-5-2017, we have completed.