Artech Empire - Progress
Work status as on 08-01-2019, we have completed the following
- RCC for Structure – 100% completed
- Ceiling Plastering work – 100% completed
- Block/Brick masonry work – 100% completed
- Wall plastering work – 100% completed
- Aluminium Windows and Ventilators – 100% completed
- Grill making & fixing – 100% completed
- Electrical HT work – 100% completed
- Wire pulling – 100% completed
- 1st coat painting work – 100% completed
- 2nd coat painting work – 100% completed
- External plastering work – 100% completed
- CP sanitary fixing work – 100% completed
- Yard work – 100% completed
As per the current work status from our site we are targeted to complete the following works by end of December 2019
- Yard work – 100% to be completed
Work status as on 06-12-2018, we have completed the following
- RCC for Structure – 100% completed
- Ceiling Plastering work – 100% completed
- Block/Brick masonry work – 100% completed
- Wall plastering work – 100% completed
- Aluminium Windows and Ventilators – 100% completed
- Grill making & fixing – 100% completed
- Electrical HT work – 100% completed
- Wire pulling – 100% completed
- 1st coat painting work – 100% completed
- 2nd coat painting work – 100% completed
- External plastering work – 100% completed
- CP sanitary fixing work – 100% completed
- Yard work – 95% completed